3/25/1986/FUL - Erection of 4 x industrial units (use classes E[g], B2 and B8) with associated parking and external works at Buntingford Business Park, Baldock Road, Buntingford

Decided Committee 4 papers

AI summaryEast Hertfordshire development committee considers four industrial units at Buntingford Business Park, with officer recommendation to approve subject to conditions. Full committee resolution not recorded in supplied text.

AI summaryIn plain English

Written from the decision wording; the report is not read yetPDF Pro
OutcomeDecided
MoneyNot stated
What happens nextConditions to be set in permission
Who it affectsBuntingford Business Park and nearby roads

What was decided

The committee agreed, under paragraph 6.5.6 of the constitution, to allow Fergus Alexander to speak even though he registered after the 5 pm Monday 10 August 2026 deadline.

The Director for Place recommended that planning permission for application 3/25/1986/FUL be granted, subject to the conditions set out at the end of the report.

The Principal Planning Officer presented the site, planning history, design, sustainability and highways information to the committee.

Why

The business park is a designated employment site in the East Herts District Plan, and the principle of expanding employment on it is supported by the District Plan, the Buntingford Neighbourhood Plan and the Buntingford Employment Study.

The building has been designed with brickwork, metal cladding and a pitched roof to reflect existing buildings in the business park.

Sustainability measures include a fabric-first approach, air source heat pumps and roof-mounted solar panels, estimated to cut carbon emissions by 55.6% beyond Building Regulations.

What happens next

If granted, permission would be issued subject to the conditions listed in the report (not supplied).

Vehicle movements are estimated at between 71 and 275 per day, depending on the eventual occupiers; further highways detail in the report was not supplied.

Options considered

  • Recommended: Grant planning permission for four industrial units subject to conditions. Aligns with employment site designation and policy support for medium-sized employment premises.

Implications

  • Climate: Development designed to deliver a 55.6% reduction in carbon emissions beyond Building Regulations, using air source heat pumps and roof-mounted solar panels.
  • Staffing: Applicant estimates the development could support up to 112 jobs.
  • Other: Hertfordshire Highways concluded the proposal would not result in a severe impact (further detail in full report not supplied).
  • Legal: A late-registered speaker was permitted to address the committee under paragraph 6.5.6 of the constitution.

Who and where

  • Future occupiers of the four industrial units
  • Existing businesses and premises at Buntingford Business Park
  • Residents of nearby residential development in Buntingford
  • Users of the A507 and A10 road network

Timeline

  • 5 pm, Monday 10 August 2026: Speaker registration deadline for the meeting.
  • 12 August 2026: Development Management Committee considered application 3/25/1986/FUL.

Plain English for the jargon

  • Use Class E(g): Use class covering offices, research and development, and light industrial processes that can be carried out in a residential area.
  • Use Class B2: General industrial use.
  • Use Class B8: Storage or distribution use.
  • Sunnyside Nursery: Previous historical use of the site as a garden nursery, identified in the planning history.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

RESOLVED - in accordance with paragraph 6.5.6 of the constitution, Fergus Alexander be permitted to address the Committee in respect of application 3/25/1986/FUL, as he had registered to speak after the registration deadline of 5 pm on Monday 10 August 2026. The Director for Place recommended that in respect of application 3/25/1986/FUL, planning permission be granted subject to the conditions set out at the end of the report. The Principal Planning Officer presented a site location plan and an aerial image identifying the site. He said that the site was a parcel of undeveloped grassland and vegetation on the south-eastern side of Buntingford Business Park. The Buntingford Business Park was a designated employment site within the East Herts District Plan. Members were advised that the site was directly to the west of Buntingford and was outside of the settlement boundary of the town. The site was therefore within the rural area beyond the Green Belt. Members were shown location plans, aerial photographs and site photographs illustrating the site's relationship with the existing business park, nearby residential development and the surrounding highway network (A507 and the A10). The Principal Planning Officer advised that the land was historically used as a garden nursery known as Sunnyside Nursery. He summarised in detail the planning history of the site. The previous planning permissions had been identified as material planning considerations. Members were advised that the current proposal sought permission for a single employment building containing four industrial units providing approximately 1,908 square metres of floorspace. The units would be suitable for Use Class E(g), B2 or B8 purposes and were intended to address identified demand for medium-sized employment premises. The applicant estimated that the development could support up to 112 jobs. Members were advised that the principle of expanding employment provision within the designated employment area was supported by the East Herts District Plan, the Buntingford Neighbourhood Plan and the Buntingford Employment Study. The Principal Planning Officer set out details of the proposed design and said that the building would incorporate brickwork and metal cladding with a pitched roof and had been designed to reflect the appearance of existing buildings within the business park. Members were advised that the sustainability measures would include a fabric-first approach, air source heat pumps and roof-mounted solar photovoltaic panels, resulting in an estimated 55.6% reduction in carbon emissions beyond Building Regulation requirements. The Principal Planning Officer said that, in respect of highways matters, the development would generate between 71 and 275 vehicle movements per day, depending on the eventual occupiers. Hertfordshire Highways had concluded that the proposal would not result in a severe impact ... view the full minutes text for item 5.
Word for word from the decision East Hertfordshire published for this meeting. Source: democracy.eastherts.gov.uk

