Resolved
RESOLVED – that the report be received.
Audit Committee decided this item on Wednesday 25 November 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – that the report be received.
DRAFT This version of the report is a draft. Its contents and subject matter remain under review and its contents
The Annual Audit Letter may change and be expanded as part of the finalisation of the report.
for East Hertfordshire District Council
Year ended 31 March 2015 October 2015
Paul Grady Director T 020 7728 2301 E [email removed]
Sarah Ironmonger Senior Manager T [phone removed] E [email removed]
Will King Executive T 020 7728 2819 E [email removed]
© 2015 Grant Thornton UK LLP | Annual Audit Letter 2014/15 DRAFT Contents Section Page
1. Key messages 3 Appendices A Key issues and recommendations B Summary of reports and audit fees
© 2015 Grant Thornton UK LLP | Annual Audit Letter 2014/15 2 DRAFT Key messages
Our Annual Audit Letter summarises the key findings arising from the work that we have carried out at East Hertfordshire District Council for the year ended 31 March 2015.
The Letter is intended to communicate key messages to you and external stakeholders, including members of the public. Our annual work programme, which includes nationally prescribed and locally determined work, has been undertaken in accordance with the Audit Plan that we presented to the Audit Committee on 15 July 2015 and was conducted in accordance with the Audit Commission's Code of Audit Practice, International Standards on Auditing (UK and Ireland) and other guidance issued by the Audit Commission and Public Sector Audit Appointments Limited.
Financial statements audit (including We reported our findings arising from the audit of the financial statements in our Audit Findings Report on 23 audit opinion) September 2015 to the Audit Committee. The key messages reported were: • we did not identify any adjustments affecting your reported financial position, and your recorded net expenditure remains unchanged at £18.9 million • we identified a number of adjustments to improve the presentation of the financial statements. • your information system capability caused difficulties during the audit, in particular: • providing a detailed listing of debtor and creditor amounts that remained outstanding at the balance sheet date was problematic; • producing support for your asset management figures was difficult • comparison of your carrying value to fair value for property assets identified a significant variance.
We issued an unqualified opinion on your 2014/15 financial statements on 30 September 2015, meeting the deadline set by the Department for Communities and Local Government. Our opinion confirms that the financial statements give a true and fair view of your financial position and of the income and expenditure recorded by you. Value for Money (VfM) conclusion We issued an unqualified VfM conclusion for 2014/15 on 30 September 2015.
On the basis of our work, and having regard to the guidance on the specified criteria published by the Audit Commission, we are satisfied that in all significant respects you put in place proper arrangements to secure economy, efficiency and effectiveness in your use of resources for the year ending 31 March 2015. © 2015 Grant Thornton UK LLP | Annual Audit Letter 2014/15 3 DRAFT Key messages continued
Certification of housing benefit grant claim Our work to certify your 2014/15 housing benefit grant claim is on-going.
Audit fee Our fee for 2014/15 was £69,775, excluding VAT which was in line with our planned fee for the year. Further detail is included within appendix B.
© 2015 Grant Thornton UK LLP | Annual Audit Letter 2014/15 4 DRAFT Appendix A: Key issues and recommendations This appendix summarised the significant recommendations identified during the 2014/15 audit.
No. Issue and recommendation Priority Management response/ responsible office/ due date
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
External Audit report: 2014/15 Annual Audit LetterReport | 133 KB | DownloadRead as text |
Follow Audit Committee at East Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jan 2016 | Training item - Risk ManagementRESOLVED – that the presentation be received. | Decided | Open |
| 20 Jan 2016 | Minutes - 25 November 2015RESOLVED - that the Minutes of the meeting held on 25 November 2015 be confirmed as a correct record and signed by th... | Decided | Open |
| 20 Jan 2016 | External Audit - Grants Claim Certification Work 2014/15RESOLVED – that the report be received. | Decided | Open |
| 20 Jan 2016 | Treasury Management Strategy Statement 2016/17RESOLVED – that (A) the Treasury Management Strategy and Annual Investment Strategy detailed in paragraphs 2.1 – 2.2 ... | Decided | Open |
| 20 Jan 2016 | Shared Internal Audit Service - Audit Plan Update ReportRESOLVED – that (A) the Internal Audit Progress report be noted; (B) the amendments to the Audit Plan as at 1 January... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.