Resolved
DECISION: The recommendation(s) was/were approved by a Senior Officer. The Senior Officer Decision Notice is listed above under Additional Documents.
Audit and Governance Committee approved this item on Thursday 20 January 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
DECISION: The recommendation(s) was/were approved by a Senior Officer. The Senior Officer Decision Notice is listed above under Additional Documents.
Report to: Audit and Governance Committee
Date of Meeting: 20 January 2022 Document classification: Part A Public Document Exemption applied: None Review date for release: N/A
Update to the SWAP Audit of the Integrated Asset Management Contract Report summary: This report is to update members on work undertaken following the findings and recommendations contained within the SWAP Audit report of July 2020 and offer assurance that the amber concerns raised have been dealt with in a timely manner
The Integrated Asset Management Contract is the delivery mechanism for all the HRA repairs, maintenance and void processes and is managed by our procured contractor Ian Williams. The contract is currently in its 3 rd year of operation and the partnership is maturing well. The working relationship between Ian Williams and EDDC is strong and able to withstand considerable challenge when required to ensure delivery targets are met
It is a sizable and highly transactional service contract completing some 900 -1400 jobs per month on behalf of our tenants and the HRA
There are very strong governance procedures written within the contract and these are followed scrupulously to ensure a clear audit trail, risk mitigation, value for money and financial probity. The governance meeting structure is set out below;
Tool Box Talks and Training – to ensure all front line operatives have the skills and expertise they require to complete their job role and are clear about EDDCs expectations and delivery standards
Reactive Repairs Meetings – held weekly for resource planning to ensure all targets are met
Voids Meetings again held weekly, Housing Allocations Officers also attend this meeting to ensure a smooth transition back into rental
Operational Group Meeting – Operational Managers meet weekly to discuss and address any delivery issues. If there are issues they are unable to address these are escalated to senior managers. Operational Group reports to Core Group
Core Group – Strategic management and oversight of the contract and its delivery; review of KPIs, finance, risk, BCP, complaints etc
Is the proposed decision in accordance with: Budget Yes ☒ No ☐ Policy Framework Yes ☒ No ☐ Recommendation: Members are requested to note this report as an update of the SWAP Audit carried out on the Integrated Asset Management Contract in July 2021 Reason for recommendation: The above mentioned audit gave an amber pass to some areas of delivery. This report seeks to provide reassurance to members that these issues have been addressed and that this contract is robustly and competently managed to the benefit of the council and its tenants
Officer: Joanne Garfoot – Housing Service Lead – Acting [email protected]
Portfolio(s) (check which apply): ☐ Climate Action and Emergency Response ☐ Coast, Country and Environment ☐ Council and Corporate Co-ordination ☐ Democracy, Transparency and Communications ☐ Economy and Assets ☐ Finance ☐ Strategic Planning ☒ Sustainable Homes and Communities ☐ Tourism, Sports, Leisure and Culture
Equalities impact Low Impact This contract was put in place to ensure EDDC could fully comply with its landlord and social housing provider obligations and value for money for the council. Climate change Low Impact Risk: Low Risk; Links to background information Link to Council Plan Priorities (check which apply) ☒ Better homes and communities for all ☐ A greener East Devon ☒ A resilient economy
Report in full This report is intended to offer members reassurance and updated information on the amber rated key findings within the SWAP Audit Report. For ease the numbers below correspond with the findings within the audit
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
SWAP audit of Integrated Asset Management Contract updateReport | 213 KB | DownloadRead as text |
PDF |
Senior Officer Decision SWAP IAM auditDecisions | 172 KB | Download |
Follow Audit and Governance Committee at East Devon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Jul 2026 | Internal Audit Progress Report - Quarter 4 2025-26That the Audit & Governance Committee note the progress against the 2025/26 Internal Audit Plan as of 30 June 2026 an... | Decided | Open |
| 23 Jul 2026 | Internal Audit Annual Opinion 2025/26That the Audit & Governance Committee note the Internal Audit Annual Opinion for 2025/26. | Decided | Open |
| 23 Jul 2026 | External Audit Plan 2025 - 2026That the External Audit Plan 2025 – 2026 be noted. | Noted | Open |
| 23 Jul 2026 | Draft Statement of Accounts 2025/26 including Annual Governance StatementThat Members note the draft statement of accounts 2025/26 had been signed by the S151 Officer. 2. That the audited st... | Noted | Open |
| 23 Jul 2026 | Proceeds of Crime Act (Anti-Money Laundering) PolicyThat the adoption of the Proceeds of Crime Act (Anti Money Laundering) Policy be agreed. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.