RESOLVED that Cabinet: Gives authority for EDDC to enter into the collaboration agreement with Devon County Council to commit to the LEVI Project and provides delegated authority to the Director of Finance to agree the terms of the agreement in consultation with the Director of Governance and the Portfolio Holder for Economy & Assets. Approves the minimum list of Car Park sites to be included within the DCC LEVI project and provides delegated authority to the Director of Finance in consultation with the Director of Governance and the Portfolio Holder for Economy & Assets to add to or remove sites from the project. Gives authority for EDDC to enter into lease agreements and any other legal documentation required for the siting of the EV charge points and provides delegated authority to the Director of Finance to agree the terms of the legal documents in consultation with the Director of Governance and the Portfolio Holder for Economy & Assets. REASON: The DCC LEVI project represented an opportunity for EDDC to provide additional EV chargers within District owned car parks that did not already contain them, including in some locations that may only be viable because of this funding stream. There would be no capital cost to EDDC and DCC had received funding for project management of the installation programme. EDDC had worked with DCC on two previous EV installation projects and its collaboration with this project aligned with the principles and approach of the EDDC Parking Strategy, provided economies of scale as well as consistency of charging infrastructure across Devon.
Word for word from the decision East Devon published for this meeting.Source: democracy.eastdevon.gov.uk
Date of Meeting 10 July 2024 Document classification: Part A Public Document Exemption applied: None Review date for release N/A
Local Electric Vehicle Infrastructure (LEVI) – Project progress update Report summary: Devon County Council (DCC) have been allocated £7,067,000 funding through the Local Electric Vehicle Infrastructure (LEVI) Capital Fund to facilitate the installation of EV chargers across Devon.
DCC have invited EDDC to be part of the project by selecting car park sites to have 22kWh chargers installed.
EDDC have already been part of several previous EV charge point projects working with DCC and other local authorities in Devon. This project in particular benefits from the LEVI capital fund which will be used to unlock previously unviable sites.
Is the proposed decision in accordance with:
Budget Yes ☒ No ☐ Policy Framework Yes ☒ No ☐ Recommendation: 1. That Cabinet provides authority for EDDC to enter into the collaboration agreement with Devon County Council to commit to the LEVI Project and provides delegated authority to the Director of Finance to agree the terms of the agreement in consultation with the Director of Governance.
2. That Cabinet approves the minimum list of Car Park sites to be included within the DCC LEVI project and provides delegated authority to the Director of Finance in consultation with the Director of Governance to add to or remove sites from the project.
3. That Cabinets provides authority for EDDC to enter into lease agreements and any other legal documentation required for the siting of the EV chargepoints and provides delegated authority to the Director of Finance to agree the terms of the legal documents in consultation with the Director of Governance. Reason for recommendation: The DCC LEVI project represents an opportunity for EDDC to provide additional EV chargers within District owned car parks that do not already contain them, including in some locations that may only be viable as a result of this funding stream. There will be no capital cost to EDDC, and DCC have received funding for project management of the installation programme. EDDC have worked with DCC on two previous EV installation projects and our collaboration with this project aligns with the principles and approach of the EDDC Parking Strategy, provides economies of scale as well as consistency of charging infrastructure across Devon. Officer: Richard Easthope – Parking Services Manager – [email protected]
Portfolio(s) (check which apply): ☒ Climate Action and Emergency Response ☐ Coast, Country and Environment ☐ Council and Corporate Co-ordination ☐ Communications and Democracy ☐ Economy ☒ Finance and Assets ☐ Strategic Planning ☐ Sustainable Homes and Communities ☐ Culture, Leisure, Sport and Tourism Equalities impact Low Impact Climate change Low Impact Risk: Low Risk; The primary risk for this project is that of potential alternative use for any of the selected sites within the agreed lease term. This will result in EDDC having to provide financial compensation to the chosen supplier should it wish to end the lease contract. It is therefore important to find the balance between taking advantage of an available funding stream, and exposing the Council to additional risk should EDDC wish to use the sites for something elseduring term of the expected lease. A secondary risk is the loss of parking spaces within each chosen site to facilitate the installation of the chargepoints. 3 normal parking bays will be lost to accommodate the installation of 2 charging bays at each site. Links to background information Introductory Cabinet Report advising of our engagement with the LEVI project
Link to Council Plan Priorities (check which apply) ☐ Better homes and communities for all ☒ A greener East Devon ☐ A resilient economy
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.