Exemption to Contract Standing Orders to appoint specialist underwater contractor

Noted Executive 1 paper

AI summaryCabinet noted an approved exemption to contract rules to appoint a specialist underwater contractor for works at three council swimming pools, with a £46,344 quote saving about £13,000 against a £60,000 budget.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted the granting of an exemption to contract rules
Money£46,344Quote accepted, saving about £13,000 against £60,000 budget
What happens nextWorks to proceedSpecialist contractor to carry out underwater repairs at three pool sites
Who it affectsThree council swimming poolsOperated by LED

What was decided

Cabinet noted the action taken to grant an exemption to Contract Standing Orders for appointing a specialist underwater contractor. Report P5, P14

The specialist contractor's quote of £46,344 was accepted as good value, giving a saving of about £13,000 on the allocated budget. Report P12

The exemption was supported by the Assistant Director, the Finance Director, and the Director of Governance. Report P13

Why

Only a limited number of contractors can do the specialist underwater work, and availability is further restricted by the need to work outside hours to minimise disruption and loss of income to the operator. Report P10

The cost is well below the public procurement threshold of £884,720 for Small Lots Works, so obtaining more than three quotations could not be fulfilled under current Contract Standing Orders. Report P11

Using the existing specialist contractor, already familiar with each site, reduces health and safety risks and shortens the timeframe, lowering costs. Report P12

What happens next

The specialist contractor will undertake the underwater works at the council's three swimming pool sites, funded from the existing 2025 to 2026 capital budget. Report P9, P12

The money

  • £60,000 Capital funding allocated in the 2025 to 2026 budget for specialist underwater works at the swimming pools Report P9
  • £46,344 Quote from the specialist contractor for the works Report P12
  • £13,000 Approximate saving on the allocated budget Report P12
  • £20,001 Threshold above which use of the exemption must be reported to Cabinet Report P5, P14
  • £884,720 Public procurement threshold for Small Lots Works Report P11

Options considered

  • Chosen: Grant an exemption to Contract Standing Orders and accept the specialist contractor's quote. Limited specialist market, need to work outside hours, contractor familiar with each site, good value at £46,344 Report P10, P11, P12, P13
  • Rejected: Obtain more than three quotations under standard competition requirements. Competition requirements could not be fulfilled due to the limited number of specialist contractors and market availability Report P11

Implications

  • Financial: The work can be met from an existing approved budget, with a quote representing about £13,000 saving. Report P12, P15
  • Legal: The contract value falls below the procurement threshold, and the exemption is validly relied upon under Contract Standing Orders, agreed by the S151 officer and Monitoring Officer. Report P15
  • Equalities: Low impact. Report P8
  • Climate: Low impact. Report P8
  • Risk: Low risk; using the familiar specialist contractor reduces health and safety risks. Report P8, P12

Who and where

  • Users of the council's three swimming pools, currently operated by LED Report P9, P10
  • LED as the current pool operator, due to potential disruption and loss of income if works are not timed outside working hours Report P10
  • The specialist underwater contractor undertaking the cyclical compliance surveys Report P12

Timeline

  • 29/10/2025: Cabinet meeting at which the exemption was noted Report P2
  • 2025-2026: Budget year in which the £60,000 capital funding is allocated Report P9

Plain English for the jargon

  • Contract Standing Orders: The council's internal rules governing how contracts are procured and awarded.
  • S151 officer: The Chief Finance Officer designated under section 151 of the Local Government Act 1972, responsible for financial administration.
  • Small Lots Works: A category under public procurement rules for smaller works contracts, with a threshold of £884,720.
  • Exemption to Contract Standing Orders: A formal departure from the usual procurement rules, granted where standard requirements cannot be met.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item98

Resolved

RESOLVED that Cabinet ; Notes the action taken. REASON: Under Contract Standing Orders item 2.3.2, Request for Exemption to Contract Standing Orders must be reported to Cabinet for support. “Where the Contract sum is £20,001 or above then the use of the exemption must be reported by the Officer, to the next meeting of the Cabinet for them to note their support for the action taken.”
Word for word from the decision East Devon published for this meeting. Source: democracy.eastdevon.gov.uk

Follow this further

Built from East Devon's papers

What the report saysPro

Report to Cabinet

Report to: Cabinet

Date of Meeting 29/10/2025 Document classification: Part A Public Document Exemption applied: None Review date for release N/A

Appointment of Specialist Contractor to Undertake Underwater Works at East Devon District Council Swimming Pools Report summary: The report informs Cabinet of an Exemption to Contract Standing Orders approved with regards to appointing specialist underwater contractor to undertake works at the Council’s swimming pools.

Is the proposed decision in accordance with: Budget Yes ☒ No ☐ Policy Framework Yes ☒ No ☐ Recommendation: That Cabinets notes the action taken.

