Resolved
that the Housing Review Board note the update on the current position with the delivery of the housing stock condition survey.
Housing Overview and Scrutiny Committee (formerly Housing Review Board) noted this item on Wednesday 18 January 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
that the Housing Review Board note the update on the current position with the delivery of the housing stock condition survey.
.Report to: Housing Review Board
Date of Meeting 18th January 2023 Document classification: Part A Public Document Exemption applied: None Review date for release N/A
Full Housing Stock Condition Survey Report summary: To update the Housing Review Board on the current position with the delivery of the Stock Condition Survey.
Is the proposed decision in accordance with: Budget Yes ☒ No ☐ Policy Framework Yes ☒ No ☐ Recommendation: That the Housing Review Board note the update on the current position with the delivery of the Housing Stock Condition Survey.
Reason for recommendation: To monitor the progress of the delivery of a full and robust Stock Condition Survey being carried out to the Housing Assets/Portfolio.
Officer: Graham Baker – Property & Asset Manager - [email protected]
Portfolio(s) (check which apply): ☒ Climate Action and Emergency Response ☐ Coast, Country and Environment ☐ Council and Corporate Co-ordination ☐ Democracy, Transparency and Communications ☒ Economy and Assets ☒ Finance ☒ Strategic Planning ☒ Sustainable Homes and Communities ☐ Tourism, Sports, Leisure and Culture
Equalities impact Low Impact . Climate change Low Impact Risk: Low Risk; EDDC is at greater risk if we do not undertake a full Stock Condition Survey Links to background information HRB Agenda and minutes June 2017; HRB Agenda and minutes April 2021; HRB Agenda and Minutes March 2022 Link to Council Plan Priorities (check which apply) ☒ Better homes and communities for all ☒ A greener East Devon ☐ A resilient economy
Stock Condition Survey 1. Current Position:
2. A formal contractual arrangement is in place between East Devon District Council and the specialist contractor engaged to carry out the Stock Condition Survey, Currie & Brown.
3. The mobilisation period has been completed, the work carried out during this period included:
Finalising the exact detail for the Stock Condition Survey. Establishing and agreeing all the areas that would form the survey and the data sets that will be collected to inform the following areas: Property condition information Component data/information HHSRS (Housing Health & Safety Rating Scheme) information Energy assessment EPC Certificate Building and fully testing the Stock Condition survey form that will be used to collect the data; the surveys will be carried out using i Pads as a Total Mobile solution, once the survey has been completed on site all data will be uploaded to detail review/quality control assessments. Full testing of the IT systems to ensure that capture and process the data. Liaison with our internal Housing Systems Team to ensure that they have a full understanding of the information/data that they will be receiving to load into our system. Agreement of the Programme of Work. Agreement of the content and the issue of formal letters to our Tenants to advise them of the impending Stock Condition Survey and requesting that they allow the Currie & Brown surveyors access to carry out the work. The communication also includes an information sheet of FAQ’s (frequently asked questions).
4. The Mobilisation Period took a little longer than hoped, but the delay was considered reasonable as it was essential that all the above was fully in place and agreed prior to commencing the Stock Condition Survey in full.
5. Void properties were used to carry out some initial test surveys, the purpose of these was:
Gain a general understanding of the EDDC stock. Fully Test all the IT systems/equipment etc. Allow the Surveyors opportunity to understand the specific requirements of the EDDC Stock Condition survey.
These initial test surveys served their purpose; they identified some IT issues that needed to be addressed before the Stock Condition commenced in full. 6. Programme:
7. The Stock Condition survey finally commenced in full during September 2022 albeit with a very slow/soft start up until Christmas. The intention of this was a further opportunity to:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Update on stock condition surveyReport | 258 KB | DownloadRead as text |
Follow Housing Overview and Scrutiny Committee (formerly Housing Review Board) at East Devon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Apr 2026 | Forward planto note the Housing Review Board forward plan. | Noted | Open |
| 30 Apr 2026 | Finance reportthat the initial variances identified in the revenue and capital monitoring process be noted. | Noted | Open |
| 30 Apr 2026 | Housing complaints - performance report 2025-26 (Q4)that the Housing Review Board note the content ... view the full minutes text for item 108. | Noted | Open |
| 30 Apr 2026 | Tenancy services - performance report 2025-26 (Q4)that the housing performance report – tenancy services quarter 4 (2025/26) is ... view the full minutes text for item... | Decided | Open |
| 22 Jan 2026 | Housing Review Board forward planTo note the Housing Review Board forward plan. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.