Build & Buy - A housing investment and delivery plan for East Devon
NotedScrutiny2 papers
Housing Overview and Scrutiny Committee (formerly Housing Review Board) noted this item on Thursday 31 July 2025. Below is the council's own wording, with the papers it was decided on.
Decision making and delegated authority. Build and Buy – A Housing Investment and Delivery Plan for East Devon was a bold, ambitious and proactive response to the district’s housing challenges. The Board noted that the development process could be lengthy and complex with the potential for lengthy delays, particularly at the planning and pre planning stage. Multiple external factors such as inflation, particularly on build costs and labour, could adversely affect development viability and necessitate a deviation from the plan target. As such, the hugely ambitious target of 500 homes over 5 years should be seen as an aspirational target. The next steps included: • Finalising site feasibility prioritisation and engagement plans. • Establishing delivery partnerships and a pipeline of acquisitions. • Regular progress reporting to Members, in addition to regular review to monitor delivery, risks, and financial performance. • Seeking formal approval of the HRA Business Plan which would provide the strategic financial investment framework for financing the plan. Concern was expressed over the resources that could be required to deliver such an ambitious plan. It was acknowledged that not all of the resource was currently available in-house and this would be built into the plan. It was currently a conceptual piece of work, with broad figures in principle. There would be precise ... view the full minutes text for item 67.
Word for word from the decision East Devon published for this meeting.Source: democracy.eastdevon.gov.uk
Report to Housing Overview and Scrutiny Committee (formerly Housing Review Board)
Report to: Housing Review Board
Date of Meeting 30th July 2025 Document classification: Part A Public Document Exemption applied: None Review date for release N/A
Build & Buy - A Housing Investment & Delivery Plan for East Devon
Report summary: The report is a response to a growing housing need and feedback from the Housing Strategy consultation. The report provides an overview and introduction to ‘Build and Buy’ A Housing Investment & Delivery Plan for East Devon.
Is the proposed decision in accordance with: Budget Yes ☒ No ☐ Policy Framework Yes ☐ No ☐ Recommendation:
That Housing Review Board recommend to cabinet that;
1) The Build & Buy Plan is endorsed by the Council
2) It be noted that the financing of the plan is subject to the approval of the HRA Business Plan and the 2026/27 budget setting process in due course.
Reason for recommendation: To increase the supply of affordable homes for residents of east Devon and contribute to wider housing and community objectives, including estate regeneration.
Officer: Tom Butcher – Development Surveyor; Liam Reading – Assistant Director Programmes, Investment & Development
Portfolio(s) (check which apply): ☐ Assets and Economy ☐ Communications and Democracy ☐ Council, Corporate and External Engagement ☐ Culture, Leisure, Sport and Tourism ☐ Environment - Nature and Climate ☐ Environment - Operational ☐ Finance ☐ Place, Infrastructure and Strategic Planning ☒ Sustainable Homes and Communities
Equalities impact Low Climate change Medium Impact Risk: Medium Risk; Risk table is included on page 4 of this report, and financial implications from point 13 onwards. Links to background information None Link to Council Plan Priorities (check which apply) ☒ A supported and engaged community ☒ Carbon neutrality and ecological recovery ☐ Resilient economy that supports local business ☒ Financially secure and improving quality of services
Build & Buy: A Housing Investment & Development Plan for East Devon
Introduction
1. This report outlines the Council’s vison for new housing through ‘Build and Buy – A Housing Investment & Delivery Plan for East Devon.
2. The purpose of the plan is to maximise the use of our assets, address housing need and support the Council’s strategic objective of having a supported and engaged community that have the right homes in the right places and with the appropriate infrastructure.
3. The Plan aims to deliver 500 new homes over the next five years, with an equal split between homes developed on Council owned land and homes acquired through partnerships with private developers.
• 250 homes will be delivered through direct development on the Council’s existing landholdings. • 250 homes will be purchased from developers as part of Section 106 agreements, joint ventures, or off-the-shelf acquisitions.
4. This mixed delivery approach is intended to accelerate housing supply, make efficient use of public assets, and ensure the Housing Revenue Account (HRA) has a range of housing stock to meet local needs. Key Considerations
Site and Development Feasibility
5. Council owned land will be subject to detailed design proposals and local engagement prior to the submission of Planning. Consideration of local need, house types, location and local infrastructure will be included.
6. Delivery of homes will be phased to manage risk and delivery over the 5 year period.
Construction Type, Procurement and Delivery Models
7. The form of construction may vary depending on site specific requirements, but could include traditional build or Modern Methods of Construction (MMC)
8. Procurement and delivery is likely to be a mix of design & build contracts, partnerships with housing associations and developer-led schemes. The use of Framework Agreements where appropriate will streamline procurement and ensure value for money.
Housing Mix and Design Standards
9. The plan proposes to deliver a range of 2, 3 and 4 Bedroom, general needs homes, to create a range of house types
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Housing Overview and Scrutiny Committee (formerly Housing Review Board) at East Devon and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.