Reason for recommendation: Under Contract Standing Orders item 2.3.2, Request for Exemption to Contract Standing Orders must be reported to cabinet for support. “Where the Contract sum is £20,001 or above then the use of the exemption must be reported by the Officer, to the next meeting of the Cabinet for them to note their support for the action taken.”

Officer: Jorge Pineda-Langford – Principal Building Surveyor / Team Lead [email protected] 01395 571633

Portfolio(s) (check which apply): ☒ Assets and Economy ☐ Communications and Democracy ☐ Council, Corporate and External Engagement ☐ Culture, Leisure, Sport and Tourism ☐ Environment - Nature and Climate ☐ Environment - Operational ☒ Finance ☒ Place, Infrastructure and Strategic Planning ☐ Sustainable Homes and Communities

Equalities impact Low Impact Climate change Low Impact Risk: Low Risk; Links to background information N/A Link to Council Plan Priorities (check which apply) ☒ A supported and engaged community ☐ Carbon neutrality and ecological recovery ☒ Resilient economy that supports local business ☒ Financially secure and improving quality of services

Report in full 1. The Council has allocated £60,000 Capital funding in its 2025-2026 Budget to undertake specialist underwater works at the Council’s three swimming pools sites. The swimming pools sites are currently operated by LED.

2. Due to the specialist nature of the works there is a limited number of contractors that can do the work, which involves teams of divers undertaking underwater repairs to the swimming pool tanks and accessing underwater confine spaces. Market availability is further restricted by the need to undertake the work outside working hours to minimise disruptions to the services and loss of income to the operator.

3. Based on the above considerations and the relatively low cost of the work, considerably under the Public Procurement Threshold (£884,720 for Small Lots Works), the competition requirements under the current Contract Standing Orders to obtain more than three quotations cannot be fulfilled and an Exemption to Contract Standing Orders was requested.

4. The current specialist contractor undertaking cyclical underwater compliance surveys has provided a quote for the works. The contractor is well familiar with each site and the work, which is a key consideration in terms of the health and safety risks involved. In addition, it will allow for the works to be done in a shorter timeframe, reducing costs. The quote for £46,344 is considered good value and represents a considerable saving on the allocated budget, approximately £13,000 saving.

5. The request for an Exemption to Contract Standing Orders has been granted and supported by the officer’s Line Manager (Assistant Director Tim Child), Finance (Finance Director (CFO/S151) Simon Davey), and Governance and Licensing (Director of Governance (Monitoring Officer and Returning Officer) Melanie Wellman).

6. As the contract value is over £20,001, the granting of the exemption must be reported for Cabinet to note.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Exemption to Contract Standing Orders to appoint specialist underwater contractorReport 161 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 26 attended
MW
Melanie WellmanOfficer, in attendance
PA
Councillor Paul ArnottChair, present
SH
Councillor Sam HawkinsCommittee Member, present
PH
Councillor Paul HaywardCommittee Member, present
NH
Councillor Nick HookwayCommittee Member, present
SJ
Councillor Sarah JacksonCommittee Member, present
GJ
Councillor Geoff JungCommittee Member, present
DL
Councillor Dan LedgerCommittee Member, present
JL
Councillor John LoudounVice-Chair, present
TO
Councillor Todd OliveCommittee Member, present
RJ
Councillor Richard JefferiesCommittee Member, present
AC
Amanda CoombesOfficer, in attendance

All 26 on the meeting page

On this subject at East Devon

Search all
  1. Exemption to Contract Standing Orders to appoint specialist underwater contractorThis decision
  2. Contract standing orders exemption Global City Futures final business caseNoted
  3. Contract standing orders exemption - Production of Recycling & Waste future model business caseDeferred
  4. Exemption to Contract Standing Orders - Strategic Flood Risk AssessmentApproved
  5. Exemption from Contract Standing Orders - UK Shared Prosperity Fund - OSMNoted
  6. Exemption to Contract Standing Orders in respect of a consultant solicitorApproved

More from East Devon Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 LGR in Devon: Government Decision and Implications for EDDCRESOLVED that Cabinet: 1. Notes the Government’s July decision and the subsequent review 2. Notes the concerns regard... Agreed Open
16 Sep 2026 Financial Strategy 2027 - 2029RESOLVED that Cabinet : 2. Agrees that the 2027/28 budget process should continue to be developed within the principl... Agreed Open
16 Sep 2026 Financial Monitoring Report and Annual Treasury Management Review 2025/26RESOLVED that Cabinet: Acknowledge the variances identified as part of the Revenue and Capital Monitoring process up ... Approved Open
16 Sep 2026 Woodbury Neighbourhood Plan to be formally 'made'RESOLVED that Cabinet: 1. Agree that the Woodbury Parish Neighbourhood Plan be ‘made’. 2. Note that once made the Pla... Agreed Open
16 Sep 2026 Green Team Project Standing Order ExemptionRESOLVED that Cabinet: 1. Notes and supports the exemption to Contract Standing Orders under the provision relating t... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies