AI summaryEast Devon audit committee reviewed the council's strategic and operational risk registers, noting no high-rated strategic risks and reinstating quarterly reporting through a new InPhase system.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedStrategic and operational risks considered by the committee
MoneyNo financial implications in the report
What happens nextQuarterly risk reportsReporting to be reinstated with the new InPhase system
Who it affectsCouncil services and residentsRisks span housing, finance, waste, planning and governance
What was decided
The committee reviewed and considered the Strategic and Operational Risks as part of its responsibility to ensure risks are being monitored and control actions implemented by Directorates and Services across the Authority. [D] Report P4
Quarterly risk reporting to the committee is to be reinstated now that the risk register is being managed again following a gap since the July 2025 report. [1.2] Report 1.2, 1.3
Why
Anticipating, identifying and managing risks at strategic and operational level is needed to deliver activities effectively and meet audit and compliance requirements. [P4] Report P4
Monitoring risks and maintaining a Risk Register allows risks to be systematically tracked and progress of control actions to be monitored, underpinning good governance and service continuity. [P4] Report P4
What happens next
Operational risk FIN8, relating to the new finance system, is to be deleted from the Operational Risk Register. [1.7] Report 1.7
A Community Infrastructure Levy review is needed, and the council will seek government and other funding to deliver required infrastructure. [P15] Report P15
The transition of waste services to a Local Authority Trading Company, East Devon Environmental Services Ltd, is being managed as a full project with its own risk register, targeting 1st July 2026. [P15] Report P15
Options considered
Rejected: Continue with current reporting arrangement. Quarterly oversight expected since July 2025 needs to be reinstated [1.2] Report 1.2
Chosen: Reinstate quarterly risk reports using the new InPhase system. New system streamlines risk management and enhances transparency [1.2, 1.3] Report 1.2, 1.3
Implications
Risk: Failure to identify, assess, monitor, review and manage risks could impact the council financially, reputationally and operationally. [P7] Report P7
Legal: It is important that members are regularly updated on the organisation's key strategic risks. [P17] Report P17
Equalities: Low impact identified for equalities. [P7] Report P7
Climate: Low impact identified for climate change. [P7] Report P7
Other: Government changes to housing requirements have significantly worsened the council's housing land supply position. [P14] Report P14
Who and where
Council Directorates and Services responsible for implementing control actions [P4] Report P4
Risk Owners across the authority, following a review in February 2026 [P3] Report P3
Communities affected by housing land supply shortfalls [P14] Report P14
Residents reliant on waste and recycling services during the move to a new delivery model [P15] Report P15
Timeline
July 2025: Last risk report presented to the committee before the Interim Performance and Risk Team Leader departed [1.2, 1.8] Report 1.2
Late January 2026: Interim Corporate Lead for Programmes and Strategies joined the council [1.2] Report 1.2
February 2026: Risks reviewed by Risk Owners in conjunction with the Interim Corporate Lead [P3] Report P3
March 2026: Date of the strategic risk position reported in Appendix A [1.5] Report 1.5
19 March 2026: Risk report considered by the Audit and Governance Committee [P2] Report P2
1st July 2026: Target date for LATCo East Devon Environmental Services Ltd to be safe and legal [P15] Report P15
Plain English for the jargon
Risk Register: A list setting out identified risks, used to systematically track them and monitor progress of control actions [P4]
Mitigated risk: The level of risk remaining after control actions have been applied [1.5, 1.7]
CIL: Community Infrastructure Levy, a charge developers pay to fund local infrastructure [P15]
LATCo: Local Authority Trading Company; here, East Devon Environmental Services Ltd, taking on waste service delivery [P15]
InPhase: New software package being introduced for managing and reporting performance and risk [1.3]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item56
Resolved
That the Audit and Governance Committee reviews and considers the Strategic and Operational Risks as part of the Council’s responsibility to ensure all risks were being monitored, and that control actions were implemented by Directorates and Services across the Authority.
Word for word from the decision East Devon published for this meeting.Source: democracy.eastdevon.gov.uk
Date of Meeting 19 March 2026 Document classification: Part A Public Document Exemption applied: None Review date for release N/A
Risk Report Report summary: The latest risk information is provided to allow the Audit and Governance Committee to monitor the risk status of Strategic and Operational Risks. This follows a review of risks by responsible officers (Risk Owners) in conjunction with the Interim Corporate Lead – Programmes and Strategies during February 2026.
Is the proposed decision in accordance with: Budget Yes ☒ No ☐ Policy Framework Yes ☒ No ☐ Recommendation: That the Audit and Governance Committee reviews and considers the Strategic and Operational Risks as part of the Council’s responsibility to ensure all risks are being monitored, and that control actions are implemented by Directorates and Services across the Authority. Reason for recommendation: To ensure its activities are delivered effectively, and that audit and compliance requirements are met, it is important that East Devon District Council anticipates, identifies and manages relevant risks at a strategic and operational level. Monitoring risks and maintaining a Risk Register allows risks to be systematically tracked and progress of implementing control actions is monitored. These are essential practices that underpin good governance, help to ensure service continuity and is party of the responsible management of the Council.
Officer: Barry James, Interim Corporate Lead – Programmes and Strategies, [email protected]
Portfolios: ☐ Assets and Economy ☐ Communications and Democracy ☒ Council, Corporate and External Engagement ☐ Culture, Leisure, Sport and Tourism ☐ Environment - Nature and Climate ☐ Environment - Operational ☒ Finance ☐ Place, Infrastructure and Strategic Planning ☐ Sustainable Homes and Communities
Equalities impact Low Impact Climate change Low Impact Risk: High Risk; Failure to identify, assess, monitor, review and manage risks could impact negatively (i.e. financial, reputational, operationally) on the council Links to background information Link to Council Plan Priorities (check which apply) ☐ A supported and engaged community ☐ Carbon neutrality and ecological recovery ☐ Resilient economy that supports local business ☒ Financially secure and improving quality of services
Report in full 1.1 The last report to the Audit & Governance Committee was provided in July 2025 prior to the departure of the Interim Performance and Risk Team Leader. Since that time Risk is the responsibility of the Interim Corporate Lead – Programmes and Strategies (who joined EDDC in late January 2026).
1.2It is noted that the expectation expressed in the July 2025 meeting was that a quarterly report would be presented to the Committee to ensure regular oversight. This regime can now be reinstated with the reallocation of managing the risk register.
1.3The Council is introducing a new system for managing and reporting both performance and risk. InPhase is a software package which provides the new basis for risk management as well as to streamline our management systems, support continuous improvement and enhance transparency.
1.4Strategic Risks – there are a total of 18 risks on the Strategic Risk Register split between Governance (9 risks), Housing and Health (5), Finance (2), Place (1) and the Chief Executive (1).
1.5Appendix A provides a report as of 1 st March 2026; the mitigated risks are presented with 13 Medium and 5 Low Risk. There are no risks classed as High.
1.6Operational Risks – there 106 risks on the Operational Risk Register. Risks with a mitigated risk rating of High are noted below:
a. Pla22 – Place (Planning Policy): risk associated with failing to demonstrate a 5-year housing land supply. Risk Owner Comments: Government changes to housing requirements have significantly worsened our housing land supply position.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.