Budget 2022/23 and Medium Term Financial Plan 2022 – 2025 Preparation

Agreed Executive 3 papers

Executive agreed this item on Tuesday 28 September 2021. Below is the council's own wording, with the papers it was decided on.

Item180

Resolved

a) Agree, as guidance to officers, that the budget proposals should be based on a Council Tax increase of £5, contract inflation up to 4%, no inflation in other goods and services budgets and that the provision for the national pay award will be up to 3% (effectively 2.75% as 0.25% of the pay provision this year will be carried forward as a result of the 1.75% final pay offer from the employer’s side); b) Note the comprehensive spending review savings to be implemented in 2022/23 and 2023/24 as agreed by Council in March 2021 and acknowledge the requirement of Council that compensating savings, delivered to the same timescales, have to be put in place and reported to the next Council meeting should the Executive decide that any savings proposals should not proceed, or are reduced by 10% or more; c) Welcome the Collection Fund updated estimate that the Business Rates deficit being spread over 3 years will be met in full by changes to the appeals provision removing a £0.900 million pressure on the General Fund and the forecast increase in Local Council Tax Support cases has not materialised and the Council Tax Base is now forecast to increase in future years; d) Note the assumption that the Transforming East Herts Programme will not start to result in revenue savings until the latter half of 2022/23 and into 2023/24 e) Agree: the re-phasing of the capital programme and revenue impacts of capital financing; that existing minor projects should be subject to a full value for money test before proceeding; and that no new projects may come forward for the capital programme unless they are able to cover the capital financing costs in full or mitigate significant increases in revenue costs; f) Note the revised savings requirements of £0.967 million in 2022/23, £1.520 million in 2023/24 – 2025/26 rising to £1.901million in 2026/27; and g) Agree that all service areas should review fees and charges and ensure that, where the council has discretion to set the charge, that charges should be set so as to: recover full costs; concessions should be explicitly linked to an Equalities Impact Assessment; and that services which are not currently charged for the introduction of a charge should be considered unless the service is provided generally under a statutory provision.
Word for word from the decision East Hertfordshire published for this meeting. Source: democracy.eastherts.gov.uk

Follow this further

Built from East Hertfordshire's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Budget 2022/23 and Medium Term Financial Plan 2022: 2025 PreparationReport 271 KB Copy on its way
PDF
MTFP Initial Appendix AAppendix 54 KB Copy on its way
PDF
MTFP Initial Appendix BAppendix 252 KB Copy on its way

At this meeting

Whole meeting

On this subject at East Hertfordshire

Search all
  1. Budget 2022/23 and Medium Term Financial Plan 2022 – 2025 PreparationThis decision
  2. Draft Budget 2026/27 and Medium-Term Financial Plan 2026-2031Agreed
  3. Budget 2025-26 and Medium-Term Financial Plan (MTFP) 2025-2035 PreparationAgreed
  4. Budget 2024/25 and Medium Term Financial Plan 2024 - 2034Agreed
  5. Budget 2023/24 and Medium Term Financial Plan 2023/24 - 2027/28Approved
  6. Budget 2023/24 and Medium-Term Financial Plan 2023 – 2028 for scrutinyNoted

More from East Hertfordshire Executive

All decisions
MeetingDecisionOutcome
8 Sep 2026 Minutes – 14 July 2026RESOLVED – that the Minutes of the meeting held on 14 July 2026 be approved as a correct record and signed by the Lea... Approved Open
8 Sep 2026 Financial Management 2026/27 - Quarter 1 forecast to year enda) To note that the Revenue forecast position is a £440k overspend as of the end of June 2026; and b) Note the Capita... Noted Open
8 Sep 2026 Strategic Risk Register Q1 monitoring and Annual Review of Risk Management Strategya) The 2026/27 quarter one corporate risk register and actions being taken to control and mitigate risk be noted. b) ... Noted Open
8 Sep 2026 Treasury Management 2025/26 OutturnRESOLVED – Executive recommended to Council that it approve the Treasury Management Annual Outturn 2025/26, including... Approved Open
8 Sep 2026 Future of Water Lane Halla) That spend of up to £22,500 is approved for legal fees and costs to support Executive in considering a community a... Approved Open