That the April to May 2010 Revenue spend financial monitoring report and associated forecasts in terms of the outturn position 2010/11 be noted. That quarterly reports continue to be submitted to Members for consideration, in line with the Forward Plan.
Word for word from the decision Durham published for this meeting.Source: democracy.durham.gov.uk
Financial Monitoring Report – Position at 31/5/10, with Projected Outturn at 31/03/11
Joint Report of Terry Collins – Corporate Director: Neighbourhood Services; Stuart Crowe – Corporate Director: Resources
Purpose of the Report 1. The purpose of this report is to set out details of income and expenditure in the period 1 April to 31 may 2010, with a projection of the anticipated outturn to 31 March 2011, highlighting areas of over / underspend against the revenue budgets at a service expenditure analysis level.
2. The report also sets out details of the funds and reserves of the Joint Committee at 1 April 2010 and estimated position at 31 March 2011, taking into account the forecast financial outturn.
Background 3. Prior to Local Government Reorganisation the Crematorium’s budget was held within Derwentside District Council’s General Services budget area and was monitored as part of the Authority’s monthly budgetary control process. However, as the Crematorium Committee has, in the past, only met 2-3 times a year, budget reports were generally only presented to members at the year-end.
4. The 2008-09 external audit “issues arising” letter recommends that, in order to improve financial governance, regular budgetary control reports are presented to Members of the Joint Committee, on at least a quarterly basis. Members will note that the Treasurer’s forward plan and suggested meeting schedule considered earlier has incorporated quarterly financial monitoring reporting.
Financial Performance 5. In terms of this budgetary control report, the year to date actual position has been extracted directly from the general ledger in Oracle, through which all former County Council transactions are processed.
6. As members may be aware, the former District Council financial management systems continue to be used for accounts payable and accounts receivable transactions. All these transactions are interfaced into Oracle on a daily basis, in accordance with mapping work undertaken in March, which effectively replicated the District cost centres within Oracle. All payroll costs are processed via the County Council’s Northgate Resourcelink System and is interfaced directly into Oracle.
Page 1 of 4 7. Budgetary control reports, incorporating outturn projections, are considered by Neighbourhood Services’ Management Team on a monthly basis. The County Councils Corporate Management Team also considers monthly budgetary control reports, with quarterly reports being considered by Cabinet / Scrutiny Committee. The year to date and outturn projections for the Mountsett Crematorium are included within these reports.
8. The projections have been calculated using income and expenditure for the year to date, consideration of expenditure patterns in previous years and information supplied by the Superintendant Registrar. The following table highlights the year to date actual and projected outturn financial performance.
Original Base Year to Date Probable Variance Budget Actual Outturn Over/ Subjective Analysis 2010/11 (Apr-May) 2010/11 (Under) £ £ £ £ Employees 115,615 20,916 114,515 (1,100) Premises 119,100 (5,248) 119,100 0 Transport 300 0 300 0 Supplies & Services 68,250 1,629 68,250 0 Agency & Contracted 17,415 0 17,415 0 Transfer Payments 0 0 0 0 Capital Charges 0 0 0 0 Central Support Costs 8,330 0 8330 0 Gross Expenditure 329,010 17,297 327,910 (1,100)
Income (573,900) (46,044) (573,900) 0
Net Income (244,890) (28,747) (245,990) (1,100) Transfer to Reserves - Repairs Reserve 15,000 0 15,000 0 - Cremator Reserve 65,000 0 66,100 1,100 Distributable Surplus (164,890) 0 164,890 0 35% to Gateshead 57,712 0 57,712 0 65% to Durham County 107,178 0 107,178 0
Balance @ Mountsett Transfers to Transfers Balance @ 31 March Crematorium Reserve From Reserve 31 March 2009 2010 Earmarked Reserves £ £ £ £ Cremator Replacement (160,412) (66,100) 0 (226,512) Reserve
Major Repairs Reserve (37,547) (15,000) 0 (52,547)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Provision of Support Services 2026-27That the Service Level Agreement attached at Appendix 2 (including the relevant schedule) for the year 2026/27 be app...
Revenue Budget 2026-27 MountsettResolved : That the budget proposals contained within the report (as set out at Appendix 2) and that the forecast lev...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.