Resolved
RESOLVED – that the report be noted.
Audit Committee noted this item on Wednesday 23 March 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – that the report be noted.
East Hertfordshire District Council
Review of the Council's arrangements for securing financial resilience March 2011 Project specification
Contents Page
1 Summary of the review 2
2 Work plan 3
© 2010 Grant Thornton UK LLP. All rights reserved. 1 Summary of the review
1.1Context
Our 2010/11 Value for Money conclusion will be based upon two reporting criteria specified by the Audit Commission being: • Criteria 1 - The Council has proper arrangements in place for securing financial resilience • Criteria 2 - The council has proper arrangements for challenging how it secures economy, efficiency and effectiveness.
The guidance issued by the Audit Commission surrounding the first criteria requires auditors to consider whether the Council has robust financial systems and processes to manage effectively financial risks and opportunities and to secure a stable financial position that enables it to continue to operate for the foreseeable future.
1.2Our work
We will undertake a review of the Council's arrangements specifically looking at selected key indicators of performance, financial governance, strategic financial planning and financial control. Part of our work will involve detailed review of the robustness of aspects of the Medium Term Financial Plan, including realism of assumptions (e.g. staffing, inflation, interest rates, pension contributions) and detail of savings plans including supporting documentation and arrangements at the departmental level. We will not be conducting an audit of financial models produced by the Council.
1.3Benefits
The review will provide the Council with independent review and constructive challenge and will contribute to the Council's assurance around its management arrangements for securing financial resilience. We will provide the Council with a simple report (including Red/Amber/Green ratings) highlighting key strengths and areas where the Council could improve its arrangements. Our work is intended to help the Council to continually improve the robustness of its arrangements for dealing with the significant financial challenge ahead.
1.4Logistics
We anticipate carrying out the review in March to June 2011 and reporting the results to the September meeting of the Audit Committee (to be agreed with management). Our work will involve review of key documents and interviews with officers. The review will be managed by Nick Taylor and delivered using members of the audit team who are experienced in performing such reviews. We anticipate that the main point of contact at the Council, with whom we will agree the detailed work and report, will be Alan Madin, Director of Internal Services. 2 Work plan
2.1Key indicators of performance
Through consideration of the Council's own performance measures and operational objectives we will select some relevant key indicators of performance for benchmarking analysis. We will then be able to review the Council's position against those of similar Councils and make some observations in the selected areas of review.
The ratios considered in this will include some or all of the following as well as other additional measures:
• Working capital ratio • Out-turn against budget • Useable reserves to gross revenue expenditure (excluding housing and council tax benefits) • Long term borrowing to tax revenue • Gross expenditure (excluding housing and council tax benefits) per head of population • Share of net revenue expenditure committed to long term contracts without provision to reduce activity. Investment income as a share of net revenue expenditure • Sickness absence levels • Council tax income as proportion of net revenue expenditure • Financing revenue spend from grants, council tax, NNDR and other income • Government grants as proportion of revenue expenditure.
2.2Strategic financial planning
This area of our work is specifically concerned with the Council's Medium Term Financial Plan (MTFP) for revenue and capital expenditure and will focus on the following areas;
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
External Auditor's report: Financial Resilience: Terms of ReferenceReport | 89 KB | DownloadRead as text |
Follow Audit Committee at East Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jan 2016 | Training item - Risk ManagementRESOLVED – that the presentation be received. | Decided | Open |
| 20 Jan 2016 | Minutes - 25 November 2015RESOLVED - that the Minutes of the meeting held on 25 November 2015 be confirmed as a correct record and signed by th... | Decided | Open |
| 20 Jan 2016 | External Audit - Grants Claim Certification Work 2014/15RESOLVED – that the report be received. | Decided | Open |
| 20 Jan 2016 | Treasury Management Strategy Statement 2016/17RESOLVED – that (A) the Treasury Management Strategy and Annual Investment Strategy detailed in paragraphs 2.1 – 2.2 ... | Decided | Open |
| 20 Jan 2016 | Shared Internal Audit Service - Audit Plan Update ReportRESOLVED – that (A) the Internal Audit Progress report be noted; (B) the amendments to the Audit Plan as at 1 January... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.