Resolved
RESOLVED That the Audit Committee submits the final monitoring report of the progress of the implementation of the review of Conisholme Wind Farm to Council.
Audit and Governance Committee decided this item on Monday 16 June 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the Audit Committee submits the final monitoring report of the progress of the implementation of the review of Conisholme Wind Farm to Council.
Internal REVIEW OF CONISHOLME WIND FARM PLANNING APPLICATION PROCESS – Audit IMPROVEMENT PLAN Services Internal Audit Report - Appendix A
REPORT REFERENCE FINDING PROPOSED ACTION OFFICER BY 4.4.2 The Committee resolved 2.1 The way in which the reasons for 6.1… ELDC needs to have clear and to go against that refusal were changed was not correct robust practices for dealing with recommendation and to refuse situations such as the formulation of planning permission for the 4.4.5 (a) It should be clear as to why a reasons for refusal where reports are First Application. The local planning authority is refusing before the Committee recommending Committee was under a duty to planning permission at the time of approval for a planning application. give reasons for that refusal, refusal The way in which the full reasons for but these were not considered refusal of the First Application were in full by the Committee at that 4.4.5 (d) In any event, this would have finalised was unsatisfactory. We have meeting been good practice at the time the First set out two means by which full Application was determined and we reasons for refusal could be 4.4.3 On 3 December 2004 would have expected relevant officers formulated and placed before the Brownejacobson advised that to have given advice to members along Committee before the refusal notice is "the refusal of permission these lines issued would be difficult to defend". On 16 December 2004 they 6.3 The Members’ Planning Code of Peter 31 Dec recommended including an Good Practice should be amended to Hickson 2007 additional reason for refusal on include procedures to enable the need proper formulation of refusals contrary to officer recommendation.
6.4We would recommend appropriate Simon 31 Mar training for Members and officers in Machin 2008 particular covering the areas addressed in this report
4.6.4 We need to make the 2.2.1 The report on the Second 6.4 We would recommend appropriate Simon 31 Mar point that the report is not very Application should have been clearer in training for Members and officers in Machin 2008 clear in the way it distinguishes the way it described and applied particular covering the areas between adopted and emerging adopted and emerging planning policies addressed in this report Audit Ref: Auditor: Status of Report: Issue Date Main Report PH P Hickson Draft V1.1 8/11/2007 Page 1 of 10 Internal REVIEW OF CONISHOLME WIND FARM PLANNING APPLICATION PROCESS – Audit IMPROVEMENT PLAN Services Internal Audit Report - Appendix A
REPORT REFERENCE FINDING PROPOSED ACTION OFFICER BY policies. This is important in showing that the duty to 6.2 It appears that officers have not determine applications in been entirely clear about how they accordance with the should deal with previous decisions for development plan unless similar proposals on the same site, material considerations indicate consistency of approach in assessing otherwise has been discharged. landscape matters and how properly to The weight which the set out development plan policies and Committee is advised to give to assess their weight. Officers writing policies is important reports need to consider such matters carefully in future 4.7.1 it appears that John 2.2.2 The Second Application should NB Jeremy Webb identifies a Campion’s study was have been assessed by an independent protocol for dealing with ‘large abandoned. No new study by landscape consultant. planning applications’. This would other landscape consultants (if take account of such issues (email the reasons for abandonment 4.7.2 We consider that because: - 30 October 2007 see pages 8 -10) made it no longer possible to engage JC) has been carried (a) the First Application was vetted by Formal protocol to be drafted Paul 31 Dec out. an external landscape consultant; Robinson 2007 & Simon (b) landscape and visual issues formed Machin the reason for refusal of the First Application;
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Conisholme Wind Farm Improvement Plan: AppAReport | 10 pages | DownloadRead as text |
PDF |
Progress in Implementation of the review of Conisholme Wind Farm application process: Improvement Plan:Report | 4 pages | Download |
Follow Audit and Governance Committee at East Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | 2026/27 Q1 Treasury UpdateThat the report be noted. | Noted | Open |
| 9 Sep 2026 | Q1 Risk report 2026/27That the Q1 Risk Report - 2026/27 Report be noted. | Noted | Open |
| 9 Sep 2026 | Local Code of Corporate GovernanceThat the updated Local Code of Corporate Governance be approved. | Approved | Open |
| 9 Sep 2026 | Audit & Governance Committee Annual Report 2025/26That the Audit and Governance Committee's Annual Report 2025/26 be approved and presented to Full Council in October ... | Approved | Open |
| 9 Sep 2026 | Annual Governance Statement 2025/26That the draft Annual Governance Statement 2025/26 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.