RESOLVED - that a waiver of the EHC Procurement Regulations [in accordance with PR 12.1] be approved, to allow SLM Ltd, the Council’s contracted leisure management contractor, to purchase gym equipment and associated packages on the Council’s behalf to secure better value for money than the normal purchasing process.
Word for word from the decision East Hertfordshire published for this meeting.Source: democracy.eastherts.gov.uk
Client Capital Strategy Group Project Gym equipment replacement, Fanshawe & Leventhorpe Document Project Initiation Document Author Mark Kingsland Published Date 23.9.2011 Version 4
Change History
This document is to be submitted to the project team for approval and signoff. Thereafter amendments are to be approved by the appropriate Change Control processes.
Issue Date of Issue Comments / Reason for change 1.00 20.7.2011 Initial Draft 2.00 1.8.11 1st revision, responded to GAR comments 3.00 3.8.11 2nd revision, revised value of capital requested, updated timescale.
4.0023.9.11 3rd revision, CapEx details revised after discussions with SLM
Distribution
Name Position Organisation Will O’Neill Head of Customer and East Herts Council Community Services Alan Madin Director of Internal Services East Herts Council George Robertson Director of Customer and East Herts Council Community Services
2. Introduction Both Fanshawe Pool & Gym and Leventhorpe Pool & Gym are joint provision sites, facilities owned by Herts County Council and managed by SLM as East Herts Council’s leisure provider.
Originally, the funding for the replacement of the gym/fitness equipment for both the facilities was included in SLM’s Fee Schedule within the Leisure Management Contract. Their business model upon which their bid was based included £27,552, plus depreciation for Leventhorpe and £52,395, plus depreciation, for Fanshawe, spread over the final six years of the contract period.
If the Council is able to fund equipment replacement up to the value of £113,000 the leisure revenue medium term financial plan (MTFP) has the opportunity to show an engineered reduction in the contract payment of £22,100 annually, against the agreed contract fee to SLM from January 2012, generating a gross revenue saving of £154,700 over the remaining seven years of the contract.
The purchase of the required gym equipment will be in the region of £113,000 split between the two sites. Replacement gym equipment at Fanshawe cost; £84,000 from January 2012 and replacement gym equipment at Leventhorpe cost; £29,000 at an agreed date between April 2012 and March 2013. There is also a trade in value of around £16,500.00 for the existing gym equipment at Fanshawe Pool & Gym.
3. Objective £22,100 annual reduction in contract payments against agreed contract fee to SLM from January 2012, generating a gross revenue saving of £154,700 over the remaining seven years of the contract.
To replace aged gym equipment at Fanshawe Pool and Gym in January 2012 and Leventhorpe Pool and Gym at an agreed date between April 2012 and March 2013.
To allow these facilities to compete, to maintain and develop the service offered to users from the surrounding areas and to encourage residents to lead a healthy lifestyle.
4. Scope Inclusions – Specification for new equipment Purchase of new equipment, including warranties’ etc. Removal of the old gym equipment Delivery of the new equipment Installation and commissioning of the new equipment Gym equipment replacement, Fanshawe & Leventhorpe Project Initiation Document
5. Description of Work
Inputs/Outputs Client side time resource Equipment Specification Tendering process Quotation analysis Coordination of delivery and gym closure to minimise disruption.
Deliverables Appropriate affordable equipment at both sites
Interfaces Project Manager/Agent
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Treasury Management 2025/26 OutturnRESOLVED – Executive recommended to Council that it approve the Treasury Management Annual Outturn 2025/26, including...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.