Internal Audit Service 2010/11

Decided Finance 4 papers

Audit Committee decided this item on Tuesday 12 July 2011. Below is the council's own wording, with the papers it was decided on.

Item158

Resolved

RESOLVED – that the report be received.
Word for word from the decision East Hertfordshire published for this meeting. Source: democracy.eastherts.gov.uk

Follow this further

Built from East Hertfordshire's papers

What the report saysPro

Report to Audit Committee

Recommendation

(A) That the report be received.

Background

1.1A report on the work of the Internal Audit Service is produced each year by the Internal Audit and Business Improvement Manager. This annual report contains a summary of activities performed by the team during 2010/11.

2.0Report

2.1The Annual Report is attached as Essential Reference Paper ‘B’.

3.0Implications/Consultation

3.1Information on any corporate issues and consultation associated with this report can be found within Essential Reference Paper ‘A’.

Background papers

Draft Strategic Internal Audit Plan 2010-2013 – Audit Committee 17 March 2010. Contact Member: Councillor Michael Tindale Executive Member for Resources & Internal Support

Contact Officers: Alan Madin Director of Internal Services- Ext 1406

Report Author: Chris Gibson Internal Audit and Business Improvement Manager- Ext 2073 ESSENTIAL REFERENCE PAPER ‘A’

Contribution to Fit for purpose, services fit for you the Council’s Deliver customer focused services by maintaining and Corporate developing a well managed and publicly accountable Priorities/ organisation. Objectives:

Consultation: No public or partner consultations were required during the preparation of this report. Legal: There are no additional legal implications to those already contained in this report. Financial: There are no additional financial implications to those already contained in this report. Human There are no additional human resource implications to Resource: those already contained in this report. Risk There are no additional risk management implications to Management: those already contained in this report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Service 2010/11Report 27 KB DownloadRead as text
PDF
Internal Audit Service ERP CReport 121 KB Download
PDF
Internal Audit Service ERP D: Audit PlanReport 24 KB Download
PDF
Internal Audit Service ESP BReport 137 KB Download

At this meeting

Whole meeting

On this subject at East Hertfordshire

Search all
  1. Internal Audit Service 2010/11This decision
  2. Annual Assurance Statement and Internal Audit Annual Report 2025/26Noted
  3. Shared Internal Audit Service - Internal Audit Plan Report 2026/27Approved
  4. Shared Internal Audit Service - Progress ReportNoted
  5. Shared Internal Audit Service - Progress ReportNoted
  6. Annual Assurance Statement and Internal Audit Annual Report 2024/25Noted

More from East Hertfordshire Audit Committee

All decisions
MeetingDecisionOutcome
20 Jan 2016 Training item - Risk ManagementRESOLVED – that the presentation be received. Decided Open
20 Jan 2016 Minutes - 25 November 2015RESOLVED - that the Minutes of the meeting held on 25 November 2015 be confirmed as a correct record and signed by th... Decided Open
20 Jan 2016 External Audit - Grants Claim Certification Work 2014/15RESOLVED – that the report be received. Decided Open
20 Jan 2016 Treasury Management Strategy Statement 2016/17RESOLVED – that (A) the Treasury Management Strategy and Annual Investment Strategy detailed in paragraphs 2.1 – 2.2 ... Decided Open
20 Jan 2016 Shared Internal Audit Service - Audit Plan Update ReportRESOLVED – that (A) the Internal Audit Progress report be noted; (B) the amendments to the Audit Plan as at 1 January... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies