Exemption to Contract Standing Orders to appoint specialist underwater contractor
NotedExecutive1 paper
AI summaryCabinet noted an approved exemption to contract rules to appoint a specialist underwater contractor for works at three council swimming pools, with a £46,344 quote saving about £13,000 against a £60,000 budget.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted the granting of an exemption to contract rules
Money£46,344Quote accepted, saving about £13,000 against £60,000 budget
What happens nextWorks to proceedSpecialist contractor to carry out underwater repairs at three pool sites
Who it affectsThree council swimming poolsOperated by LED
What was decided
Cabinet noted the action taken to grant an exemption to Contract Standing Orders for appointing a specialist underwater contractor. Report P5, P14
The specialist contractor's quote of £46,344 was accepted as good value, giving a saving of about £13,000 on the allocated budget. Report P12
The exemption was supported by the Assistant Director, the Finance Director, and the Director of Governance. Report P13
Why
Only a limited number of contractors can do the specialist underwater work, and availability is further restricted by the need to work outside hours to minimise disruption and loss of income to the operator. Report P10
The cost is well below the public procurement threshold of £884,720 for Small Lots Works, so obtaining more than three quotations could not be fulfilled under current Contract Standing Orders. Report P11
Using the existing specialist contractor, already familiar with each site, reduces health and safety risks and shortens the timeframe, lowering costs. Report P12
What happens next
The specialist contractor will undertake the underwater works at the council's three swimming pool sites, funded from the existing 2025 to 2026 capital budget. Report P9, P12
The money
£60,000 Capital funding allocated in the 2025 to 2026 budget for specialist underwater works at the swimming pools Report P9
£46,344 Quote from the specialist contractor for the works Report P12
£13,000 Approximate saving on the allocated budget Report P12
£20,001 Threshold above which use of the exemption must be reported to Cabinet Report P5, P14
£884,720 Public procurement threshold for Small Lots Works Report P11
Options considered
Chosen: Grant an exemption to Contract Standing Orders and accept the specialist contractor's quote. Limited specialist market, need to work outside hours, contractor familiar with each site, good value at £46,344 Report P10, P11, P12, P13
Rejected: Obtain more than three quotations under standard competition requirements. Competition requirements could not be fulfilled due to the limited number of specialist contractors and market availability Report P11
Implications
Financial: The work can be met from an existing approved budget, with a quote representing about £13,000 saving. Report P12, P15
Legal: The contract value falls below the procurement threshold, and the exemption is validly relied upon under Contract Standing Orders, agreed by the S151 officer and Monitoring Officer. Report P15
Risk: Low risk; using the familiar specialist contractor reduces health and safety risks. Report P8, P12
Who and where
Users of the council's three swimming pools, currently operated by LED Report P9, P10
LED as the current pool operator, due to potential disruption and loss of income if works are not timed outside working hours Report P10
The specialist underwater contractor undertaking the cyclical compliance surveys Report P12
Timeline
29/10/2025: Cabinet meeting at which the exemption was noted Report P2
2025-2026: Budget year in which the £60,000 capital funding is allocated Report P9
Plain English for the jargon
Contract Standing Orders: The council's internal rules governing how contracts are procured and awarded.
S151 officer: The Chief Finance Officer designated under section 151 of the Local Government Act 1972, responsible for financial administration.
Small Lots Works: A category under public procurement rules for smaller works contracts, with a threshold of £884,720.
Exemption to Contract Standing Orders: A formal departure from the usual procurement rules, granted where standard requirements cannot be met.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item98
Resolved
RESOLVED that Cabinet ; Notes the action taken. REASON: Under Contract Standing Orders item 2.3.2, Request for Exemption to Contract Standing Orders must be reported to Cabinet for support. “Where the Contract sum is £20,001 or above then the use of the exemption must be reported by the Officer, to the next meeting of the Cabinet for them to note their support for the action taken.”
Word for word from the decision East Devon published for this meeting.Source: democracy.eastdevon.gov.uk
Date of Meeting 29/10/2025 Document classification: Part A Public Document Exemption applied: None Review date for release N/A
Appointment of Specialist Contractor to Undertake Underwater Works at East Devon District Council Swimming Pools Report summary: The report informs Cabinet of an Exemption to Contract Standing Orders approved with regards to appointing specialist underwater contractor to undertake works at the Council’s swimming pools.
Is the proposed decision in accordance with: Budget Yes ☒ No ☐ Policy Framework Yes ☒ No ☐ Recommendation: That Cabinets notes the action taken.
Reason for recommendation: Under Contract Standing Orders item 2.3.2, Request for Exemption to Contract Standing Orders must be reported to cabinet for support. “Where the Contract sum is £20,001 or above then the use of the exemption must be reported by the Officer, to the next meeting of the Cabinet for them to note their support for the action taken.”
Officer: Jorge Pineda-Langford – Principal Building Surveyor / Team Lead [email protected] 01395 571633
Portfolio(s) (check which apply): ☒ Assets and Economy ☐ Communications and Democracy ☐ Council, Corporate and External Engagement ☐ Culture, Leisure, Sport and Tourism ☐ Environment - Nature and Climate ☐ Environment - Operational ☒ Finance ☒ Place, Infrastructure and Strategic Planning ☐ Sustainable Homes and Communities
Equalities impact Low Impact Climate change Low Impact Risk: Low Risk; Links to background information N/A Link to Council Plan Priorities (check which apply) ☒ A supported and engaged community ☐ Carbon neutrality and ecological recovery ☒ Resilient economy that supports local business ☒ Financially secure and improving quality of services
Report in full 1. The Council has allocated £60,000 Capital funding in its 2025-2026 Budget to undertake specialist underwater works at the Council’s three swimming pools sites. The swimming pools sites are currently operated by LED.
2. Due to the specialist nature of the works there is a limited number of contractors that can do the work, which involves teams of divers undertaking underwater repairs to the swimming pool tanks and accessing underwater confine spaces. Market availability is further restricted by the need to undertake the work outside working hours to minimise disruptions to the services and loss of income to the operator.
3. Based on the above considerations and the relatively low cost of the work, considerably under the Public Procurement Threshold (£884,720 for Small Lots Works), the competition requirements under the current Contract Standing Orders to obtain more than three quotations cannot be fulfilled and an Exemption to Contract Standing Orders was requested.
4. The current specialist contractor undertaking cyclical underwater compliance surveys has provided a quote for the works. The contractor is well familiar with each site and the work, which is a key consideration in terms of the health and safety risks involved. In addition, it will allow for the works to be done in a shorter timeframe, reducing costs. The quote for £46,344 is considered good value and represents a considerable saving on the allocated budget, approximately £13,000 saving.
5. The request for an Exemption to Contract Standing Orders has been granted and supported by the officer’s Line Manager (Assistant Director Tim Child), Finance (Finance Director (CFO/S151) Simon Davey), and Governance and Licensing (Director of Governance (Monitoring Officer and Returning Officer) Melanie Wellman).
6. As the contract value is over £20,001, the granting of the exemption must be reported for Cabinet to note.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.