New Feniton Flood Alleviation Scheme

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 21 July 2020. Below is the council's own wording, with the papers it was decided on.

Item188

Resolved

RESOLVED that Cabinet: 1. confirm the decision to postpone the delivery of Phase 3 of the flood alleviation scheme (being the newly proposed October 2020 undertrack crossing) until the whole project including phase 4 is fully funded, on the basis of an emerging cost basis contract subject to the Environment Agency confirming the availability of the additional funding as detailed in the report, 2. delegate authority to the Strategic Lead (Housing, Health and Environment) in consultation with the Strategic Lead (Governance and Licensing) to negotiate and enter into the emerging costs basis contract with Network Rail and its contractor to deliver Phase 3 once additional funding has been secured, 3. agree that Phase 4 of the flood alleviation scheme (being the linking up and completing the project) be scheduled for delivery in 2021/22, to allow sufficient time to apply for further Government grants and plan and procure the project for a summer construction. A further report would detail the precise delivery date, 4. a section of phase 4 could be built this autumn to reduce some flood risk to Feniton ; should the plan be viable and not incur significant additional project cost or risk. REASON: As it stands, the project budget was only sufficient to complete Phase 3 (under track crossing) but insufficient to complete Phase 4, without further applications for Central Government grant money. The application for the additional funds to realise Phase 4 would not be submitted or approved prior to the last mobilisation date (03 July 2020) for Network Rail to deliver the Phase 3 under track crossing this year (and thus EDDC be committing to completing phase 4, should it complete phase 3). Indications from the Environment Agency have been positive that more funding should be available to allow Phase 4 to proceed. Much time and effort had gone into securing the May 2020 under track crossing, however this was postponed due to the unknowns surrounding the Covid-19 pandemic. It was understood there were no further possession windows planned in 2020, however Network Rail recently identified an October 2020 possession. This possession window would not delay our project and still allow for a 2021 construction of Phase 4. Network Rail had advised they had no further planned possessions in financial year 2020/21 so we would be looking at financial year 2021/22 for the next available date. There was a good chance this would likely lead ... view the full minutes text for item 188.
Word for word from the decision East Devon published for this meeting. Source: democracy.eastdevon.gov.uk

Follow this further

Built from East Devon's papers

What the report saysPro

Report to Cabinet

Report to: Cabinet Date of Meeting: 21 July 2020 Public Document: Yes Exemption: None

Review date for None release

Subject: New Feniton Flood Alleviation Scheme

Purpose of report: To confirm the delay of the implementation of Phase 3 until a possession window is available in 2021. Although this risks further delay to the project, it gives time to get all funding signed off and other cost savings investigated, with the aim to have a fully funded project before committing significant funds towards a part completion.

Recommendation: That Cabinet; 1. Confirm the decision to postpone the delivery of Phase 3 of the flood alleviation scheme (being the newly proposed October 2020 undertrack crossing) until the whole project including phase 4 is fully funded, on the basis of an emerging cost basis contract subject to the Environment Agency confirming the availability of the additional funding as detailed in the report.

2. Delegate authority to the Strategic Lead (Housing, Health and Environment) in consultation with the Strategic Lead (Governance and Licensing) to negotiate and enter into the emerging costs basis contract with Network Rail and its contractor to deliver Phase 3 once additional funding has been secured

3. Agree that Phase 4 of the flood alleviation scheme (being the linking up and completing the project) be scheduled for delivery in 2021/22, to allow sufficient time to apply for further Government grants and plan and procure the project for a summer construction. A further report will detail the precise delivery date.

4. That a section of phase 4 could be built this autumn to reduce some flood risk to Feniton, should the plan be viable and not incur significant additional project cost or risk.

Reason for As it stands, the project budget is only sufficient to complete Phase 3 recommendation: (UTX) but insufficient to complete Phase 4, without further applications for Central Government grant money.

The application for the additional funds to realise Phase 4 will not be submitted or approved prior to the last mobilisation date (03 July 2020) for Network Rail to deliver the Phase 3 UTX this year. (and thus we would be committing to completing phase 4, should we complete phase 3) Indications from the Environment Agency have been positive that more funding should be available to allow Phase 4 to proceed. Much time and effort has gone into securing the May 2020 UTX, however this was postponed due to the unknowns surrounding the Covid-19 pandemic. We understood there were no further possession windows planned in 2020, however Network Rail recently identified an October 2020 possession. This possession window would not delay our project and still allow for a 2021 construction of Phase 4. Network Rail have advised us they have no further planned possessions in FY 2020/21 so we would be looking at FY 2021/22 for the next available date. There is a good chance this would likely lead to a significant delay to Phase 4.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
New Feniton Flood Alleviation SchemeReport 264 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 48 attended
MA
Councillor Megan ArmstrongCommittee Member, present
PA
Councillor Paul ArnottChairman, present
PH
Councillor Paul HaywardVice-Chairman, present
JB
Councillor Jess BaileyCommittee Member, present
GJ
Councillor Geoff JungCommittee Member, present
DL
Councillor Dan LedgerCommittee Member, present
PM
Councillor Paul MillarCommittee Member, present
MR
Councillor Marianne RixsonCommittee Member, present
JR
Councillor Jack RowlandCommittee Member, present
JL
Councillor John LoudounCommittee Member, present
AC
Amanda CoombesOfficer, in attendance
KB
Councillor Kevin BlakeyGuest, in attendance

All 48 on the meeting page

On this subject at East Devon

Search all
  1. New Feniton Flood Alleviation SchemeThis decision
  2. New Feniton Flood Alleviation SchemeApproved

More from East Devon Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 LGR in Devon: Government Decision and Implications for EDDCRESOLVED that Cabinet: 1. Notes the Government’s July decision and the subsequent review 2. Notes the concerns regard... Agreed Open
16 Sep 2026 Financial Strategy 2027 - 2029RESOLVED that Cabinet : 2. Agrees that the 2027/28 budget process should continue to be developed within the principl... Agreed Open
16 Sep 2026 Financial Monitoring Report and Annual Treasury Management Review 2025/26RESOLVED that Cabinet: Acknowledge the variances identified as part of the Revenue and Capital Monitoring process up ... Approved Open
16 Sep 2026 Woodbury Neighbourhood Plan to be formally 'made'RESOLVED that Cabinet: 1. Agree that the Woodbury Parish Neighbourhood Plan be ‘made’. 2. Note that once made the Pla... Agreed Open
16 Sep 2026 Green Team Project Standing Order ExemptionRESOLVED that Cabinet: 1. Notes and supports the exemption to Contract Standing Orders under the provision relating t... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies