AI summaryEast Devon Planning Committee approves 70-bed care home on former Mill Water School site in Honiton, subject to conditions and a Section 106 agreement, with extra requirements on construction traffic and heat pump noise.
Written from the decision and the officer reportPDF Pro
OutcomeApproved70-bed care home, subject to S106 and extra conditions
MoneyNot stated
What happens nextSection 106 Agreement completionPlus compliance with 13 listed conditions and extra ones
Who it affectsHoniton residents and elderly care provisionAdjacent to Littletown Primary School
What was decided
Approved the application for a 70-bed care home on the former Mill Water School site, in line with the officer recommendation, despite a contrary ward member view. Report P1, P2, P239
Made approval subject to completion of a Section 106 Agreement, plus 13 standard conditions covering drainage, tree protection, construction, ecology, parking, materials, landscaping and waste. Report P239, P240, P241, P242, P243, P244, P245, P246, P247, P248, P249, P250, P251, P252, P253, P254, P255, P256, P257, P258, P259, P260, P261, P262, P263, P264, P265
Added two further conditions: construction traffic must avoid Littletown Primary School drop off and pick up times, and air source heat pump noise must be assessed and mitigated before installation.
Why
There is a documented shortfall of 183 care home beds in Honiton and 537 across East Devon, with the Local Plan identifying a need for 50 care or extra care home spaces in Honiton. Report P4, P186, P189, P191
The site lies within the Honiton built up area boundary, on previously developed land, and the loss of the former school use is not harmful as the facility relocated to Bicton College in 2015 and still serves the area. Report P3, P162, P175, P184
Technical consultees raised no overriding concerns: the County Highway Authority had no objection, the Lead Local Flood Authority withdrew its objection, and impacts on amenity, design, trees and protected species were found acceptable with mitigation. Report P5, P6, P7, P28, P34, P35, P44, P45, P201, P209, P212, P221, P228
What happens next
The Section 106 Agreement must be completed before the permission is finalised.
Pre commencement conditions require submission and approval of a detailed drainage design, tree protection details, a Construction and Environment Management Plan, and a waste audit statement. Report P242, P243, P244, P245, P246, P247, P248, P249, P252, P253, P257, P258, P259, P260
An amended CEMP must set construction traffic timings outside school drop off and pick up periods, and any air source heat pumps must be supported by a noise assessment and any required mitigation before use.
Options considered
Chosen: Approve with conditions, per officer recommendation. Care home need, sustainable location, acceptable technical impacts, and compliance with the development plan outweighed identified harms. Report P236, P237, P238
Rejected: Refuse, reflecting the ward member, parish council and 21 objector concerns. Concerns on overdevelopment, traffic, parking, overlooking, ecology, drainage and infrastructure were not found to be severe or demonstrably harmful when weighed against policy and technical evidence. Report P7, P11, P12, P16, P26, P83, P105
Implications
Equalities: The facility will provide 70 beds, including for people with dementia and other complex needs, responding to an ageing population and an identified care bed shortfall. Report P164, P186, P187, P189
Legal: Approval is conditional on completing a Section 106 Agreement, and a holding ecology objection noted that Biodiversity Net Gain validation requirements had not yet been demonstrated. Report P62, P63
Financial: No affordable housing is required because the use is a care home within Use Class C2. Report P51
Climate: Surface water drainage achieves a 97 to 98 percent betterment over existing run off, and air source heat pump noise must be assessed and mitigated. Report P227
Risk: Construction impacts, including possible piling, are to be controlled through a CEMP, with bore piling preferred over driven piling due to ground conditions. Report P235, P253
Who and where
Future residents and staff of the 70-bed care home Report P1, P164, P165, P166, P167
Adjacent residents on Gronau Close, Holy Close, Hazelwood Close, Gosceline Walk and Coly Road Report P159, P194, P195
Littletown Primary School and its pupils, especially around drop off and pick up times Report P11, P12, P100, P102, P184
People needing care home places in Honiton and East Devon Report P4, P189
Timeline
16.08.1979: Planning permission granted for enclosed swimming pool and changing rooms on the site. Report P110
09.12.1986: Approval for extensions. Report P111
January 2015: Mill Water School relocated to a purpose built school at Bicton College. Report P184
24 June 2025: The ward member for Honiton St Michaels raised objections and requested committee determination. Report P11, P12, P13
1 July 2025: Contaminated Land Officer recommended a condition for unexpected contamination. Report P42, P43
21 July 2025: Parish or town council resolved to object, with 4 in favour of objecting, 1 against, 0 abstentions. Report P14, P15, P16, P26
22 July 2025: South West Water set out drainage hierarchy and connection requirements. Report P64, P65, P66, P67, P68, P69, P70, P71, P72, P73, P74, P75, P76, P77
29 April 2026: Devon County Council Flood Risk Management Team withdrew its objection subject to pre commencement drainage conditions. Report P44, P45, P46, P47, P48, P49, P50
9 June 2026: East Devon Planning Committee approved the application with conditions.
Plain English for the jargon
Use Class C2: Planning use class for residential institutions such as care homes.
CEMP: Construction and Environment Management Plan, setting out how construction impacts are controlled.
Section 106 Agreement: A legal agreement between a developer and the local authority tied to a planning permission.
Biodiversity Net Gain (BNG): A requirement that development delivers a measured improvement in biodiversity, calculated using a statutory metric.
SuDS: Sustainable Drainage System, used to manage surface water run off.
TPO: Tree Preservation Order, protecting specific trees or groups from removal or works.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
Approved with conditions in accordance with officer recommendation, subject to completion of the Section 106 Agreement and subject to the following additional/amended conditions: CEMP condition to be amended to require details of timings for construction traffic moving to and from the site to take place outside of Littletown Primary School drop off and pick up times, to be agreed and adhered to. Prior to installation of any air source heat pumps within the site a technical statement shall be submitted to the Local Planning Authority to demonstrate whether noise mitigation measures are required. If required, the noise mitigation measures shall be provided prior to the air source heat pumps being brought into use and the measures shall be retained and maintained for the lifetime of the development Reason: In the interest of amenity in accordance with Policy D1 of the East Devon Local plan, 2013 to 2031
Word for word from the decision East Devon published for this meeting.Source: democracy.eastdevon.gov.uk
This application seeks full planning permission for the redevelopment of the former Mill Water School site in Honiton to provide a 70-bed care home (Use Class C2), together with associated access, parking, landscaping, and infrastructure works.
The proposal has been referred to Planning due to the recommendation differing from the Ward Member view.
The site lies within the built-up area boundary of Honiton and represents previously developed land in a sustainable location. The principle of development is therefore acceptable. While the site is allocated for housing in the emerging Local Plan, the adopted Local Plan carries greater weight and the proposal accords with it. The loss of the former school use is not considered harmful, as the facility has been relocated elsewhere in the district and continues to serve the area.
A key consideration is the demonstrable need for care accommodation. Evidence submitted with the application identifies a significant shortfall in care home provision within Honiton and across East Devon, both quantitatively and qualitatively. The delivery of a modern, purpose-built care facility attracts substantial weight in support of the proposal and aligns with national and local policy objectives to meet the needs of an ageing population.
The proposal has been assessed in relation to design, residential amenity, highway safety, drainage, ecology, and trees. While concerns have been raised regarding the scale of development and its relationship with surrounding properties, the scheme is
25/1259/MFUL considered acceptable in design terms and would not result in unacceptable harm to neighbouring amenity.
Although there is a high level of public objection, the impacts identified—particularly in relation to traffic, parking, and local character—are not considered to be severe or demonstrably harmful when assessed against policy and technical evidence.
Overall, the proposal represents sustainable development that complies with the Development Plan when read as a whole. The significant benefits of delivering much- needed specialist care accommodation outweigh the identified adverse impacts. The application is therefore recommended for approval, subject to planning conditions.
CONSULTATIONS
Local Consultations
Honiton St Michaels - Cllr Jenny Brown 24 June 2025
This is next to a school which causes havoc during pick up and drop of times. The development could create further traffic problems on an area already congested at peak times. Suitable parking provisions should be implemented to avoid further congestion, so, at the present time I cannot support this proposal.
If my view differs from the planning officer I would like this to go to committee.
Parish/Town Council 21 July 2025
The applicant and agent spoke in favour of the application. 5 members of the public spoke against the application. Cllr Collins provided his views on the application.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
26/0534/MOUT (Major) WHIMPLE & ROCKBEAREThe Appropriate Assessment be adopted. 2. Approved with conditions in accordance with officer recommendation subject ...
26/0535/MFUL (Major) WHIMPLE & ROCKBEAREThe Appropriate Assessment be adopted. 2. That the SANGS application be approved, subject to conditions and to the co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.