RESOLVED - that (A) the Executive be informed that the Joint Scrutiny Committees note the invest to save aspects of the Capital Programme and consider it is appropriately phased and the Programme should be approved; and (B) a written response be provided on shared-facility swimming pools’ expenditure .
Word for word from the decision East Hertfordshire published for this meeting.Source: democracy.eastherts.gov.uk
REPORT BY EXECUTIVE MEMBER FOR RESOURCES AND INTERNAL SUPPORT
CAPITAL PROGRAMME 2010/11 (REVISED) TO 2013/14
WARD(S) AFFECTED: ALL
Purpose/Summary of Report
• The report sets out proposals for the Council’s Capital Programme for the period 2010/11 (Revised) to 2013/14.
RECOMMENDATION FOR DECISION BY JOINT SCRUTINY COMMITTEE : that
(A) the draft Capital Programme 2010/11 (Revised) to 2013/14 be scrutinised; and
(B) comments be submitted to the Executive.
RECOMMENDATION FOR DECISION BY EXECUTIVE: that
(A ) any comments made by the Meeting of Joint Scrutiny Committees on 18 January 2011 be considered; and
(B) the new Capital Programme for the period 2010/11 (Revised) to 2013/14 be recommended to Council.
1.0Background 1 1.1 The capital programme approved by the Council in February 2010 has subsequently been updated and amended initially by items of slippage and other re-phasings following the 2009/10 Capital Out- turn position.
1.2A number of further amendments to the Programme have since been approved through the Council’s monthly Healthcheck process.
1.3In line with current annual budgetary processes a complete review of the current programme has been undertaken and a new draft programme is now proposed for the period 2010/11 (Revised) to 2013/14. Lead officers have submitted proposals for new schemes to be included within the Programme. Investment requirements linked to invest to save schemes have also been identified through the MTFP process.
2.0Report
2.1As a medium term Investment Plan, the Programme will continue to be developed in response to the Council’s priorities set out in changing strategies and service plans.
2.2The Draft Programme is attached at Essential Reference Paper ‘B'. The Programme is presented this year with various detailed schemes having been combined which will facilitate the overall management of resources. CMT will continue to manage projects at an individual level. Following the approach initiated last year, the aggregate of proposed spend on individual schemes has again been adjusted by a provision for slippage to produce a programme total against which total spending will be performance managed. The adjusted figures have been assumed for estimating the financing implications within the MTFP.
2.3The Executive will note that the revised budget for the current year of £6.87m reflects slippage of £0.20m compared to the “current approved” position of £7.07m (as adjusted) being reported through the Healthcheck report (November position).
2.4Existing rolling programmes of work have been continued up to 2013/14. These programmes will continue to provide funding in areas such as affordable housing, private sector renovation grants, the provision of play equipment, community grants, information technology upgrades as well as various environmental 2 initiatives.The programme for provision of the replacement of litter bins has been extended to 2013/14 and the ongoing budget for the provision of commercial waste bins reflects growth in this area of business. Increased revenue streams are anticipated.
2.5New Schemes
The Draft Programme at Essential Reference Paper ‘B’, includes proposals for a number of new schemes. These total just over £1.6m (including a redirection of resources to fund a new telephone system) and are shown in bold typeface and summarised separately for ease of reference. Provisions are included for the enhancement and improvement of the Council’s assets in line with the Council’s Asset Management Plan.
The proposed new schemes have been scrutinised in detail by the Corporate Management Team to ensure that projects are considered to be in line with the Council’s corporate priorities and that the phasing of the projects is appropriate having regard to available resources and project lead in times.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.