1.1The Environmental Services department delivers a number of services through a range of contracts and using in-house staff. The primary objective of this report is to provide members with an annual update of the performance of the main term contracts.
1.2The new combined Refuse, Recycling and Street Cleansing contract was awarded to Veolia Environmental Services for a period of seven years, with a possible extension of up to seven years, in November 2010 and commenced on the 9th May 2011.
1.3At award the Council decided to increase the range of recyclable materials collected to include mixed plastics types 1-6 at an additional cost of £261,000 per annum. This was offset by the £1.5m saving per annum over the previous contracts.
1.4Following the award of the contract, officers entered into discussions with North Herts Council (which also contracts with Veolia) about the potential for shared services. The objective was to identify possible efficiency opportunities. It was agreed that resources for clinical waste collection and pavement washing would be shared between the two authorities, generating further financial savings for the same level of service.
1.5The Grounds Maintenance Contract was re-tendered in 2007 and awarded to John O Connor Ltd from April 2008 for six years and 9 months with a possible extension of up to seven years. The Contract includes additional elements to undertake most highways grounds maintenance (A roads are excluded) on behalf of Hertfordshire County Council and also the maintenance of grounds adjacent to ex-Council estates owned by Riversmead Housing Association. This contract is due to be reviewed in 2012/13 to consider whether it should be extended or a new contract let from January 2015.
2 Report
2.1This section of the report details contract and contractor performance over the last twelve months and compares this with the previous year. It also provides an update on some of the key initiatives undertaken by Environmental Services as a whole on associated environmental maintenance and enforcement activities. Refuse & Recycling (ARC) 2.2 The Alternate Refuse and Recycling collection service (ARC) was introduced in November 2009. In May 2011 in conjunction with the award of the new contract it was extended to include Plastics types 1-6 with popular response from our residents.
2.3In addition, communal properties have been able to take advantage of the extended service and plastics types 1-6 are now being collected from flats. This service was extended in May 2011 on a town by town basis and the service is now available throughout the District. 2.4 The contract required that new vehicles be provided for all services. Through the specification of vehicle type new, narrower vehicles for difficult access areas, the service has been able to include and provide organic collections and recycling collections to additional properties previously unsuitable for a collection service.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Contract Performance Environmental OperationsReport | 109 KB | DownloadRead as text |
Follow Environment Scrutiny Committee at East Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Feb 2016 | Environment Scrutiny Healthcheck October to December 2015RESOLVED – that the reported performance for the period October to December 2015 be approved. | Approved | Open |
| 23 Feb 2016 | Footway and Grassed Verge Parking Enforcement PolicyRESOLVED – that the Executive be advised that (A) a targeted local ban for the implementation of footway and grassed ... | Decided | Open |
| 23 Feb 2016 | Car Parking Fees and Charges 2016/17RESOLVED – that (A) that the outcome of the trial of new car park charges be noted; and (B) current trial charges be ... | Noted | Open |
| 23 Feb 2016 | Planning and Enforcement ReviewRESOLVED – that the Executive be advised that (A) the revised Planning Enforcement Policy be supported; (B) Officers’... | Decided | Open |
| 23 Feb 2016 | Waste and Street Cleansing Contract - Future Service ConsiderationsRESOLVED – that a Task and Finish Group comprising of 5 or 6 Members be set up to consider the future objectives and ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.