Resolved
RESOLVED – that the action taken to mitigate and control strategic risks during the period 1 July to 30 September 2011 be noted.
Audit Committee noted this item on Wednesday 23 November 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – that the action taken to mitigate and control strategic risks during the period 1 July to 30 September 2011 be noted.
1.1The 2011/12 Strategic Risk Register was considered by Audit Committee on 21 September 2011. Actions taken to mitigate risks have been updated. This is attached at Essential Reference Paper ‘B’
1.2Risk management remains a key business process and a sound system of internal control.
2.0Report
2.1Risk is defined as something happening that may have an impact on the achievement of the Council’s objectives. Risk management is about managing threats and opportunities to create an environment of “no surprises”. By managing risks effectively, the Authority is placed in a stronger position to deliver services in accordance with its corporate priorities. By managing opportunities, it is better positioned to provide continuous improvement in its services and better value for money.
2.2The following system of rating has been adopted: Rating the potential impact if the risk was to occur using the following scores
5 Catastrophic 4 Major long term impact 3 Major short term impact 2 Moderate long term impact 1 Moderate short term impact 0 Little impact
Rating the likelihood of occurrence using the following scores
5 Highly probable (95% or more chance) 4 Very probable (70% to 95% chance) 3 Probable (30% to 70% chance) 2 Moderate (10% to 30% chance) 1 Unlikely (less than 10% chance) 0 Remote (below 1% chance in foreseeable future)
These scores are further assessed to classify whether risks are considered to be critical, caution / contingency or control.
2.3Attached at Essential Reference Paper ‘B’ is a list detailing mitigating actions carried out during the period 1 July to 30 September 2011, together with planned mitigating actions. This information was presented to Executive on 8 November 2011 as part of the Corporate Healthcheck report. (Any comments received will be reported verbally). Full progress comments can be accessed by referring to the Council’s performance management system, Covalent (www.covalentcpm.com/eastherts).
3.0Implications/Consultations
3.1Information on any corporate issues and consultation associated with this report can be found within Essential Reference Paper ‘B’.
Risk Monitoring Report (May and June 2011) – Audit Committee 21 September 2011. Contact Member: Councillor Anthony Jackson Leader of the Council
Contact Officer: Simon Drinkwater Director of Neighbourhood Services Ext. 1405
Report Author: Graham Mully Risk Assurance Officer Ext. 2166 ESSENTIAL REFERENCE PAPER ‘A’
Contribution to Fit for purpose, services fit for you the Council’s Deliver customer focused services by maintaining and Corporate developing a well managed and publicly accountable Priorities/ organisation. Objectives (delete as appropriate): Consultation: There are no specific consultation implications arising directly from this report. Legal: There are no specific legal implications arising directly from this report. Financial: There are no specific financial implications arising directly from this report. Human There are no specific human resource implications Resource: arising directly from this report. Risk There are no additional risk management implications to Management: those already contained in this report. However, it should be noted that if East Herts did not have a risk management monitoring process, the Authority would be seen to be not managing risks appropriately, which would have a significant negative impact on recommendations made by the External Auditors through the Annual Audit Letter.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk Management monitoring report 1 August 2011 to 30 September 2011Report | 32 KB | DownloadRead as text |
PDF |
Strategic Risk Register July to Sept 11: ERP BReport | 56 KB | Download |
Follow Audit Committee at East Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jan 2016 | Training item - Risk ManagementRESOLVED – that the presentation be received. | Decided | Open |
| 20 Jan 2016 | Minutes - 25 November 2015RESOLVED - that the Minutes of the meeting held on 25 November 2015 be confirmed as a correct record and signed by th... | Decided | Open |
| 20 Jan 2016 | External Audit - Grants Claim Certification Work 2014/15RESOLVED – that the report be received. | Decided | Open |
| 20 Jan 2016 | Treasury Management Strategy Statement 2016/17RESOLVED – that (A) the Treasury Management Strategy and Annual Investment Strategy detailed in paragraphs 2.1 – 2.2 ... | Decided | Open |
| 20 Jan 2016 | Shared Internal Audit Service - Audit Plan Update ReportRESOLVED – that (A) the Internal Audit Progress report be noted; (B) the amendments to the Audit Plan as at 1 January... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.