Infrastructure Funding Statement

Noted Planning 2 papers

AI summaryEast Devon councillors noted the 2024/25 Infrastructure Funding Statement covering £9.9m of approved CIL bids and £1.6m of S106 contributions, and approved its publication to government.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedAnnual statement approved for submission to government
Money£9.9m of CIL bids approvedSeven bids approved by Strategic Planning Committee
What happens nextPublish and submit to governmentAssistant Director may amend Neighbourhood CIL list
Who it affectsParishes, developers, infrastructure providersCIL receipts and S106 contributions recorded for 2024/25

What was decided

The committee noted the report and the requirement to provide an Annual Infrastructure Funding Statement. Report P5, P6

The committee approved publication and submission to government of the 2024/25 Annual Funding Statement, with delegated authority to the Assistant Director for Planning Strategy and Development Services to amend the Neighbourhood CIL summary list in consultation with the Chair. Report P8, P30

Why

The statement records the securing, collecting and spending of Community Infrastructure Levy and Section 106 contributions in the period 1 April 2024 to 31 March 2025. Report P6, P7

In Autumn 2024 the Council invited bids for CIL from infrastructure providers, and seven bids with a combined funding request of £ 9.9million were approved by the Strategic Planning Committee on 19 May 2025. Report P8, P14

What happens next

The 2024/25 statement will be published and submitted to government, with the Assistant Director given delegated authority to amend the Neighbourhood CIL summary list after consulting the Chair. Report P30

The money

  • £ 9.9million Combined funding request of 7 CIL bids approved on 19 May 2025 Report P14
  • £ 4,035,694.52 Total value of CIL set out in all demand notices in 2024/25 Report P18
  • £ 1,888,007.75 Total CIL receipts for the reported year Report P19
  • £ 10,113,007.29 Total CIL receipts collected before 2024/25 not yet allocated Report P20
  • £ 6,808,535.30 Total CIL receipts collected before 2024/25 and allocated in year Report P21
  • £ 420,717.96 Total CIL expenditure for the reported year Report P22
  • £ 1,065,909.75 CIL receipts allocated but not spent during the reported year Report P23
  • £ 199,363.00 CIL spent on administrative expenses in 2024/25 Report P26
  • £ 514,422.78 CIL receipts allocated but not spent on habitat mitigation Report P29
  • £ 1,622,561.74 S106 money received during 2024/25 Report P35, P39
  • £ 734,747.04 S106 money spent in 2024/25 Report P36, P45
  • £ 4,959,773.63 Total money under planning obligations entered into in 2024/25 Report P38
  • £ 1,163,127.82 S106 money allocated but not spent during 2024/25 Report P44
  • £ 8,744,944.73 S106 money retained at end of reported year Report P52

Options considered

  • Chosen: Note the report and approve publication and submission to government. To meet the requirement to provide an Annual Infrastructure Funding Statement covering CIL and S106 activity in 2024/25 Report P5, P6

Implications

  • Financial: Seven CIL bids with a combined £9.9million request were supported, all benefitting from match funding from other sources. Report P14
  • Other: Education and highways contributions are excluded as these are the responsibility of Devon County Council. Report P9
  • Other: Habitat mitigation contributions secured through S111 are not recorded in this report. Report P9
  • Legal: Publication is required under Community Infrastructure Levy Regulations (2019 Amendment) Regulation 121A Schedule 2. Report P16, P33

Who and where

  • Parish and town councils receiving and spending Neighbourhood CIL Report P30, P31
  • Infrastructure providers including schools, health, sport, transport and habitat mitigation Report P11, P15
  • Developers entering into S106 agreements Report P35, P38
  • Residents of new and growing communities benefiting from funded facilities Report P14, P15

Timeline

  • 1 April 2024, 31 March 2025: Reporting period covered by the statement Report P2, P6
  • Autumn 2024: Council invited bids for CIL from infrastructure providers Report P8
  • 19 May 2025: Seven CIL bids totalling £9.9million approved by Strategic Planning Committee Report P14
  • 11/25: Statement correct at time of production Report P58
  • 2026-01-06: Strategic Planning Committee noted the report and approved publication

Plain English for the jargon

  • CIL: Community Infrastructure Levy, a charge on new development used to fund local infrastructure
  • S106: Section 106 agreements, planning obligations attached to planning permissions to mitigate development impact
  • NCIL: Neighbourhood CIL, the portion of CIL passed to parish and town councils
  • S278: Section 278 of the Highways Act 1980, agreements for highway works funded by developers
  • SANG: Suitable Alternative Natural Greenspace, used to mitigate recreation pressure on protected habitats
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item44

Resolved

That the contents of this report and the requirements to provide an Annual be noted. 2. That the publication and submission to government of the 2024/25 Annual Funding Statement based on the information detailed in the report be approved and delegated authority be given to the Assistant Director – Planning Strategy and Development Services, in consultation with the Chair to amend the Neighbourhood CIL summary list.
Word for word from the decision East Devon published for this meeting. Source: democracy.eastdevon.gov.uk

Follow this further

Built from East Devon's papers

What the report saysPro

Report to Strategic Planning Committee

Annual Infrastructure Funding Statement Community Infrastructure Levy and Section 106

1 April 2024 – 31 March 2025

Photography by Still Imaging

eastdevon.gov.uk

1 Introduction

This statement provides a record of the securing, collecting and spending of Community Infrastructure Levy (  CIL ) and S106 contributions in the period 1 April 2024 – 31 March 2025.

