that 1. East Devon District Council take the transfer of a plot of serviced land at the Ingram’s sports hub in Cranbrook and procure and project manage the delivery of a sports pavilion at the sports hub (to a design to be agreed with Cranbrook Town Council) using identified Section 106 monies and external funding. 2. Delegated authority be given to the Deputy Chief Executive, in consultation with the Strategic Leads for Governance and Licensing and Finance, to carry out appropriate due diligence, agree satisfactory heads of terms with relevant parties, secure external funding and thereafter to progress the transfer of the land, delivery of the project and transfer of the completed sports pavilion to Cranbrook Town Council, upon practical completion of the building. REASON: East Devon District Council was best placed to bring together a number of different funding streams and to coordinate and manage the final design, procurement and delivery of an important asset for the town of Cranbrook. To ensure that the asset was managed by and for the town, it needed to be subsequently transferred to the Town Council upon practical completion. Whilst facilitating the delivery of the Pavilion, East Devon District Council did not wish to incur liabilities beyond the practical completion stage.
Word for word from the decision East Devon published for this meeting.Source: democracy.eastdevon.gov.uk
Report to: Cabinet Date of Meeting: 27 November 2019 Public Document: Yes Exemption: None
Review date for None release
Subject: Cranbrook Sports Pavilion
Purpose of report: To seek authority for the project management of the Cranbrook sports pavilion
Recommendation: That Cabinet agree to: 1. East Devon District Council taking the transfer of a plot of serviced land at the Ingram’s sports hub in Cranbrook and procuring and project managing the delivery of a sports pavilion at the sports hub (to a design to be agreed with Cranbrook Town Council) using identified Section 106 monies and external funding.
2. Delegated authority being given to the Deputy Chief Executive, in consultation with the Strategic Leads for Governance and Licensing and Finance, to carry out appropriate due diligence, agree satisfactory heads of terms with relevant parties, secure external funding and thereafter to progress the transfer of the land, delivery of the project and transfer of the completed sports pavilion to Cranbrook Town Council upon practical completion of the building.
Reason for East Devon District Council is best placed to bring recommendation: together a number of different funding streams and to coordinate and manage the final design, procurement and delivery of an important asset for the town of Cranbrook To ensure that the asset is managed by and for the town, it needs to be subsequently transferred to the Town Council upon practical completion. Whilst facilitating the delivery of the Pavilion, East Devon District Council do not wish to incur liabilities beyond the practical completion stage. Officer: James Brown Cranbrook New Community Manager [email protected] 01395 517572 Financial Risks have been highlighted within the report along with implications: mitigating actions and funding streams identified. Previous examples of transferring assets to Town Councils shows this can be complex and time consuming with no budget provision available. Legal implications: The approach of taking land, obtaining funding, procuring the construction of the sports pavilion and transferring the building to the Town Council upon completion is permissible legally. The project when broken down into constituent parts – conveying land, securing external funding and procuring construction and project management of the build - will have legal implications which cannot be addressed in this report. Each individual item will be subject to legal input to ensure a lawful approach to the various transactions / activities. However, there is a need to ensure that the Council’s interests are appropriately protected through due diligence and agreements with other parties and the delegation to the Deputy Chief Executive facilitates this occurring and for the project to then progress Equalities impact: Low Impact To meet the FA, ECB and Sport England requirements adequate provision must be given to accessibility to the new building (and rooms inside) as well as in making suitable provision and separate changing and toilet facilities for both men and women, teams and officials. Climate change: Medium Impact
While every effort will be made in the design and procurement of the building to ensure that it is efficiently designed, made from sustainable material, minimises water use and is energy efficient to run, these attributes will need to be balanced against the costs of procurement. There is a maximum budget within which the building must be delivered and therefore a balance will need to be struck between its sustainability and the size/specification of the building.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.