CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
East Hertfordshire District Council
Audit Committee, Wednesday 18 March 2015 at 7.00pm

Shared Internal Audit Service - Audit Plan Update report

Approved Finance 1 paper

Audit Committee approved this item on Wednesday 18 March 2015. Below is the council's own wording, with the papers it was decided on.

Item597

Resolved

RESOLVED – that (A) the report be received; and (B) the removal of the implemented high priority recommendations be approved.
Word for word from the decision East Hertfordshire published for this meeting. Source: democracy.eastherts.gov.uk

Follow this further

Built from East Hertfordshire's papers

What the report saysPro

Report to Audit Committee

Recommendation

Members are recommended to:  Note the Internal Audit Progress Report; and  Agree removal of implemented high priority recommendations. Contents

1 Introduction and Background 1.1 Purpose 1.2 Background

2 Audit Plan Update 2.1 Delivery of Audit Plan and Key Findings 2.3 High Priority Recommendations 2.4 Proposed Amendments to Audit Plan 2.5 Performance Management

Appendices

A Progress against the 2014/15 Audit Plan

B Implementation Status of High Priority Recommendations

C Audit Plan Items (April 2014 to March 2015) – Start Dates Agreed with Management 1. Introduction and Background Purpose of Report

1.1This report details:

a) Progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s Annual Audit Plan for 2014/15 as at 27 February 2015. b) Proposed amendments to the approved 2014/15 Audit Plan. c) Implementation status of previously agreed high priority audit recommendations. d) An update on performance management information as at 27 February 2015.

Background

1.2The 2014/15 Audit Plan was approved by Audit Committee on 19 March 2014.

1.3The Audit Committee receives periodic updates against the Annual Internal Audit Plan, the most recent of which was brought to this Committee on 21 January 2015.

1.4The work of Internal Audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit provision is fulfilling its statutory obligations. It is considered good practice that progress reports also include proposed amendments to the agreed annual audit plan.

2. Audit Plan Update Delivery of Audit Plan and Key Audit Findings

2.1As at 27 February 2015, 86% of the 2014/15 Audit Plan days had been delivered. Appendix A provides a status update on each individual project within the audit plan. 2.2 The following 2014/15 reports have been finalised since 5 January 2015 (cut-off date for January 2015 Audit Committee):

Audit Title Date of Assurance Number and Issue Level Priority of Recommendations AGS Benchmarking Jan ‘15 N/A N/A Creditors Jan ‘15 Full None (CRSA Year 2) None (comment in Executive Summary Benefits Jan ‘15 Substantial affects overall assurance opinion) Leisure Services – Ten medium Third Party Jan ‘15 Moderate Two merits attention Inspections Treasury Jan ‘15 Moderate Four medium Management Fees and Charges Feb ‘15 Full None IT Business One medium Feb ‘15 Substantial Continuity Planning One merits attention IT Change Control Feb ‘15 Substantial One high Main Accounting Feb ‘15 Full None System

High Priority Recommendations

2.3Members will be aware that a Final Audit Report is issued when it has been agreed by management; this includes an agreement to implement the recommendations that have been made. It is SIAS’s responsibility to bring to the attention of Members the implementation status of high priority recommendations; it is the responsibility of Officers to implement the recommendations by the agreed date.

Proposed Audit Plan Amendments

2.4There are no further changes to the 2014/15 Audit Plan for the Committee to consider. Performance Management

2.5Annual performance indicators and associated targets were approved by the SIAS Board in 2011.

2.6As at 27 February 2015 actual performance for East Herts against the targets that can be monitored in year was as shown in the table below.

Performance Annual Profiled Actual to Indicator Target Target to 27 27 February February 2015 2015 1. Planned Days – percentage of actual billable days against planned chargeable 95% 90% 86% days completed (excluding unused contingency)

2. Planned Projects – percentage of actual 76% 76% completed projects to (22 of 29 (22 of 29 draft report stage 95% projects to projects to against planned draft) draft) completed projects

3. Client Satisfaction – percentage of client satisfaction questionnaires 100% 100% 100% returned at ‘satisfactory’ level

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Shared Internal Audit Service: Audit Plan Update reportReport 319 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at East Hertfordshire

Search all
  1. Shared Internal Audit Service - Audit Plan Update reportThis decision
  2. Shared Internal Audit Service - Internal Audit Plan Report 2026/27Approved
  3. Shared Internal Audit Service - Progress ReportNoted
  4. Shared Internal Audit Service - Progress ReportNoted
  5. Shared Internal Audit Service - Progress ReportNoted
  6. Shared Internal Audit Service - Internal Audit Plan Progress ReportNoted

More from East Hertfordshire Audit Committee

All decisions
MeetingDecisionOutcome
20 Jan 2016 Training item - Risk ManagementRESOLVED – that the presentation be received. Decided Open
20 Jan 2016 Minutes - 25 November 2015RESOLVED - that the Minutes of the meeting held on 25 November 2015 be confirmed as a correct record and signed by th... Decided Open
20 Jan 2016 External Audit - Grants Claim Certification Work 2014/15RESOLVED – that the report be received. Decided Open
20 Jan 2016 Treasury Management Strategy Statement 2016/17RESOLVED – that (A) the Treasury Management Strategy and Annual Investment Strategy detailed in paragraphs 2.1 – 2.2 ... Decided Open
20 Jan 2016 Shared Internal Audit Service - Audit Plan Update ReportRESOLVED – that (A) the Internal Audit Progress report be noted; (B) the amendments to the Audit Plan as at 1 January... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies