RESOLVED 1) That the findings and recommendations of the Scrutiny B Review be noted by the Overview Committee. 2) That a Sustainability Working Group be established to oversee the development of a Strategic Sustainability Policy and Action Plan. 3) That the Sustainability Working Group be responsible for reporting its progress to the Portfolio Holder for Culture, Leisure and the Environment and the Lead Officer responsible for co-ordinating the Environmental Sustainability Policy, following which regular updates would be provided to the Executive Board 4) That Councillor Mrs V.C. Ayling be appointed Chairman of the Sustainability Working Group. EUROPEAN FUNDING REVIEW Members received a report from the Chairman of the Scrutiny B Committee outlining the recommendations of the Scrutiny Review relating to European Funding. The report sought Members to endorse the recommendations detailed on page 5 of the report presented. The Scrutiny Officer referred Members to a background paper which had been tabled at the Meeting. The Vice-Chairman of the Scrutiny B Committee informed Members that Scrutiny B had undertaken a review of European Funding to establish the achievements in the Objective 2 EU programme 2000 – 2006; to look at the lessons learned from the last ... view the full minutes text for item 68.
Word for word from the decision East Lindsey published for this meeting.Source: democracy.e-lindsey.gov.uk
The Scrutiny B Committee has agreed the following recommendations for submission to the Overview Committee. The background to these recommendations is outlined in paragraph 2 below:
• A Corporate Regeneration Project Group be established to provide a co-ordinated approach to project development. • A strategy for intervention utilising ERDF be formulated. • A tool kit is devised for project selection in line with the Corporate Strategy aims, objectives and ambitions. • More publicity is given to what funding is available and what has been achieved.
1.0REPORT/INTRODUCTION
The Scrutiny B Committee is undertaking a review of EU funding. The key objectives for this review are to:
• Establish the achievements in the objective 2 EU programme 2000 – 2006. • Look to see if there are lessons to be learned from the last round. • Make recommendations where necessary to maximise the potential for the District in line with corporate aims and priorities.
2.0SUMMARY OF THE EU FUNDING REVIEW
The background research showed that ELDC as a prime bidder was not as proactive in the last round of (objective 2) 2000 – 2006 EU Regional Development Funds compared to the previous round. The research however did show that the County Council levered in substantial funds where East Lindsey as District gained significant benefits; the Broadband initiative was a good example. The Economic Development team were invited to the Committee to present a status report. This report outlined the achievements; lessons learned and put forward some recommendations for future bids. An invitation was also extended to Justin Brown from the County Council Economic Development team to provide a brief on the new round of EU funds
In the conclusions from the review it was accepted that ELDC did not directly sponsor as many project as in the previous rounds however there was a more restrictive project framework and staff resources were still deployed on delivering projects from the previous round thus restricting resource availability for new bid activity. It was noted that, overall, East Lindsey derived significant outcome benefits particularly in establishing the new business centres and the Horncastle industrial estate (as well as from the County wide projects of tourism and broadband).
One of the major lessons learned was the need to have a more streamlined coordinated approach to project development. There is a tendency for the Fund Administrators to issue calls for projects which can spend and deliver quickly particularly towards the end of programme financial years. It would therefore be advantageous if we had projects on the shelf ready to submit at short notice. More collaborative working can also be a benefit particularly where it can reduce the administrative burden on the Council.
Project selection was also an important factor. Any projects put forward would have to meet ERDF selection criteria as well as meeting the Corporate Strategy priorities.
It was also important to recognise that the Council should not chase funding for the sake of it as this can lead to damaging long - term commitments with no real benefits for the community. Against the three objectives of the review the Scrutiny B Committee has now established the outcomes. As a general point, Members considered that there was a lack of understanding of what EU funding has achieved in the District and what Funds are available for the period 2007- 2013.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.