Resolved
RESOLVED That the report be noted by the Lincs Building Consultancy Executive Board.
Lincs Building Consultancy Executive Board noted this item on Monday 30 June 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the report be noted by the Lincs Building Consultancy Executive Board.
The Board is recommended to:
• Note the report results of the Customer Consultation Report • Note the report from the Charter Mark inspection • Note the report from the ISO Inspection
To acknowledge the performance of the service
OTHER CHOICES FOR CONSIDERATION
None
FINANCIAL IMPLIATIONS
None.
IMPLICATIONS HIGH MEDIUM LOW NONE FINANCIAL x ENVIRONMENTAL x PERSONNEL x CRIME & DISORDER x HUMAN RIGHTS x DATA PROTECTION x RISK x 1.0. RISK
1.1Failure to note and report on the performance would adversely affect the Charter Mark and ISO accreditation of the service.
2.0REPORT/INTRODUCTION
2.1The Consultation Report for 2007/08 demonstrated the continued commitment of the service to maintain the high level of customer care and satisfaction required to maintain our business.
2.2The report clearly demonstrates the staff have delivered a quality service, which our customers demand. The conclusion in the report states:-
“The feedback received from this exercise once again highlights that the Building Control Service continues to be provided to a high standard and is well regarded by stakeholders, both long established and new customers alike”.
2.3On the 25th April 2008, EMCQ carried out a full days inspection in respect of our Charter Mark accreditation. Inspections were carried out at two of our offices, Manby and Skegness.
2.4The assessor’s findings are as follows:
“Both verbal and written evidence confirm that the front line service delivery continues to meet user satisfaction. All staff are committed to a user-focused culture and make themselves available to help all agents, partners, Contractors and members of the public when they apply for approvals under the Building Regulations. Agents, Partners and Contractors spoken to during the visit confirmed that the staff make every effort to ensure that their needs are met.”
2.5On the 63 criteria we were evaluated on we achieved full compliance. This award will take us through until 2011 when we will need to obtain the new Charter Mark, which is currently being introduced. We will commence our preparation for this in the next year. The Director would like to express his thanks to all of the staff for their efforts in achieving this award, in particular Melanie Robinson who is the Charter Mark Manager. This is the highest achievement possible in the public sector in relation to customer service.
2.6On the 25th April 2008 the ISO inspector made the following observation :-
Management Summary • The areas assessed during the course of the visit were generally found to be effective. • There were no outstanding non-conformities to review from previous assessments. • No new non-conformities were identified during the assessment.
2.7It can be seen that this level of high performance and customer satisfaction could not be obtained without a highly motivated and professional staff who are suitably rewarded for all of their work and efforts to promote the service.
Background Documents None
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Consultation, Charter Mark & ISO Report:Report | 3 pages | DownloadRead as text |
Follow Lincs Building Consultancy Executive Board at East Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jun 2011 | Election of ChairmanRESOLVED That Councillor A. Wallace be elected Chairman of the Lincs Building Consultancy for the 2011/12 Council year. | Decided | Open |
| 27 Jun 2011 | Election of Vice-ChairmanRESOLVED That Councillor N.D. Cooper be elected as Vice-Chairman of the Lincs Building Consultancy for this Meeting o... | Decided | Open |
| 27 Jun 2011 | Director's End of Year Report 2010-11RESOLVED That the draft 2010/11 end of year financial report be approved and the annual return signed off by the Chai... | Approved | Open |
| 27 Jun 2011 | Financial Performance Monitoring ReportRESOLVED That the progress on the partnership be noted. | Noted | Open |
| 27 Jun 2011 | To consider proposed meeting dates for 2011/12It was agreed to circulate proposed Meeting dates for the 2011/12 Council year, following the Meeting. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.