Collectively, CIL and S106 are known as Planning Obligations whose purpose is to mitigate the impact of development through provision of infrastructure in the local area.

In Autumn 2024, the Council invited bids for CIL from infrastructure providers. The outcome is summarised in this statement.

This report does not record contributions secured through S111 for the purpose of habitat mitigation. Education and highways contributions are also excluded as these are the responsibility of Devon County Council.

The following items could be wholly or partially funded by CIL:

• Clyst Valley Regional Park • Community and Youth facilities • Education • Emergency Services facilities • Exe Estuary habitat mitigation • Healthcare facilities • Library facilities • Open space/recreation provision • Pebblebed Heaths habitat mitigation • Sport and Leisure Provision • Transport

2 Latest Allocation of CIL Funds

The CIL funds held by the Council are distributed periodically by inviting bids from infrastructure providers listed in the Infrastructure Delivery Plan.

In total 7 bids, with a combined funding request of £ 9.9million, were approved by the Council’s Strategic Planning Committee on 19 May 2025. The supported bids all benefit from match funding from other sources but the monies from CIL will ensure that these can be delivered for the benefit of the community.

Tithebarn/Mosshayne Primary School (  £ 4.5m ) Exmouth Rugby Club changing room extension A new primary school will be built to support (  £ 80k ) families in the growing Tithebarn community, The expansion will add two RFU compliant changing reducing pressure on nearby schools and ensuring rooms to support the growing number of women’s that local children can go to school close to where and girls’ rugby teams, strengthening opportunities they live. Funding is conditional on detailed costings for female participation in the sport. The original from Devon County Council. CIL award was reduced from £ 100k following confirmation of partial VAT recovery by the bidder Pinhoe Surgery extension (  £ 800k ) An extension to Pinhoe Surgery will provide six Mosshayne Lane to Station Road multi-use path additional clinical rooms to accommodate rising (  £ 1.8m ) patient numbers from new housing developments. A 1.5km off-road walking, wheeling, and cycling route will improve active travel links between Honiton Sports provision enhancements (  £ 601k ) Cranbrook and Exeter, and beyond, promoting Honiton will benefit from new football and rugby sustainable transport. facilities, including youth football pitches, a floodlit 3G pitch, and rugby club upgrades, boosting local London Road footpath and cycle enhancements sports participation. (  £ 750k ) This project will fill critical gaps in the Cranbrook Clyst Meadows Country Park, Broadclyst footpath and cycle network, ensuring safer (  £ 1.383m ) pedestrian and cycling routes between key A new 10 hectare country park will provide much community areas. needed green space and wildlife protection to mitigate impacts on the protected habitats of the Exe Estuary and Pebblebed Heaths National Nature Reserve.

3 Community Infrastructure Levy Matters Community Infrastructure Levy Regulations (  2019 Amendment ) Regulation 121A Schedule 2 Section 1

Section 1

a The total value of CIL set out in all demand notices issued £  4,035,694.52 in the reported year.

b The total amount of CIL receipts for the reported year £ 1,888,007.75

c The total amount of CIL receipts, collected by the authority, £ 10,113,007.29 or by another person on its behalf, before the reported year but which have not been allocated

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
4a. Infrastructure Funding Statement 2025Report 1.7 MB DownloadRead as text
PDF
Infrastructure Funding StatementReport 156 KB Download

At this meeting

Whole meeting

Who was there

11 of 20 attended
JB
Councillor Jessica BaileyCommittee Member, present
KB
Councillor Kevin BlakeyCommittee Member, present
OD
Councillor Olly DaveyCommittee Member, present
PF
Councillor Peter FaithfullCommittee Member, present
PF
Councillor Paula FernleyCommittee Member, apologies
CF
Councillor Charlotte FitzgeraldCommittee Member, present
PH
Councillor Paul HaywardCommittee Member, absent
MH
Councillor Mike HoweVice-Chair, present
BI
Councillor Ben InghamCommittee Member, present
GJ
Councillor Geoff JungCommittee Member, present
DL
Councillor Dan LedgerCommittee Member, absent
YL
Councillor Yehudi LevineCommittee Member, apologies

All 20 on the meeting page

On this subject at East Devon

Search all
  1. Infrastructure Funding StatementThis decision
  2. Infrastructure Funding StatementNoted
  3. Infrastructure Funding StatementNoted
  4. Infrastructure Funding StatementNoted
  5. Infrastructure Funding StatementApproved
  6. Infrastructure Funding Statement 2019/20Noted

More from East Devon Strategic Planning Committee

All decisions
MeetingDecisionOutcome
14 Jul 2026 Response to consultation on the Mid Devon Local PlanThat the Strategic Planning Committee endorsed the officer recommended response to Mid Devon District Council’s Local... Agreed Open
5 May 2026 Heritage Strategy 2024-2042That the updated second Heritage Strategy (2024 – 2042) be adopted in support of the Council’s duty towards the histo... Approved Open
5 May 2026 Self-Build and Custom House-Building Update and Monitoring Report for 2024 - 2025That the draft monitoring report for use in planning decisions (both planning policy and development management) be e... Agreed Open
3 Mar 2026 Cranbrook Category 4 Infrastructure ContributionsThe Committee recommends to the Cabinet that the ‘Mechanism for the allocation of category 4 infrastructure contribut... Approved Open
3 Mar 2026 Habitat Regulation Non-Infrastructure ContributionsRESOLVED That the revised non-infrastructure habitat mitigation contributions as shown in table 3 within the report b... Approved Open