Resolved
RESOLVED - that (A) the Internal Audit Progress report be received; (B) the amendments to the Audit Plan as at 20 June 2014 be approved; and (C) high priority recommendations which had been implemented, be removed.
Audit Committee approved this item on Wednesday 16 July 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED - that (A) the Internal Audit Progress report be received; (B) the amendments to the Audit Plan as at 20 June 2014 be approved; and (C) high priority recommendations which had been implemented, be removed.
Members are recommended to: Note the Internal Audit Progress Report; Approve the amendments to the Audit Plan as at 20 June 2014; and Agree removal of implemented high priority recommendations. Contents
1 Introduction and Background 1.1 Purpose 1.2 Background
2 Audit Plan Update 2.1 Delivery of Audit Plan and Key Findings 2.3 High Priority Recommendations 2.4 Proposed Amendments to Audit Plan 2.5 Performance Management
A Progress against the 2014/15 Audit Plan
B Implementation Status of High Priority Recommendations
C Audit Plan Items (April 2014 to March 2015) – Start Dates Agreed with Management
Page 1 1. Introduction and Background Purpose of Report
1.1This report details:
a) Progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s Annual Audit Plan for 2014/15 as at 20 June 2014. b) Proposed amendments to the approved 2014/15 Audit Plan. c) Implementation status of previously agreed high priority audit recommendations. d) An update on performance management information as at 20 June 2014.
1.2The 2014/15 Audit Plan was approved by Audit Committee on 19 March 2014.
1.3The Audit Committee receives periodic updates against the Annual Internal Audit Plan, the most recent of which was brought to this Committee on 19 March 2014.
1.4The work of Internal Audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit provision is fulfilling its statutory obligations. It is considered good practice that progress reports also include proposed amendments to the agreed annual audit plan.
2. Audit Plan Update Delivery of Audit Plan and Key Audit Findings
2.1As at 20 June 2014, 11% of the 2014/15 Audit Plan days had been delivered. Appendix A provides a status update on each individual project within the audit plan.
Page 2 2.2 The following 2013/14 reports have been finalised since 28 February 2014 (cut-off date for 19 March 2014 Audit Committee) and represents closure of the 2013/14 Audit Plan:
Audit Title Date of Assurance Number and Issue Level Priority of Recommendations Land Charges Mar ‘14 Substantial One medium Main Accounting Mar ‘14 Substantial None Debtors Mar ‘14 Substantial None Creditors Mar ‘14 Full None Two medium Payroll Mar ‘14 Substantial Four merits attention Environmental Protection (Food Mar ‘14 Substantial None Hygiene) Facilities Three high Mar ‘14 Limited Management Three medium One medium Licensing Apr ‘14 Substantial Three merits attention Three medium Safe Staffing Apr ‘14 Moderate One merits attention Seven merits Social Media Apr ‘14 Substantial attention Payroll – post implementation Apr ‘14 Moderate Three medium review One high Pest Control Apr ‘14 Moderate Four medium Two merits attention IT Data May ‘14 Substantial One merits attention Management Treasury May ‘14 Full None Management Two medium Asset Management May ‘14 Substantial Four merits attention
Page 3 2.3 No 2014/15 reports have yet been finalised. Details of the status of audits in this year’s plan are shown in Appendix A and include a start month for each planned assignment which has been agreed with management. Appendix C details the agreed start month for each audit.
High Priority Recommendations
2.4Members will be aware that a Final Audit Report is issued when it has been agreed by management; this includes an agreement to implement the recommendations that have been made. It is SIAS’s responsibility to bring to Members’ attention the implementation status of high priority recommendations; it is the responsibility of Officers to implement the recommendations by the agreed date.
Proposed Audit Plan Amendments
2.5Consultation with management has resulted in the cancellation of the planned review of the IT Help Desk. The unused time has been returned to contingency.
Performance Management
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Shared Internal Audit Service: Audit Plan UpdateReport | 359 KB | DownloadRead as text |
Follow Audit Committee at East Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jan 2016 | Training item - Risk ManagementRESOLVED – that the presentation be received. | Decided | Open |
| 20 Jan 2016 | Minutes - 25 November 2015RESOLVED - that the Minutes of the meeting held on 25 November 2015 be confirmed as a correct record and signed by th... | Decided | Open |
| 20 Jan 2016 | External Audit - Grants Claim Certification Work 2014/15RESOLVED – that the report be received. | Decided | Open |
| 20 Jan 2016 | Treasury Management Strategy Statement 2016/17RESOLVED – that (A) the Treasury Management Strategy and Annual Investment Strategy detailed in paragraphs 2.1 – 2.2 ... | Decided | Open |
| 20 Jan 2016 | Shared Internal Audit Service - Audit Plan Update ReportRESOLVED – that (A) the Internal Audit Progress report be noted; (B) the amendments to the Audit Plan as at 1 January... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.