Resolved
(i) That the budget proposals as outlined within the report be noted and approved. (ii) That the forecasted level of reserves and balances at 31 March 2014 be noted.
Mountsett Crematorium Joint Committee noted this item on Thursday 31 January 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
(i) That the budget proposals as outlined within the report be noted and approved. (ii) That the forecasted level of reserves and balances at 31 March 2014 be noted.
1. The purpose of this report is to set out for members’ consideration proposals with regards to the 2013/14 revenue budget for the Mountsett Crematorium.
Background Information
2. The 2013/14 budget has been developed with the Bereavement Services Manager, taking into account the proposed Fees and Charges set out in the previous report, the 2012/13 forecast outturn position and known expenditure pressures in the coming year.
Budget Proposals 2013/14
3. The proposed 2013/14 revenue budget is shown at Appendix 2, together with the forecast position with regards to the reserves of the Mountsett Crematorium. Members should note that the main changes from the 2012/13 budget are as follows:
Employees 4. The 2013/14 budget has reduced slightly by (£849). As a result of the Single Status exercise undertaken at Durham County Council, the grades, terms and conditions have increased the salary of the Crematorium Superintendent and Registrar post. This is however offset charges to the Part III terms and conditions of other crematorium staff. A 1% pay award has also been factored into the 2013/14 budget.
5. The budget considers the current vacancy of the Superintendent and Registrar. Options are currently being considered regarding this post (as reported in the Bereavement Services Manager’s report considered earlier in the agenda). Following consideration at the future meeting, any budget revisions will be considered and reported.
Premises
6. The base budget has increased by £108,871 from 2012/13.This is due to a number of factors, detailed below:- • The Repairs and maintenance budgets have increased by £96,000 in consideration of the works required and highlighted in the Service Asset Management Plan presented and approved by members at the September 2012 meeting. These requirements will be one – off items for the 2013/14 budget. • The Cremator Reline budget has been increased by £4,000 in line with the requirements of the Service Asset Management Plan.
• Utility Budgets and the NNDR Budget have been increased to reflect the impact of inflation and the 2012/13 provisional outturn – This has resulted in an overall increase of £8,871. Supplies and Services 7. Provision has been made within the Supplies and Services budget for the Cremation Abatement of Mercury Emissions Organisation (CAMEO) Scheme – Mercury Abatement charges. Whilst an exact charge has not been communicated by CAMEO, the budget has been set on the basis of a £50 charge against 50% of budgeted cremations. This has resulted in an overall increase of £24,000 from the 2012/13 budget base
Agency and Contracted The Agency and Contracted Services budget has reduced by a net (£1,000). • The Independent Testing of Cremators budget has increased by £500 in line with actual charges received in 2012/13 • The budget for the registration with the FSA in 2012/13 is no required in 2013/14 resulting in a saving of (£1500).
Central Support Costs 8. The 2013/14 budget factors in the proposed SLA for the provision of Support Service. As members will be aware from the previous report, the proposals are to increase this charge by £1,800.
Income 9. The 2013/14 budget factors in the budgetary impact of applying the increases in fees and charges proposed in the fees and charges report considered earlier. As members will be aware, the proposals are to:-
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2013/14 Revenue BudgetReport | 133 KB | DownloadRead as text |
PDF |
Item9 31.3.13 Revenue Budget 2013-14: Appendix 2Appendix | 22 KB | Download |
Follow Mountsett Crematorium Joint Committee at Durham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jan 2026 | Quarterly Performance and Operational ReportResolved That the Committee: - i) Noted the current performance of the crematorium. ii) Noted the current staffing si... | Noted | Open |
| 30 Jan 2026 | Financial Monitoring ReportThat the April to December 2025 financial monitoring report and associated provisional outturn position as at 31 Marc... | Noted | Open |
| 30 Jan 2026 | Provision of Support Services 2026-27That the Service Level Agreement attached at Appendix 2 (including the relevant schedule) for the year 2026/27 be app... | Agreed | Open |
| 30 Jan 2026 | Fees and Charges 2026/27i) It is recommended that members of the Joint Committee note and approve the proposed fees and charges at Appendix 2... | Approved | Open |
| 30 Jan 2026 | Revenue Budget 2026-27 MountsettResolved : That the budget proposals contained within the report (as set out at Appendix 2) and that the forecast lev... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.