RESOLVED – that (A) that the Performance Indicators EHPI 2.1d and 2.1e be noted; (B) the Committee recommends to the Executive t o consider the implications of reviewing the 15 day target in relation to 2.1d (Planning Enforcement Initial Site Inspections) and to report back to the joint meeting of Scrutiny Committees in February as part of the 2016/17 Future Targets report; and (C) the Executive be requested to delete the Performance Indicator 2.1e (Service of Planning Enforcement Notices) but that Development Management Committee be provided with an update on each occasion when authorisation has been given.
Word for word from the decision East Hertfordshire published for this meeting.Source: democracy.eastherts.gov.uk
1.1Consideration was given to the Council’s published performance indicators at the joint meeting of Scrutiny Committees of 10 February 2015 and at the Environment Scrutiny Committee of 17 February 2015. After considering the indicators that relate to planning enforcement activity, members of the committees resolved that these should be reviewed by this committee at its meeting of 9 June 2015.
1.2The relevant performance indicators are EHPI 2.1d – planning enforcement initial site inspections and EHPI 2.1e – service of planning enforcement notices. The first of these measures the length of time taken (in working days) between the raising of a potential planning enforcement matter with the Council and the first inspection of the site to which the matter relates by the Councils Enforcement Officers. The current target is that 75% of all sites are inspected within 15 working days.
1.3The second indicator, 2.1e, measures the time which elapses (again in working days), between the resolution of the Development Management committee that a planning enforcement notice should be served (ie formal action is commenced) and the actual serving of that notice. The current target is that 70% of notices authorised in this way are served within 30 working days.
1.4The Council reviewed and revised its Planning Enforcement Policy in 2010. This work was undertaken by a task and finish group set up by this committee. Consideration was given to timescales and performance during that work and the current performance indicators are largely based on the policy. A copy of the policy is attached as Essential Reference Paper B.
2.0Current Performance
2.1Performance for the 2014/15 year is set out in the table below:
Indicator 2.1d – site inspections 2.1e – service of notices Target 75% of sites inspected 70% of notices served in 15 working days within 30 working days of authorisation Month Outcome (%) Outcome (%) April 14 91 n/a May 14 78 100 June 14 81 n/a July 14 70 n/a August 14 88 100 September 14 61 100 October 14 74 100 November 14 78 100 December 14 85 100 January 15 77 n/a February 15 81 n/a March 15 83 n/a Note: n/a – not applicable – this applies when no enforcement notices were served in that month.
3.0Indicator 2.1d – Site Inspections
3.1The policy establishes a priority approach to enforcement cases when considering timescales. A range of cases are identified as urgent priority (see 3.16 of the policy) – including cases where listed buildings or protected trees may be impacted, where there may be severe and irreversible impact as a result of unauthorised actions, where there may be traveller activity or highway danger or where immunity from action may be achieved if it is not taken in the next six months.
3.2In these urgent priority cases, the policy sets out that, initial site inspections will be undertaken within 2 working days of the matter being raised with the Council and, if there is potential for the loss of assets, within half of a working day.
3.3All other cases are identified as normal priority – and are subject to the site inspection target of 15 working days.
3.4Only the overall (15 working days) performance is captured by our recording systems and reported to Members through the normal processes. Officers however are working to the much shorter policy targets if they are dealing with a case which is identified as urgent priority.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment Scrutiny Committee at East Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
Car Parking Fees and Charges 2016/17RESOLVED – that (A) that the outcome of the trial of new car park charges be noted; and (B) current trial charges be ...
Planning and Enforcement ReviewRESOLVED – that the Executive be advised that (A) the revised Planning Enforcement Policy be supported; (B) Officers’...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.