Resolved
That Council approve that up to £673,000 of the works budget is spent at risk before external funding could be confirmed and claimed in late summer in order for the scheme to be completed within the required timescale.
Council approved this item on Wednesday 18 June 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
That Council approve that up to £673,000 of the works budget is spent at risk before external funding could be confirmed and claimed in late summer in order for the scheme to be completed within the required timescale.
Paper A
Report to: Cabinet
Date of Meeting 4 June 2025 Document classification: Part A Public Document Exemption applied: None Review date for release N/A
Seaton Coast Protection Scheme. Funding and proceeding prior to external funding being claimable Report summary: This report is to update Cabinet and to seek approval to spend up to £673,500 at risk to enable the project to start within the desired time frame before external grant confirmation and payment is received.
The report explains the reasons for the administrative delay in grant confirmation and payment and highlights the risks to the council.
Is the proposed decision in accordance with: Budget Yes ☐ No ☒ Policy Framework Yes ☒ No ☐ Recommendation: 1. That Cabinet recommend to Council that up to £673,000 of the works budget is spent at risk before external funding can be confirmed and claimed in late summer in order for the scheme to be completed with the required timescale.
Reason for recommendation: 1.To enable the project to proceed. Deferring the project by a year will likely lead to prices increasing further, so it’s the last chance to proceed with the current scheme. There is a small chance the scheme can proceed this year without this upfront spend, however the window is small.
Officer: Tom Buxton-Smith [email protected] 01395571630
Portfolio(s) (check which apply): ☐ Assets and Economy ☐ Communications and Democracy ☐ Council, Corporate and External Engagement ☐ Culture, Leisure, Sport and Tourism ☒ Environment - Nature and Climate ☒ Environment - Operational ☒ Finance ☐ Place, Infrastructure and Strategic Planning Paper A
☐ Sustainable Homes and Communities
Equalities impact Low Impact Climate change High Impact Risk: Medium Risk; Project is well developed, but lacking funding Links to background information May add link to updated business case when prepared. Link to Council Plan Priorities (check which apply) ☐ A supported and engaged community ☐ Carbon neutrality and ecological recovery ☒ Resilient economy that supports local business ☐ Financially secure and improving quality of services
Report in full 1. Background
1.1Seaton Hole Beach Management Plan (BMP) has been developed over many years and the Outline Business Case (OBC) was assured in 2021 by the Environment Agency, securing external funding subject to approval. Since the OBC was assured, the project has been transferred to BCP (Bournemouth Christchurch Poole) Council to run under our South West Flood and Coastal (SWFC) service share agreement. The project is now called the Seaton Hole Coastal Protection Scheme (CPS)
1.2The projects aim is to reduce the rate of erosion on the cliffs at Seaton Hole and reduce risk of cliff falls to beach users. Paper A
Figure The 2012 cliff slip at Seaton Hole, East Devon (Source: https://www.dailymail.co.uk/news/article-3712663/Three-cliff-houses-command- premium-prices-stunning-sea-views-virtually-worthless-huge-landslip-left-brink-100ft- drop.html) 1.3. The project is largely to increase the volume of existing rock armour on the beach at the toe of the cliffs and also upgrade gabion baskets and maintain the existing wall.
Image 1.3. Overview of the works area.
1.4We have tendered the contract for these works to the open market receiving two compliant bids back, and subject to funding, we will award the winning bidder to complete the works. 1.5. The tendered price is above what was allowed for in the business case, so we require additional funding to close the funding gap. (See section 2) 1.6. The works require 7000 tonnes of rock to be brought to Seaton. We have enquired about bringing this by road, but due to the road network, a sea only delivery is possible, which has led to the increased scheme cost Paper A
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Paper A.Seaton Coast Protection SchemeReport | 381 KB | DownloadRead as text |
PDF |
Seaton Coast Protection SchemeReport | 250 KB | Download |
Follow Council at East Devon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2026 | Community Governance Review - Cranbrook and surrounding areasThat the making of the East Devon District (Reorganisation of Community Governance) Order 2026 (the Reorganisation Or... | Approved | Open |
| 17 Sep 2026 | Local Government Act 1972 - Exclusion of Press and PublicThat under Section 100(A) (4) of the Local Government Act 1972 the public (including the press) be excluded from the ... | Decided | Open |
| 15 Jul 2026 | Local Development SchemeThat Council adopt and publish the proposed new East Devon . | Approved | Open |
| 15 Jul 2026 | Recommendations from Independent Remuneration PanelThat Council: 1. approves the Councillor Scheme of Allowances (Appendix 2), subject to any minor drafting changes. 2.... | Approved | Open |
| 15 Jul 2026 | Recommendation from Cabinet - 9 July 2026: Financial Outturn Report 2025/2026That Council approve the outturn position for 2025/26 including the implications and proposals relating to the Balanc... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.