RESOLVED that Cabinet: 1. Agrees to using EDDC’s UKSPF and REPF allocation to part-fund up to £600,000 for the Public Toilet Investment Programme (PTIP) and up to £200,000 to part-fund the Carbon Action Programme (CAP). 2. Agrees to allocate and ringfence the internal funding saved through this measure to deliver all remaining UKSPF and REPF activity endorsed by Cabinet and/or the UKSPF Programme Management Panel. The amount of funding ringfenced will be equal to the total sum of UKSPF and REPF payments to part-fund the PTIP and CAP. 3. Agrees to give delegated authority to the Director of Place, in consultation with the S151 officer and the Monitoring Officer, to determine the total amount of UKSPF and REPF funding (up to £800,000) to be allocated to part-fund the PTIP and CAP and to authorise the relevant payments. 4. Agrees to delegate authority for the ringfenced funding to the UKSPF Programme Management Panel and the Director of Place, in consultation with the S151 officer and the Monitoring Officer, to allocate the funding, amend existing projects and approve new projects (up to £800,000). REASON: Cabinet approval was required to ensure that UKSPF and REPF activity could continue following the updated guidance issued by MHCLG. This would significantly reduce the risk of EDDC having to repay a significant amount of funding back to MHCLG.
Word for word from the decision East Devon published for this meeting.Source: democracy.eastdevon.gov.uk
Date of Meeting 27 November 2024 Document classification: Part A Public Document Exemption applied: None Review date for release N/A
UKSPF Programme Amendment Report summary: MHCLG have recently updated the guidance on the UK Shared Prosperity Fund (UKSPF) and Rural England Prosperity Fund (REPF), stating that all funded activity, including that delivered by third parties, must conclude by the end of the current financial year. This updated guidance now threatens a number of our planned projects which were forecasting end dates beyond March 2025.
To complete all spend and activity by the March deadline, officers have explored alternative projects which can be fully delivered within the timeframe and demonstrate alignment with the UKSPF guidance. Phase 1 of EDDC’s Public Toilet Investment Programme (PTIP), along with our Carbon Action Programme (CAP), meet both of these criteria. Both initiatives are due to be completed and fully spent by the end of the financial year and are compatible with the UKSPF interventions. We therefore have an opportunity to utilise remaining UKSPF funding by part- funding our PTIP and CAP schemes. In return, we are recommending that the EDDC funding saved through the utilisation of the UKSPF budget is to be committed for the delivery of the remaining UKSPF projects.
This cost-neutral solution ensures successful delivery of the PTIP, CAP and the UKSPF projects, and reduces the likelihood of any underspend being returned to MHCLG. It allows EDDC to retain the benefits of the UKSPF allocation within the local community and continue the positive impacts into the 2025/26 financial year.
Is the proposed decision in accordance with: Budget Yes ☒ No ☐ Policy Framework Yes ☒ No ☐ Recommendations: 1. That Cabinet agrees to using EDDC’s UKSPF and REPF allocation to part-fund up to £600,000 for the Public Toilet Investment Programme (PTIP) and up to £200,000 to part-fund the Carbon Action Programme (CAP). 2. That Cabinet agrees to allocate and ringfence the internal funding saved through this measure to deliver all remaining UKSPF and REPF activity endorsed by Cabinet and/or the UKSPF Programme Management Panel. The amount of funding ringfenced will be equal to the total sum of UKSPF and REPF payments to part-fund the PTIP and CAP. 3. That Cabinet agrees to give delegated authority to the Director of Place, in consultation with the S151 officer and the Monitoring Officer, to determine the total amount of UKSPF and REPF funding (up to £800,000) to be allocated to part-fund the PTIP and CAP and to authorise the relevant payments. 4. That Cabinet agrees to delegate authority for the ringfenced funding to the UKSPF Programme Management Panel and the Director of Place, in consultation with the S151 officer and the Monitoring Officer, to allocate the funding, amend existing projects and approve new projects (up to £800,000). Reason for recommendation: Cabinet approval is required to ensure that UKSPF and REPF activity can continue following the updated guidance issued by MHCLG. This will also significantly reduce the risk of EDDC having to repay a significant amount of funding back to MHCLG.
Portfolio(s) (check which apply): ☐ Climate Action and Emergency Response ☐ Coast, Country and Environment ☐ Council and Corporate Co-ordination ☐ Communications and Democracy ☒ Economy ☒ Finance and Assets ☐ Strategic Planning ☐ Sustainable Homes and Communities ☐ Culture, Leisure, Sport and Tourism
Equalities impact Low Impact Climate change High Impact Risk: Low Risk; Links to background information East Devon’s UKSPF Investment Plan and REPF Addendum. Public Toilet Cabinet Report (12 May 2021) and Carbon Action Programme Cabinet Report (3 January 2024. Link to Council Plan Priorities (check which apply) ☐ Better homes and communities for all ☐ A greener East Devon ☒ A resilient economy
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.