RESOLVED that Cabinet: 1. Notes the progress made within the Enterprise Zone designation 2. Agrees the principle of a £1m fund to enable the continuation of an Enterprise Zone Business Rate Relief programme 3. Receives further papers setting out detailed investment proposals. RECOMMENDED to Council 4. That it agrees the principle of increasing borrowing up to £20m against ring fenced business rate income to fund the delivery of capital projects. REASON Cabinet last received a paper on the financial position of the EZ in March 2019. During the intervening period, work had focused on gaining approval for projects that support the delivery of the EZ, in terms of overcoming identified barriers and bringing forward catalytic investments that could increase the pace of delivery for new commercial space and jobs.
Word for word from the decision East Devon published for this meeting.Source: democracy.eastdevon.gov.uk
Report to: Cabinet Date of Meeting: 30 September 2020 Public Document: Yes Exemption: None Review date for None release
Subject: Exeter & East Devon Enterprise Zone
Purpose of report: To provide an update on the financial position with regard to the Enterprise Zone (EZ) programme and seek approval for additional borrowing against future ring-fenced business rate income. The additional borrowing will allow further investment in enabling delivery of new commercial space and jobs in the Enterprise Zone, supporting recovery from Covid 19 and providing opportunities for clean and inclusive growth.
Recommendation: It is recommended that Cabinet: 1. Notes the progress made within the Enterprise Zone designation 2. Agrees the principle of increasing borrowing up to £20m against ring fenced business rate income to fund the delivery of capital projects and makes this recommendation to Council 3. Agrees the principle of a £1m fund to enable the continuation of an Enterprise Zone Business Rate Relief programme 4. Receives further papers setting out detailed investment proposals Reason for Cabinet last received a paper on the financial position of the EZ in March recommendation: 2019. During the intervening period, work has focused on gaining approval for projects that support the delivery of the EZ, in terms of overcoming identified barriers and bringing forward catalytic investments that can increase the pace of delivery for new commercial space and jobs. Officer: Naomi Harnett, Enterprise Zone Programme Manager [email protected] / [phone removed] / 01395 571 746 Portfolio Holder: Portfolio Holder Economy and Assets Financial The financial details are outlined in the report. Sensitivity scenarios have implications: been considered with the projected income and the £20m borrowing is still viable under a 50% reduction in rate income. It should be noted that although the EZ business rates income is ring-fenced to meet the costs involved and the rate income does come to the District Council the liability of the loan repayments is with EDDC.
Legal implications: What is proposed is permissible within the framework of the Enterprise Zone. There are no other legal implications requiring comment. Equalities impact: Low Impact Potential impacts on equality will be managed through the Implementation Plan for the Zone. Climate change: Medium Impact The Enterprise Zone has focused on sustainability from the inception of the designation. The zone supports the delivery of district heating (DH) with the recent adoption of the Local Development Order and the existing DH network serving three of the four designated sites. New commercial buildings within the zone are built to high sustainability standards, with recently constructed new buildings meeting BREEAM excellent ratings. The development of the designation, supported by additional funding, will support green recovery and clean inclusive growth.
Risk: Medium Risk This paper seeks approval for additional borrowing against future ring- fenced business rate income to invest in enabling projects. Further papers will be reported to Cabinet on specific projects with financial appraisals before funding is drawn down. The risks associated with project delivery will be mitigated through robust project management procedures. Links to background Cabinet Paper – March 2019 information: Cabinet Paper – April 2018
Link to Council Plan: .
Outstanding Economic Growth, Productivity, and Prosperity
Report in full 1. Introduction
1.1Cabinet has received a series of papers on the Enterprise Zone (EZ) from when the designation became operational in April 2017. During the intervening period there has been steady progress made in the delivery of new commercial floor space on Science Park and Sky Park.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.