Executive, Tuesday 6 December 2011 at 7.00pm

Replacement Gym Equipment at Fanshawe and Leventhorpe pools (2)

Approved Executive 2 papers

Executive approved this item on Tuesday 6 December 2011. Below is the council's own wording, with the papers it was decided on.

Item473

Resolved

RESOLVED - that a waiver of the EHC Procurement Regulations [in accordance with PR 12.1] be approved, to allow SLM Ltd, the Council’s contracted leisure management contractor, to purchase gym equipment and associated packages on the Council’s behalf to secure better value for money than the normal purchasing process.
Word for word from the decision East Hertfordshire published for this meeting. Source: democracy.eastherts.gov.uk

Follow this further

Built from East Hertfordshire's papers

What the report saysPro

Report to Executive

Gym equipment replacement, Fanshawe & Leventhorpe Project Initiation Document

Project Champion: Head of Customer and Community Services Version: 4 Date: 23rd September 2011

Gym equipment replacement, Fanshawe & Leventhorpe (PID)

East Herts District Council Council Offices, The Causeway Bishop’s Stortford Hertfordshire

Tel: 01279 501508 Fax: 01279 502015 Gym equipment replacement, Fanshawe & Leventhorpe Project Initiation Document 1. Document Control

Document

Client Capital Strategy Group Project Gym equipment replacement, Fanshawe & Leventhorpe Document Project Initiation Document Author Mark Kingsland Published Date 23.9.2011 Version 4

Change History

This document is to be submitted to the project team for approval and signoff. Thereafter amendments are to be approved by the appropriate Change Control processes.

Issue Date of Issue Comments / Reason for change 1.00 20.7.2011 Initial Draft 2.00 1.8.11 1st revision, responded to GAR comments 3.00 3.8.11 2nd revision, revised value of capital requested, updated timescale.

4.0023.9.11 3rd revision, CapEx details revised after discussions with SLM

Distribution

Name Position Organisation Will O’Neill Head of Customer and East Herts Council Community Services Alan Madin Director of Internal Services East Herts Council George Robertson Director of Customer and East Herts Council Community Services

Abbreviations

Corporate Management Team – CMT Sport & Leisure Management Ltd - SLM Gym equipment replacement, Fanshawe & Leventhorpe Project Initiation Document

2. Introduction Both Fanshawe Pool & Gym and Leventhorpe Pool & Gym are joint provision sites, facilities owned by Herts County Council and managed by SLM as East Herts Council’s leisure provider.

Originally, the funding for the replacement of the gym/fitness equipment for both the facilities was included in SLM’s Fee Schedule within the Leisure Management Contract. Their business model upon which their bid was based included £27,552, plus depreciation for Leventhorpe and £52,395, plus depreciation, for Fanshawe, spread over the final six years of the contract period.

If the Council is able to fund equipment replacement up to the value of £113,000 the leisure revenue medium term financial plan (MTFP) has the opportunity to show an engineered reduction in the contract payment of £22,100 annually, against the agreed contract fee to SLM from January 2012, generating a gross revenue saving of £154,700 over the remaining seven years of the contract.

The purchase of the required gym equipment will be in the region of £113,000 split between the two sites. Replacement gym equipment at Fanshawe cost; £84,000 from January 2012 and replacement gym equipment at Leventhorpe cost; £29,000 at an agreed date between April 2012 and March 2013. There is also a trade in value of around £16,500.00 for the existing gym equipment at Fanshawe Pool & Gym.

3. Objective £22,100 annual reduction in contract payments against agreed contract fee to SLM from January 2012, generating a gross revenue saving of £154,700 over the remaining seven years of the contract.

To replace aged gym equipment at Fanshawe Pool and Gym in January 2012 and Leventhorpe Pool and Gym at an agreed date between April 2012 and March 2013.

To allow these facilities to compete, to maintain and develop the service offered to users from the surrounding areas and to encourage residents to lead a healthy lifestyle.

4. Scope Inclusions – Specification for new equipment Purchase of new equipment, including warranties’ etc. Removal of the old gym equipment Delivery of the new equipment Installation and commissioning of the new equipment Gym equipment replacement, Fanshawe & Leventhorpe Project Initiation Document

5. Description of Work

Inputs/Outputs Client side time resource Equipment Specification Tendering process Quotation analysis Coordination of delivery and gym closure to minimise disruption.

Deliverables Appropriate affordable equipment at both sites

Interfaces Project Manager/Agent

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gym Equipment: ERPReport 62 KB DownloadRead as text
PDF
Replacement Gym Equipment at Fanshawe and Leventhorpe pools (2)Report 40 KB Download

At this meeting

Whole meeting

On this subject at East Hertfordshire

Search all
  1. Replacement Gym Equipment at Fanshawe and Leventhorpe pools (2)This decision
  2. Replacement Gym Equipment at Fanshawe and Leventhorpe poolsApproved

More from East Hertfordshire Executive

All decisions
MeetingDecisionOutcome
8 Sep 2026 Minutes – 14 July 2026RESOLVED – that the Minutes of the meeting held on 14 July 2026 be approved as a correct record and signed by the Lea... Approved Open
8 Sep 2026 Financial Management 2026/27 - Quarter 1 forecast to year enda) To note that the Revenue forecast position is a £440k overspend as of the end of June 2026; and b) Note the Capita... Noted Open
8 Sep 2026 Strategic Risk Register Q1 monitoring and Annual Review of Risk Management Strategya) The 2026/27 quarter one corporate risk register and actions being taken to control and mitigate risk be noted. b) ... Noted Open
8 Sep 2026 Treasury Management 2025/26 OutturnRESOLVED – Executive recommended to Council that it approve the Treasury Management Annual Outturn 2025/26, including... Approved Open
8 Sep 2026 Future of Water Lane Halla) That spend of up to £22,500 is approved for legal fees and costs to support Executive in considering a community a... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies