CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
East Hertfordshire District Council
Executive, Tuesday 5 January 2016 at 7.00pm

Waytemore Castle Improvement Project HLF Bid

Approved Executive 4 papers

Executive approved this item on Tuesday 5 January 2016. Below is the council's own wording, with the papers it was decided on.

Item493

Resolved

That (A) the terms and conditions of the grant be accepted; and (B) the proposals to fund the project be approved and submitted for inclusion in the Council’s Capital Programme for 2017/18.
Word for word from the decision East Hertfordshire published for this meeting. Source: democracy.eastherts.gov.uk

Follow this further

Built from East Hertfordshire's papers

What the report saysPro

Report to Executive

EAST HERTS COUNCIL

EXECUTIVE – 5 JANUARY 2016

REPORT BY THE EXECUTIVE MEMBER FOR ENVIRONMENT AND PUBLIC SPACE

WAYTEMORE CASTLE IMPROVEMENT PROJECT – HLF BID

WARD(S) AFFECTED: Bishop‟s Stortford Meads

Purpose/Summary of Report

 To report progress of the first round of the Heritage Lottery Fund HLF) Parks for People bid for restoration and improvements to Waytemore Castle Gardens, Bishop‟s Stortford.

 To confirm the potential grant fund available.

 To explain the commitments necessary for the Council to accept the grant.

 To place the second phase of the project in the 2017/18 Capital Programme.

RECOMMENDATIONS FOR THE EXECUTIVE: That :

(A) the terms and conditions of the grant are accepted; and

(B) the proposals to fund the project be approved and submitted for inclusion in the Council’s Capital Programme for 2017/18.

1 Background 1.1 A Project Initiation Document was presented to CMT on 25 November 2014 to outline the project and funding requirements as part of the Capital Programme Bid Proposals for 2015/16. At that stage in advance of the application submission it was agreed that the project should be fully explored with a view to recommending it to Executive if an acceptable project could be developed.

1.2Officers submitted an Expression of Interest bid to Lottery for funding for a project from 2016 to 2020. This was successful and therefore a first round Stage 1 bid was prepared. 1.3 The HLF „Parks for People‟ Stage 1 bid was completed and submitted in September 2015. See Essential Reference Paper ‘B’ for a copy of the submitted bid. The application has been in partnership with Bishop‟s Stortford Town Council who own Sworders Field. Both Waytmore Castle and Sworders Field are included for improvement as part of a wider project area named for the purposes of this bid as Castle Park.

1.4The Stage 1 bid was decided by HLF on 15th December 2015 and notified by telephone on 16th December 2015. On this occasion the Council were unfortunately not successful. The Council does however have the right to re-apply under the next tranche of applications in 2016. HLF will be writing to provide some initial feedback and have offered the opportunity for a post rejection meeting. They have advised that this was a “near miss” and have indicated which specific areas of the bid require further clarity. They have encouraged the Council to re-apply. 1.5 If successful with the next application, the Council will be required to accept the terms and conditions of the grant within 28 days of receiving a Grant Notification Letter. This report asks the Executive to approve the terms to allow this potential future project to proceed. Formal approval at this stage is important in preparation for a successful second bid given the tight timescales involved. 1.6 The full value of the project has been estimated within the grant application and is split into two phases; the development phase and the delivery phase. The first round “Development” involves consultation and preparatory design and costing works. The second round “Delivery” involves the final design works and installation of improvements on the ground. 1.7 The Council is expected to contribute toward the cost of the project (match funding). The level of contributions has been proposed in the grant application: Full estimated Council Value of Grant costs Contribution

Development Stage 1 £238,618 £23,918 £214,700

Delivery Stage 2 £1,534,169 £168,758 £1,365,410

2 Report

2.1The purpose of the project is to conserve and enhance the heritage of the Waytemore Castle Gardens including Sworders Field and improve the park facilities to provide a wider range of activities, events and opportunities for community involvement.

2.2The submission was introduced as follows:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Waytemore Castle Improvement Project HLF BidReport 278 KB DownloadRead as text
PDF
Waytemore HLF bid: ERP A (implications)Report 120 KB Download
PDF
Waytemore HLF bid: ERP B (Final submission)Report 261 KB Download
PDF
Waytemore HLF bid: ERP C (terms of grant)Report 323 KB Download

At this meeting

Whole meeting

More from East Hertfordshire Executive

All decisions
MeetingDecisionOutcome
8 Sep 2026 Minutes – 14 July 2026RESOLVED – that the Minutes of the meeting held on 14 July 2026 be approved as a correct record and signed by the Lea... Approved Open
8 Sep 2026 Financial Management 2026/27 - Quarter 1 forecast to year enda) To note that the Revenue forecast position is a £440k overspend as of the end of June 2026; and b) Note the Capita... Noted Open
8 Sep 2026 Strategic Risk Register Q1 monitoring and Annual Review of Risk Management Strategya) The 2026/27 quarter one corporate risk register and actions being taken to control and mitigate risk be noted. b) ... Noted Open
8 Sep 2026 Treasury Management 2025/26 OutturnRESOLVED – Executive recommended to Council that it approve the Treasury Management Annual Outturn 2025/26, including... Approved Open
8 Sep 2026 Future of Water Lane Halla) That spend of up to £22,500 is approved for legal fees and costs to support Executive in considering a community a... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies