Resolved
That the ongoing work on local plan production as summarised in the report be noted.
Strategic Planning Committee noted this item on Tuesday 9 January 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
That the ongoing work on local plan production as summarised in the report be noted.
Report to: Strategic Planning Committee
Date of Meeting: 9 January 2024 Document classification: Part A Public Document Exemption applied: None Review date for release N/A
East Devon Local Plan – timetable update report Report summary: At Strategic Planning Committee on the 31 October 2023 it was suggested that at every second meeting of committee there should be an update report on overall progress on local plan production. This report summarises progress on key work streams. In summary it is reported that work is progressing according to timetables. It is highlighted that we have issued a tender brief seeking appointment of consultants to produce a whole plan viability assessment.
Is the proposed decision in accordance with: Budget Yes ☒ No ☐ Policy Framework Yes ☒ No ☐ Recommendation: That committee note the ongoing work on local plan production as summarised in this update report.
Reason for recommendation: To ensure Members of committee are kept aware of local plan making progress.
Officer: Ed Freeman – Assistant Director, Planning Strategy and Development Management, e-mail – [email protected], Tel 01395 517519
Portfolio(s) (check which apply): ☒ Climate Action and Emergency Response ☒ Coast, Country and Environment ☒ Council and Corporate Co-ordination ☒ Democracy, Transparency and Communications ☒ Economy and Assets ☒ Finance ☒ Strategic Planning ☒ Sustainable Homes and Communities ☒ Tourism, Sports, Leisure and Culture
Equalities impact Low Impact . Climate change Low Impact Risk: Low Risk; . Links to background information The consultation draft local plan from November 2022 and other local plan papers can be viewed at: Draft Local Plan Consultation - East Devon Links to other background documents, if provided, are contained in the body of this report.
Link to Council Plan Priorities (check which apply) ☒ Better homes and communities for all ☒ A greener East Devon ☒ A resilient economy
1. Local plan work planning
1.1At Strategic Planning Committee on 31 October 2023 it was agreed that at every second meeting an update report on local plan work progress would be presented to committee. In practical terms we would see this as being once every two months, or at committee meetings that most closely correspond to this pattern.
1.2The emphasis on updating being to: report on key work and tasks being undertaken to highlight any concerns about deviation from the timetable, and to report on forthcoming reports to committee.
1.3Updating on progress should be seen within the wider context of getting to the Publication consultation stage of plan making to a target date of November 2024 and thereafter to the Submission stage to a target date of May 2025.
1.4We are reviewing work progress alongside the timeline chart set out below/over. This chart was first presented to committee on 31 October 2023. It is not changed from its original iteration as there are no programming changes to report on. In subsequent drafts, however, we will look to amend if appropriate and if changes are needed, if or where so these will be reported on. Proposed table of key work stages to take the East Devon Local Plan to Submission for Examination
2023 2024 2025
May
May Mar
Mar Nov
Nov Dec
Dec Aug Feb
Sep
Feb Oct
Oct Apr
Apr Jun
Jun Jan
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
East Devon Local Plan: Timetable update reportReport | 765 KB | DownloadRead as text |
Follow Strategic Planning Committee at East Devon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2026 | Response to consultation on the Mid Devon Local PlanThat the Strategic Planning Committee endorsed the officer recommended response to Mid Devon District Council’s Local... | Agreed | Open |
| 5 May 2026 | Heritage Strategy 2024-2042That the updated second Heritage Strategy (2024 – 2042) be adopted in support of the Council’s duty towards the histo... | Approved | Open |
| 5 May 2026 | Self-Build and Custom House-Building Update and Monitoring Report for 2024 - 2025That the draft monitoring report for use in planning decisions (both planning policy and development management) be e... | Agreed | Open |
| 3 Mar 2026 | Cranbrook Category 4 Infrastructure ContributionsThe Committee recommends to the Cabinet that the ‘Mechanism for the allocation of category 4 infrastructure contribut... | Approved | Open |
| 3 Mar 2026 | Habitat Regulation Non-Infrastructure ContributionsRESOLVED That the revised non-infrastructure habitat mitigation contributions as shown in table 3 within the report b... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.