To note the Level 1 SFRA and to endorse it as evidence to underpin flooding issues for the emerging Local Plan. 2. To agree that the SFRA should be used in the formulation of policies to be included in the Local Plan relating to flood risk. 3. That the need to consider the results of ongoing work on a Level 2 SFRA before local plan allocations are finalised be noted.
Word for word from the decision East Devon published for this meeting.Source: democracy.eastdevon.gov.uk
Date of Meeting: 30 April 2024 Document classification: Part A Public Document Exemption applied: None Review date for release N/A
Strategic Flood Risk Assessment Level 1 and scoping for Level 2 SFRA Report summary: The National Planning Policy Framework (NPPF) requires the local plan to have regard to the long-term implications of flood risk and to help manage flood risk from all sources, taking account of the future impacts of climate change. It states that strategic policies should be informed by a strategic flood risk assessment and that we should apply a sequential, risk-based approach to the location of development to avoid, where possible, flood risk to people and property. Local plans should also: safeguard from development any land likely to be required for flood management; secure green and other infrastructure that will reduce flooding and consider relocating existing development to more sustainable locations where climate change is expected to increase flooding. A Level 1 Strategic Flood Risk Assessment (SFRA) has been completed in accordance with the relevant national guidance and in collaboration with Environment Agency and Devon County Council. It was prepared by specialist environmental and engineering consultants JBA. Targeted consultation was undertaken on the draft SFRA with relevant bodies such as South West Water, reservoir owners, emergency planners, coastal groups and neighbouring authorities. Climate change modelling was undertaken in accordance with the national planning guidance and in agreement with the Environment Agency. The SFRA Level 1 has been undertaken to provide evidence for the local plan, but will also be useful for neighbourhood planning, developers and to inform development management decisions. This report highlights those elements of the SFRA Level 1 that are considered to be most relevant to plan making, but Members should be aware that this is highly technical work, and they should refer to the report produced by JBA for a fuller understanding of the scope of the work and its complexities. The Executive Summary of the report is reproduced in Appendix 1 of this report. The SFRA Level 1 reports that the main sources of flooding in East Devon are from watercourses, the sea, surface water and sewers. Historically, most recorded flood incidents within East Devon have been due to fluvial flooding and surface water flooding but there has also been significant tidal flooding in communities along the coast. The cumulative impact of flooding was considered, and areas identified where there is a greater chance of encountering cumulative effects from planned development. The report sets out mitigation measures that could be undertaken to ensure flood risk is not exacerbated, and states that in many cases new development should be used to improve the flood risk. Detailed guidance is given on how applicants should prepare strategic flood risk assessments for development proposals and sustainable drainage systems. The report makes a series of recommendations to guide the allocation of sites and development of policies to manage flood risk in the local plan. Government guidance suggests that a Level 2 SFRA should be prepared if land is considered for allocation in areas at risk of flooding to give more detail on the nature of the flood risks involved. Following the Level 1 SFRA a scoping exercise was undertaken by JBA to identify sites that would need to be subject to a Level 2 SFRA. This work commenced in April 2024 and is expected to take 4 to 5 months (some detailed survey work is required). The SFRA Level 1 provides the highly technical and robust evidence necessary to inform the policies and allocations of the local plan. It is recommended that SPC endorse the work and use it to inform the emerging local plan.
Is the proposed decision in accordance with: Budget Yes ☒ No ☐ Policy Framework Yes ☒ No ☐
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.