Resolved
(A) the budgetary variances set out in paragraph 2.1 of the report be noted; (B) £20,000 of the IT Network, Servers and Storage capital budget is re-profiled from 2012/13 into 2013/14, as detailed at paragraph 2.34 of the report; (C) £30,000 of the Hardware Funding capital budget is re-profiled from 2012/13 into 2013/14 as detailed at paragraph 2.35 of the report; (D) £40,000 of The Bourne Ware play development area capital budget is re-profiled from 2012/13 into 2013/14 as detailed at paragraph 2.36 of the report; (E) £25,000 of the Hartham Common parks development plan project capital budget is re-profiled from 2012/13 into 2013/14 as detailed at paragraph 2.37 of the report; (F) the £10,000 capital budget for the Ventilation improvements to the Café kitchen at Hertford Theatre is vired to replacing the roof at the Castle Gardens bungalow as detailed at paragraph 2.38 of the report; (G) action taken to control strategic risks during the period July to September 2012, be noted; and (H) the list of 2011/12 Unit Cost performance indicators as detailed in paragraph 2.42 and Essential Reference Paper ‘G’ of the report submitted, be noted.