That (A) the development of an outline Business Case with North Herts District Council as detailed in paragraphs 2.10 - 2.11 of the report submitted, be approved; and (B) a report be brought back to the Executive in Spring 2015 to include an outline Business Case with the objective of obtaining approval of both Councils to proceed to the next stage of jointly procuring these services and specifically on how this joint project will be controlled and managed and the governance arrangements once the joint contract has been awarded.
Word for word from the decision East Hertfordshire published for this meeting.Source: democracy.eastherts.gov.uk
1.1The Hertfordshire Waste Partnership, comprising the ten district/borough councils and the County Council, work together to co-ordinate and deliver services for the residents of Hertfordshire. Under the Hertfordshire Waste Partnership Agreement, the authorities have agreed to work together where possible to improve service performance and identify efficiencies through joint working.
1.2In 2014 the Partnership commissioned a ‘Peer Review’, supported by the LGA, to consider whether the Partnership was meeting its objectives and how it could improve. One aspect of the review was to consider the extent of partners’ interest in forming a single joint waste authority for Hertfordshire. The conclusion was that while there was no appetite from all Hertfordshire authorities for such a solution, some District / Borough councils may wish to consider whether they wanted to work together in smaller groups to investigate the potential for shared waste services.
1.3Bringing services together across local authority boundaries presents many challenges due to contract lengths, vehicle life cycles, logistical challenges and preferences for how services are designed and delivered to meet local needs. However, there are now numerous examples of local authorities bringing their waste services together to improve efficiency and deliver financial savings. 1.4 North and East Herts Councils have contracted out services, similar geography and demography and closely aligned services. There is also a history of these authorities working together, through a common contractor, to share resources for clinical waste services and street washing/graffiti.
1.5If joint operations were to be considered, a key milestone for both authorities is the end date of current waste services contracts. East Herts’ contract ends in May 2018 while North Herts’ is the end of July 2017. Waste contracts require a two year procurement phase and this means a decision to proceed would be required in Spring 2015.
1.6The district boundaries are provided in the following table and diagram, which show population and size are similar.
District Councils North Herts East Herts Total Population 127,114 137,687 264,801 Area in sq miles 145 164 309 1.7 Along with all other Local Authorities across the country, North and East Herts Councils will continue to need to find ways to deliver services at less cost in order to balance budgets. The availability of funding from Central Government is expected to continue to reduce until at least 2020 and yet the upward pressure on expenditure budgets through inflation will continue. The Medium Term Financial Plan indicates that the funding gap will widen in 2017/18 and 2018/19.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Treasury Management 2025/26 OutturnRESOLVED – Executive recommended to Council that it approve the Treasury Management Annual Outturn 2025/26, including...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.