Follow this further

Built from East Hertfordshire's papers

What the report saysPro

Report to Development Management Committee
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
3.25.1986.FUL: Buntingford Business Park: Location Plan.pdfPlan 2 MB Copy on its way
PDF
3.25.1986.FUL: Buntingford Business Park: Location Plan.pdfPlan 2.2 MB Download
PDF
3/25/1986/FUL: Erection of 4 x industrial units (use classes E[g], B2 and B8) with associated parking and external works at Buntingford Business Park, Baldock Road, BuntingfordReport 1 MB Copy on its way
PDF
3/25/1986/FUL: Erection of 4 x industrial units (use classes E[g], B2 and B8) with associated parking and external works at Buntingford Business Park, Baldock Road, BuntingfordReport 1.2 MB Download

At this meeting

Whole meeting
4Minutes - 15 July 2026On the agenda
53/25/1986/FUL - Erection of 4 x industrial units (use classes E[g], B2 and B8) with associated parking and external works at Buntingford Business Park, Baldock Road, BuntingfordThis decision
6Items for Reporting and NotingNoted 8Exclusion of the Press and PublicOn the agenda

On this subject at East Hertfordshire

Search all
  1. 3/25/1986/FUL - Erection of 4 x industrial units (use classes E[g], B2 and B8) with associated parking and external works at Buntingford Business Park, Baldock Road, BuntingfordThis decision
  2. 3/23/1641/FUL - The demolition of existing buildings and erection of Barn 1: Office accommodation, and 6 units of overnight accommodation (with 14 beds in total) for staff, volunteers and students working on the farm site (class E(g);Decided
  3. 3/23/1642/FUL - Erection of 118 dwellings, including access roads, cycle and pedestrian routes, cycle and car parking, public open space, landscaping, tree protection measures, sustainable urban drainage system (SuDS) and associated ancillaAgreed
  4. 3/23/2108/FUL - Erection of 60 residential units (Use Class C3) with creation of access, car parking, landscaping, amenity and open space, substation, pedestrian/cycle paths and associated development.Agreed
  5. 3/23/0681/FUL- Change of use of land and the erection of 9 dwellings, with associated landscaping, vehicular access and parking at Land at Thorley House, Thorley Street, Thorley, Bishop's StortfordAgreed
  6. 3/15/1859/FUL – Demolition of building P5 and associated structures and erection of new manufacturing building and associated works at Glaxosmithkline Ltd, Priory Street, Ware, SG12 0DJDecided

More from East Hertfordshire Development Management Committee

All decisions
MeetingDecisionOutcome
12 Aug 2026 Items for Reporting and NotingRESOLVED – that the following reports be noted: (A) Appeals against refusal of planning permission / non-determinatio... Noted Open
15 Jul 2026 Appointment of Vice-Chair for the 2026/27 civic yearRESOLVED – that Councillor J Thomas be appointed Vice-Chair of the Development Management Committee for the 2026/27 c... Decided Open
15 Jul 2026 Minutes - 15 April 2026RESOLVED – that the Minutes of the meeting held on 15 April 2026, be confirmed as a correct record and signed by the ... Decided Open
15 Apr 2026 Minutes - 11 March 2026RESOLVED – that the Minutes of the meeting held on 11 March 2026, be confirmed as a correct record and signed by the ... Decided Open
15 Apr 2026 Items for Reporting and NotingRESOLVED – that the following reports be noted: (A) Appeals against refusal of planning permission / non-determinatio... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies