Resolved
RESOLVED – that (A) the report be received; (B) the amendments to the 2012/13 Audit Plan as at 28 December 2012 be approved; and (C) the removal of the implemented high priority recommendations be approved.
Audit Committee approved this item on Wednesday 23 January 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – that (A) the report be received; (B) the amendments to the 2012/13 Audit Plan as at 28 December 2012 be approved; and (C) the removal of the implemented high priority recommendations be approved.
Members are recommended to: • Note the Internal Audit Progress Report • Approve the amendments to the Audit Plan as at 28 December 2012; and • Agree removal of implemented high priority recommendations Contents
1 Introduction and Background 1.1 Purpose 1.2 Background
2 Audit Plan Update 2.1 Delivery of Audit Plan and Key Findings 2.3 High Priority Recommendations 2.5 Proposed Amendments to Audit Plan 2.6 Performance Management
A Progress against the 2012-13 Audit Plan
B Implementation Status of High Priority Recommendations
Page 1 1. Introduction and Background Purpose of Report
1.1This report details:
a) Progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s Annual Audit Plan for 2012-13 as at 28 December 2012. b) Proposed amendments to the approved 2012-13 Audit Plan. c) Implementation status of previously agreed high priority audit recommendations. d) An update on performance management information as at 28 December 2012.
1.2The 2012-13 Annual Audit Plan was approved by the Audit Committee on 14 March 2012.
1.3The Audit Committee receives periodic updates against the Annual Internal Audit Plan, the most recent of which was brought to this Committee on 19 September 2012.
1.4The work of Internal Audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit provision is fulfilling its statutory obligations. It is considered good practice that progress reports also include proposed amendments to the agreed annual audit plan.
2. Audit Plan Update Delivery of Audit Plan and Key Audit Findings
2.1As at 28 December 2012, 58% of the 2012-13 Audit Plan days had been delivered. Appendix A provides a status update on each individual project within the audit plan.
2.2The following 2012-13 reports have been finalised in the period since 25 August 2012: Audit Title Date of Assurance Number and Priority of Issue Level Recommendations Authorisations Sep ‘12 Substantial three merits attention and Delegations Project Oct ‘12 Full none Management
Page 2 Utilities Oct ‘12 Moderate four medium one merits attention Section 106 Oct ‘12 Moderate five high two medium two merits attention Commercial Nov ‘12 Full none Waste and Cleansing Leisure Nov ‘12 Substantial one merits attention Management Improvement Nov ‘12 Substantial two merits attention Grants Financial Dec ‘12 Not nine recommendations Regulations assessed on areas of best practice Benchmarking applicable to all five district / borough SIAS clients Homelessness Dec ‘12 Substantial two medium three merits attention
High Priority Recommendations
2.3Members will be aware that a Final Audit Report is issued when it has been agreed by management; this includes an agreement to implement the recommendations that have been made. It is SIAS’s responsibility to bring to Members’ attention the implementation status of high priority recommendations; it is the responsibility of Officers to implement the recommendations by the agreed date.
2.4For this committee, updates have been obtained for high priority audit recommendations, including IT-related recommendations dating back to 2009. The outcomes of our follow-up work are detailed in the standard template at Appendix B.
Proposed Audit Plan Amendments
2.5The following deletions from the 2012-13 Audit Plan have been agreed with the Officers of the Council and are detailed below for Audit Committee approval:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Shared Internal Audit Service: Progress ReportReport | 213 KB | DownloadRead as text |
Follow Audit Committee at East Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jan 2016 | Training item - Risk ManagementRESOLVED – that the presentation be received. | Decided | Open |
| 20 Jan 2016 | Minutes - 25 November 2015RESOLVED - that the Minutes of the meeting held on 25 November 2015 be confirmed as a correct record and signed by th... | Decided | Open |
| 20 Jan 2016 | External Audit - Grants Claim Certification Work 2014/15RESOLVED – that the report be received. | Decided | Open |
| 20 Jan 2016 | Treasury Management Strategy Statement 2016/17RESOLVED – that (A) the Treasury Management Strategy and Annual Investment Strategy detailed in paragraphs 2.1 – 2.2 ... | Decided | Open |
| 20 Jan 2016 | Shared Internal Audit Service - Audit Plan Update ReportRESOLVED – that (A) the Internal Audit Progress report be noted; (B) the amendments to the Audit Plan as at 1 January... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.