Communications Update

Decided Committee 1 paper

AI summaryBishop Auckland Stronger Towns Board agrees one final double edition of the programme newsletter and reallocates £2,500 to wider marketing activity.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedOne final double edition planned, £2,500 reallocated to marketing
Money£2,500 reallocatedFreed from newsletter costs into marketing budget
What happens nextPlan final double editionTo be published at appropriate time near programme end
Who it affectsNewsletter and town marketingBishop Auckland residents, businesses and visitors

What was decided

One final double edition of the newsletter will be planned for an appropriate time towards the end of the programme.

Around £2,500 will be reallocated from the newsletter budget to wider marketing activity. Report P12

Why

The budget previously allocated for the newsletter has run out, so future editions must come from the Stronger Towns Board marketing budget. Report P11

Publishing one double edition instead of two separate issues is expected to save about £2,500 through reduced distribution costs, freeing money for wider marketing. Report P12

What happens next

Plan and publish the final double edition at an appropriate time towards the end of the Stronger Towns programme. Report P12

Reallocate around £2,500 into the wider marketing activity budget. Report P12

Encourage partners to send positive news to the council contact for the Bishop Regeneration website. Report P22

The money

  • £2,500 Reallocated to the marketing budget from the newsletter Report P12
  • approximately £5,000 Set aside for two more editions of the newsletter Report P11
  • £30,000 Budget for physical marketing activity around the town Report P14
  • £8,500 Awarded to PeaceGold from the Property Reuse Fund Report P10

Options considered

  • Rejected: Reduce newsletter frequency to six monthly (two more editions in July and November). Would not free up the additional £2,500 for wider marketing that a single double edition would release through reduced distribution costs Report P11, P12
  • Chosen: Publish one final double edition of the newsletter at an appropriate time. Provides a full update on remaining funding and frees around £2,500 for wider marketing activity Report P12

Implications

  • Financial: Around £2,500 is freed from newsletter production for wider marketing activity, while £5,000 remains allocated within the marketing budget for the final double edition. Report P11, P12
  • Other: Physical marketing assets including digital display screens, bus shelter ad shells, lamppost graphics and Market Place hotel hoardings are due to be visible around the town by May. Report P15, P16

Who and where

  • Residents, businesses and visitors to Bishop Auckland who see the town's marketing and read the newsletter Report P10, P16
  • Stronger Towns Board partners asked to share positive news through the council contact Report P22
  • Members of the public attending the Strategic Advisory Panel Report P18, P20

Timeline

  • 30 March: Issue 19 of the Bishop newsletter to be published and distributed Report P9
  • 28 January: First meeting of the new-style Strategic Advisory Panel took place, with more than 20 attending Report P18
  • 15 April: Next Strategic Advisory Panel meeting scheduled Report P5, P20
  • April: Bishop Auckland Bus Station opening featured in newsletter Report P10
  • May: Physical marketing assets to be in place and visible around the town Report P16
  • July and November: Originally planned quarterly publication dates for two further newsletter editions before the decision to switch to one final double edition Report P11

Plain English for the jargon

  • STB: Stronger Towns Board, the Bishop Auckland body taking this decision
  • SAP: Strategic Advisory Panel, the board's public engagement meeting
  • ST and FHS funds: Stronger Towns and Future High Streets funding streams supporting the programme
  • TAP: The Auckland Project, awarded Accredited Museum Status by Arts Council England
  • Property Reuse Fund: Stronger Towns fund supporting new uses of town centre property, including the PeaceGold award
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

Resolved That one final double edition of the newsletter be planned for an appropriate time towards the end of the programme and £2,500 be reallocated to the marketing budget.
Word for word from the decision Durham published for this meeting. Source: democracy.durham.gov.uk

Follow this further

Built from Durham's papers

What the report saysPro

Report to Bishop Auckland Stronger Town Board

Bishop Auckland Stronger Towns Board Communications Update 2 April 2026

This report provides an overview of current communications activity linked to the Stronger Towns programme.

1. Recent communications and engagement activity

New board members – press release issued to media, posted on Bishop Regeneration and partner websites and shared via partner social media channels. Video featuring a short clip of each new member introducing themselves also shared.

Strategic Advisory Panel – social media post issued before January meeting to encourage attendance and afterwards talking about a positive session having taken place. Posts to be scheduled to promote next meeting on 15 April.

100 Portraits of Bishop Auckland exhibition – story about call-out for artists linked to Artists’ Hub added to Bishop Regeneration website.

