Resolved

RESOLVED – that (A) the revised completion dates against the 2011/12 Service Plan actions be noted; and (B) the comments made by Corporate Management Team in congratulating staff, be endorsed.
Word for word from the decision East Hertfordshire published for this meeting. Source: democracy.eastherts.gov.uk

Follow this further

Built from East Hertfordshire's papers

What the report saysPro

Report to Community Scrutiny Committee

Background

1.1The 2011/12 Service Plans were scrutinised by the joint meeting of Scrutiny Committees held on 15 February 2011 and approved by the Executive at its meeting on 8 March 2011. Community Scrutiny received a report detailing progress as at the end of September 2011 at its meeting on 22 November 2011. This report details progress as at the end of March 2012 for the following services:

o Community and Cultural Services

o Health and Housing

o Licensing and Community Safety

o Revenues and Benefits

1.2The Corporate Management Team (CMT) is pleased to commend the progress against service plans to Members. While there are some actions in the service plans which have required changes to their timetable, CMT congratulates Heads of Service and staff for delivering well, particularly in the context of the difficult times of 2011/12. C3W, shared services, staffing restructure, delivering efficiencies and severe recruitment constraints have made the operating environment extremely challenging for Heads of Service, managers and staff across the organisation.

1.3Going forward this is the last time the monitoring of service plan actions will be presented in this format. For 2012/13 a different approach to reporting on service plan achievements will be adopted. However the report will always highlight revised completion dates and actions that have been deferred.

2.0Report

2.1In total, there are 29 actions in the 2011/12 Service Plans relevant to Community Scrutiny Committee, of which:

76% (22) actions have been achieved

10% (3) on target

14% (4) actions have had their completion date revised as set out in Essential Reference Paper “B”)

2.2An overview of the achievements by Corporate Priority can be summarised as follows:-

Promoting prosperity and well being; providing access and opportunities. Enhance the quality of life, health and wellbeing of individuals, families and communities, particularly those who are vulnerable.

7 actions have been achieved

2 actions are on target

2 actions have had their completion dates revised as set out in Essential Reference Paper “B”.

Some of the key achievements were: o New standards for caravan sites have been approved by Members. A caravan inspection plan has been agreed and work has started on improving the conditions of the mobile home sites in East Herts. (Reported to Community Scrutiny Committee on 22 November 2011)

o With the exception of one or two applications that are not yet Citrix compliant, the rollout of home, remote and flexible working for staff in Revenues and Benefits has been completed in accordance with the Changing the Way We Work agenda. (Reported to Community Scrutiny Committee on 22 November 2011)

o 1,810 energy efficiencies measures were completed in East Herts to help reduce the risk of fuel poverty before the Herts Essex Energy Partnership Fuel Poverty and Carbon Reduction scheme finished on 31 March 2012.

o East Herts Council and Stevenage Borough Council have joined forces to provide housing benefit, council tax, business rates and benefit fraud investigations, providing savings for both councils.

o Performance in Revenues and Benefits has been maintained despite increase caseload and workload. For example Housing Benefit/Council Tax Benefit new claims and change events were processed within 10.3 days, against a target of 10 days in 2011/12.

Fit for purpose, services fit for you. Deliver customer focused services by maintaining and developing a well managed and publicly accountable organisation.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
End of Year Service Plan Report 2011-12Report 46 KB DownloadRead as text
PDF
End of Year Service Planning Report ERP B_v1Report 27 KB Download
PDF
End of Year Service planning report ERP AReport 21 KB Download

At this meeting

Whole meeting

On this subject at East Hertfordshire

Search all
  1. End of Year Service Plan Report 2011-12This decision
  2. 2014/15, 2013/14 and 2012/13 End of Year Service Plan Monitoring ReportDecided
  3. 2014/15, 2013/14 and 2011/12 Service Plans - End of Year Monitoring ReportsDecided
  4. 2013/14, 2012/13 and 2011/12 Service Plans - End of Year Monitoring ReportDecided
  5. Service Plans - End of Year Monitoring: 2011/12, 2012/13, 2013/14Decided
  6. 2012/13 Service Plan Monitoring - End of Year MonitoringDecided

More from East Hertfordshire Community Scrutiny Committee

All decisions
MeetingDecisionOutcome
28 Mar 2017 Markets - Options AppraisalRESOLVED – that (A) Town Councils be approached to negotiate a way forward to manage the markets in Bishop’s Stortfor... Decided Open
28 Mar 2017 Draft Physical Activity StrategyRESOLVED – that (A) Members’ comments now detailed on the draft Physical Activity Strategy within Essential Reference... Approved Open
28 Mar 2017 Community Scrutiny Work ProgrammeRESOLVED – that the work programme for Community Scrutiny Committee be included in the Scrutiny Committee Work Plans ... Decided Open
17 Nov 2015 2015/16 Service Plan and Key Projects Monitoring ReportRESOLVED – that performance for the period April 2015 to September 2015 be noted and supported. Noted Open
17 Nov 2015 Community Scrutiny Corporate Healthcheck Report - August to September 2015RESOLVED – that the reported performance for the period August to September 2015 be received. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies