Resolved
AGREED – that the report be noted
Highways Joint Member Panel agreed this item on Monday 20 August 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
AGREED – that the report be noted
1.1To advise the panel of current developments and allow members to express their views.
2.1At the last meeting of the HJMP members received a progress report on the Lea Valley & East Herts Area Plans advising on the current schemes across the East Herts District area.
3.0Schemes
3.1BISHOP’S STORTFORD
3.1.1 Construction of the additional footway improvement works for the Sainsbury’s link from Villiers-Sur-Marne is due to commence shortly subject to finalisation of a legal agreement.
3.1.2. Bishop’s Stortford SCOOT works
Design work is underway to improve the operation of the traffic signals in Bishop’s Stortford town centre by linking them to maximise flows and minimise queuing. Six Variable message signs (VMS) will be installed on the outskirts of the town to improve driver information and enable remote management of traffic incidents. These signs together with the works necessary to link the town centre traffic signals will commence in the Autumn of 2012. 3.2 Bishop’s Stortford & Sawbridgeworth Urban Transport Plan (UTP)
Work has been paused on the UTP pending the outcome of a number of development issues in Bishop’s Stortford. It is anticipated that work will commence in the Autumn.
3.3Safer Routes to School Scheme – Northgate School, Bishop’s Stortford
Initial meetings have taken place to assess and understand the potential to increase sustainable journeys to Northgate School and to further support the successful walking bus. A feasibility study outlining the options available is nearing completion.
3.4HERTFORD & WARE
3.4.1 Ware Railway Station Enhancements
Design work is in the final stages for enhancement works outside Ware Railway Station using S106 funding. Stakeholders and local residents have been informed of the main details of the scheme. Implementation is dependant on legal negotiations which are in the final stages.
3.4.2 A414 “Foxholes” Crossing Hertford
Construction of the crossing was completed in July and work is virtually complete on the associated footway & bus stop improvements works in the vicinity of the crossing. 3.4.3 Bengeo
Following the interim report to the Highways Joint Member Panel in January 2012, in response to the petition presented by residents to the July 2011 panel requesting that an ANPR solution be delivered in 2011/12, a meeting was held with members, residents and officers to discuss options. As detailed in the January 2012 interim report it was confirmed that, for the present, an ANPR solution to the through traffic issues in Bengeo is not viable. This is due to changes in legislation regarding the use of ANPR for moving traffic offences, pressures on Police resources and the infrastructure that would be required to produce the level of evidence that would be required to deliver a successful prosecution.
Other minor measures that could be implemented to reinforce the prohibition of vehicles except for access and for waiting restrictions to reduce parking at junctions and improve pedestrian safety were discussed but it was agreed that it would make more sense to retain the Sainsbury’s S106 funding available for this issue until the new store had opened and the “before and after” counts had been assessed. This would mean that there would be no expenditure on further investigation into other possible solutions in 2012/13. The “after” counts will be taken in May 2013 and compared with the “before” counts taken in May 2011.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Lea Valley and Eastern Herts Area Plans, Hertford and Ware UTP, Bishop's Stortford and Sawbridgeworth UTPReport | 673 KB | DownloadRead as text |
Follow Highways Joint Member Panel at East Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Aug 2012 | Appointment of Chairman and Vice Chairman and Panel AdministrationRESOLVED – that (A) Councillor N Poulton be appointed Chairman for the meeting; and (B) Councillor P Ruffles be appoi... | Decided | Open |
| 20 Aug 2012 | Notes of the Panel MeetingAGREED – that the Notes of the meeting held on 19 March 2012 as amended, be approved as a correct record and signed b... | Agreed | Open |
| 20 Aug 2012 | Highways Joint Member Panel - Successor ArrangementsAGREED – that the report be noted. | Agreed | Open |
| 20 Aug 2012 | Highways Locality Budgets - Progress on works deliveryAGREED – that the report be noted. | Agreed | Open |
| 20 Aug 2012 | Section 106 ContributionsAGREED – that the Panel notes the actions and proposed use of Section106 funds and makes any comments it wishes to be... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.