TAP awarded Accredited Museum Status by ACE – added to Bishop Regeneration website.

2. Newsletter

Issue 19 of the Bishop newsletter to be published/distributed on 30 March. Content includes:

• Bishop Auckland Bus Station – photo feature offering first look inside the new facility ahead of opening in April. • Property Reuse Fund – focus on ethical jeweller PeaceGold, which was awarded £8,500 to expand into neighbouring retail unit. • Project updates – new STB board members, new format of Strategic Advisory Panel, construction to start on Market Place hotel. • What’s On – Tom McGuinness Out of the Darkness at Bishop Auckland Food Festival; All My Sons at Bishop Auckland Town Hall; One Hundred Portraits of Bishop Auckland at the Artists’ Hub. • Timeline – format to be reviewed ahead of next edition.

Budget – It had previously been agreed that the newsletter would cease once all money from the ST and FHS funds had been handed over. However, the budget allocated for the newsletter has now run out. Futures editions will, therefore, need to be funded from the STB allocated marketing budget. Funding of approximately £5,000 has set aside for two more editions. Working to the current quarterly schedule, these should be published in July and November.

Recommendation – To ensure that these two final magazines provide full and thorough updates on the remainder of the funding, it is proposed that frequency is reduced to six monthly or alternatively, one final ‘double edition’ is published at an appropriate time. This second option would free up an additional amount of around £2,500 for wider marketing activity due to reduced distribution costs.

3. Marketing Plan

A plan for the £30,000 budget for physical marketing activity around the town, excluding the £5,000 currently allocated for the newsletter design, print and distribution, has now been agreed using the following platforms:

• Digital display screens at the new Bishop Auckland Bus Station • Outdoor digital display screens at Asda and Tesco Bishop Auckland, Bishop Auckland Football Club and 2 x screens on Newgate Street • Ad shells on bus shelters • Lamppost graphics • Brand hoardings – to include the hoardings around the Market Place hotel

Design of the artwork is currently underway, with the above assets due to be in place and visible around the town by May, helping residents, businesses and visitors see the progress being made in the town and strengthening confidence in the regeneration programme.

4. Strategic Advisory Panel

The first meeting of the new style Strategic Advisory Panel (SAP) took place on Wednesday, 28 January. Social media messages were issued in advance offering an ‘open invitation’ to anyone who wished to attend but requiring them to register in advance. More than 20 people were in attendance. Updates were provided on ST and FHS projects and the public were given the opportunity to ask questions. The meeting highlighted that communication with residents had clearly been an issue, but feedback from the session was positive.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Communications UpdateReport 163 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 13 attended
KA
Councillor Karen AllisonCommittee Member, present
TH
Tony HansonOfficer, present
PH
Phil HarnbyCommittee Member, present
SH
Shaun HopeChair, present
RD
Revd Dr Chris KnightsCommittee Member, present
JR
Jane RufferCommittee Member, present
JR
Jonathan RufferCommittee Member, apologies
SR
Sam RushworthCommittee Member, present
JS
Jack ShortCommittee Member, present
BS
Brian SuttonCommittee Member, present
NW
Nik WelshCommittee Member, present
RY
Rob YorkeCommittee Member, apologies

All 13 on the meeting page

On this subject at Durham

Search all
  1. Communications UpdateThis decision
  2. Project Communication Information / Branding Discussion - Julie Barnfather, Communications, Marketing and Design Strategic ManagerApproved
  3. Communications ReviewNoted
  4. CommunicationsNoted
  5. Communications ReviewNoted
  6. Pension Fund Communications - Verbal UpdateNoted

More from Durham Bishop Auckland Stronger Town Board

All decisions
MeetingDecisionOutcome
9 Dec 2024 Governance ReviewResolved That the content of the Bishop Auckland Town Board Governance Stocktake be noted and an implementation plan ... Noted Open
9 Dec 2024 CommunicationsResolved That the update be noted. Noted Open
9 Dec 2024 Programme Update - DCC/Project SponsorsResolved That the presentation be noted. Noted Open
30 Aug 2024 Programme Update - DCC / Project SponsorsIt was agreed that the Chair would be notified on submission of the Subsidy Control letter. Bishop Gateway (Formally ... Agreed Open
30 Aug 2024 Town Centre Diversification - Public Realm and PRF2Resolved That the following recommendations be approved; a) That the report be noted b) That £1,200,000 funding from ... Approved Open