RESOLVED that Cabinet: approved the Exemption from Contract Standing Orders to enable the appointment of WSP to undertake further technical work in support of an application to the Heat Networks Investment Programme. REASON: Having undertaken the initial feasibility study, WSP were considered to be uniquely placed to support the development of a bid to the HNIP programme. This would be of a substantial scale; seeking in excess of £5m, and it was vital, in order to maximise the chances of success, that it was supported by a robust evidence base. The exemption would also enable demanding timescales and deadlines to be met.
Word for word from the decision East Devon published for this meeting.Source: democracy.eastdevon.gov.uk
Report to: Cabinet Date of Meeting 25 November 2020 Document classification: Part A Public Document Exemption applied: None Review date for release N/A
Towards Zero Carbon Development in the West End Report summary: The purpose of this report is to seek authority for the use of an Exemption from Contract Standing Orders to enable the appointment of consultants WSP to support the development of a bid to the Government’s Heat Network Investment Programme (HNIP). This follows the completion of the initial feasibility study in relation to supporting the delivery of low carbon development in the West End of the District that was reported to Cabinet in September. Recommendation: Approve the use of an Exemption from Contract Standing Orders to enable the appointment of WSP to undertake further technical work in support of an application to the Heat Networks Investment Programme. Reason for recommendation: Having undertaken the initial feasibility study, WSP are considered to be uniquely placed to support the development of a bid to the HNIP programme. This will be of a substantial scale – seeking in excess of £5m – and it is vital, in order to maximise the chances of success, that it is supported by a robust evidence base. The exemption will also enable demanding timescales and deadlines to be met.
Officer: Andrew Wood, Service Lead – Growth, Development & Prosperity, Tel 01395 571743, [email protected]
Portfolio(s) (check which apply): ☒ Climate Action ☐ Corporate Services and COVID-19 Response and Recovery ☐ Democracy and Transparency ☒ Economy and Assets ☐ Coast, Country and Environment ☐ Finance ☒ Strategic Planning ☐ Sustainable Homes and Communities Financial implications: Financial details are contained in the report. Legal implications: Cabinet can grant an exemption to the requirements of Contract Standing Orders pursuant to Rule 3.1 provided the sum involved is below the EU Threshold. The sum involved here is below the EU Threshold and therefore an exemption can be validly given. The reason for the exemption seems justified in this instance. Equalities impact Low Impact Climate change High Impact Risk: Low Risk The main risk relates to timing and getting a well worked up bid submitted by the January deadline. Commissioning WSP is core to this managing this risk. Links to background information Zero Carbon Development in the West End – Report to Cabinet 10th July 2019 item 13 Towards Zero Carbon Development in the West End – Report to Cabinet 30th September 2020 item 14 Link to Council Plan: Priorities (check which apply) ☒ Outstanding Place and Environment ☒ Outstanding Homes and Communities ☒ Outstanding Economic Growth, Productivity, and Prosperity ☒ Outstanding Council and Council Services
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.