Resolved
RESOLVED – that (A) the report be received; (B) the amendments to the 2012/13 Audit Plan as at 13 February 2013 as submitted, be approved; and (C) the removal of the implemented high priority recommendations be approved.
Audit Committee approved this item on Wednesday 13 March 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – that (A) the report be received; (B) the amendments to the 2012/13 Audit Plan as at 13 February 2013 as submitted, be approved; and (C) the removal of the implemented high priority recommendations be approved.
Members are recommended to: • Note the Internal Audit Progress Report • Approve the amendments to the Audit Plan as at 22 February 2013; and • Agree removal of implemented high priority recommendations Contents
1 Introduction and Background 1.1 Purpose 1.2 Background
2 Audit Plan Update 2.1 Delivery of Audit Plan and Key Findings 2.3 High Priority Recommendations 2.5 Proposed Amendments to Audit Plan 2.6 Performance Management
A Progress against the 2012-13 Audit Plan
B Implementation Status of High Priority Recommendations
Page 1 1. Introduction and Background Purpose of Report
1.1This report details:
a) Progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s Annual Audit Plan for 2012-13 as at 22 February 2013. b) Proposed amendments to the approved 2012-13 Audit Plan. c) Implementation status of previously agreed high priority audit recommendations. d) An update on performance management information as at 22 February 2013.
1.2The 2012-13 Annual Audit Plan was approved by the Audit Committee on 14 March 2012.
1.3The Audit Committee receives periodic updates against the Annual Internal Audit Plan, the most recent of which was brought to this Committee on 23 January 2013.
1.4The work of Internal Audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit provision is fulfilling its statutory obligations. It is considered good practice that progress reports also include proposed amendments to the agreed annual audit plan.
2. Audit Plan Update Delivery of Audit Plan and Key Audit Findings
2.1As at 22 February 2013, 75% of the 2012-13 Audit Plan days had been delivered. Appendix A provides a status update on each individual project within the audit plan.
Page 2 2.2 The following 2012-13 reports have been finalised in the period since 28 December 2012 (cut-off date for the January 2013 Audit Committee):
Audit Title Date of Assurance Number and Issue Level Priority of Recommendations IT Risk Jan ‘13 Not assessed Three Diagnostics recommendations (benchmarking (no priority assigned) review) for management consideration Freedom of Feb ‘13 Substantial one medium Information two merits attention Car Parking Feb ‘13 Substantial three medium Contract one merits attention Payroll Feb ‘13 Substantial one medium
High Priority Recommendations
2.3Members will be aware that a Final Audit Report is issued when it has been agreed by management; this includes an agreement to implement the recommendations that have been made. It is SIAS’s responsibility to bring to Members’ attention the implementation status of high priority recommendations; it is the responsibility of Officers to implement the recommendations by the agreed date.
2.4Many of the IT audit recommendations dating back to 2009 relate to business continuity arrangements. The status of these, including whether they remain relevant in a changing IT environment will be considered during the IT Business Continuity audit currently in progress.
Proposed Audit Plan Amendments
2.5No deletions from the 2012-13 Annual Audit Plan are brought to this Committee for approval.
Since the last Committee, additional audits of Petty Cash and Expenses (10 days) and RIPA (10 days) have been agreed and added to the 2012-13 plan. Both are in progress.
Page 3 Performance Management
2.6Annual performance indicators and associated targets were approved by the SIAS Board in 2011.
2.7As at 22 February 2013 actual performance for East Herts against the targets that can be monitored in year was as shown in the table below.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Shared Internal Audit Service (SIAS): Progress ReportReport | 190 KB | DownloadRead as text |
Follow Audit Committee at East Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jan 2016 | Training item - Risk ManagementRESOLVED – that the presentation be received. | Decided | Open |
| 20 Jan 2016 | Minutes - 25 November 2015RESOLVED - that the Minutes of the meeting held on 25 November 2015 be confirmed as a correct record and signed by th... | Decided | Open |
| 20 Jan 2016 | External Audit - Grants Claim Certification Work 2014/15RESOLVED – that the report be received. | Decided | Open |
| 20 Jan 2016 | Treasury Management Strategy Statement 2016/17RESOLVED – that (A) the Treasury Management Strategy and Annual Investment Strategy detailed in paragraphs 2.1 – 2.2 ... | Decided | Open |
| 20 Jan 2016 | Shared Internal Audit Service - Audit Plan Update ReportRESOLVED – that (A) the Internal Audit Progress report be noted; (B) the amendments to the Audit Plan as at 1 January... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.