Lincs Building Consultancy Executive Board agreed this item on Monday 9 February 2009. Below is the council's own wording, with the papers it was decided on.
It was agreed that Client Officers from both North East Lincs Council and East Lindsey District Council should attend a Meeting to review the LBC function and report its findings/recommendations to the LBC Meeting scheduled to take place on 16 March 2009. Members agreed recommendations from the review should be in place for the next financial year. RESOLVED That a fundamental review of the LBC function be undertaken by Client Officers from both North East Lincs Council and East Lindsey District Council. That a report detailing recommendations from the Meeting between North East Lincs Council and East Lindsey District Council be considered by the LBC Executive Board at their Meeting to be held on 16 March 2009.
Word for word from the decision East Lindsey published for this meeting.Source: democracy.e-lindsey.gov.uk
Report to Lincs Building Consultancy Executive Board, 10 pages
Recommendation
The Board is recommended to:-
i) report their concerns regarding the resourcing problems within the Building Control Partnership to both Councils;
ii) and to arrange a meeting involving both Councils to seek a resolution to these funding difficulties.
OTHER OPTIONS FOR CONSIDERATION 1. Make no changes 2. Consider other options for providing the service 3. Terminate the partnership
Financial implications
It can be seen from the last two monitoring reports that the Partnership income has reduced considerably in the current year due to the adverse economic climate. Decisions need to be taken as to how all the work of the Partnership can be resourced in the current climate.
IMPLICATIONS HIGH MEDIUM LOW NONE FINANCIAL x ENVIRONMENTAL x PERSONNEL x CRIME & DISORDER x HUMAN RIGHTS x DATA PROTECTION x RISK x 1.0. RISK
1.1That by not adequately funding the non-fee earning work the Partnership undertakes for both Councils it will seriously jeopardise the current arrangements. There is a growing amount of non-fee earning work and a reduction in fee earning income. With reducing staff in order to operate within budgets this has meant a reduced service to the fee-earning paying customers. This could lead to complaints about the level of service and possibly the failure of a structure and insurance claims against the authorities. In a worst case scenario, means of escape could be inadequate in a building which may lead to fatalities.
2.0BACKGROUND AND ISSUES
2.1We are now into the 3rd year of the joint arrangement and it seems to be an opportune time to undertake a formal review of the same. The partnership was formed to develop cross boundary working which was intended to improve customer services, recruit and retain staff as well as develop a more cost effective service.
2.2In order to review the partnership it has been necessary to evaluate all aspects of the partnership. One aspect that has caused concern is the way the non-fee earning work has been funded and particular attention is needed to ensure this work is undertaken in the most cost effective way for both Councils and the partnership.
3.0SUCCESSES AND LESSONS LEARNED
3.1.The partnership has developed a strong customer driven service which has been underlined by the partnerships achievement in obtaining ISO 9001:2000 the internationally recognised quality management standard. This has allowed the partnership to secure projects which would not have been available to us had we not achieve the standard.LBC has also been accredited under the Governments Charter Mark scheme which is the highest award possible for any public body, it should be recognised that this was achieved in 2008 with full compliance of the standard.
3.2Lincs Building Consultancy (LBC) has achieved 4 awards in 2008. These were the Local Authority Building Control Regional (East Midlands) Built in Quality awards for Best Individual House; Best Community Project; Best Partnership and Sustainable Building. The Best Partnership was also short listed for the National Awards.
3.3When LBC was created ELDC Building Control had no partners and NELC Building Control only had a handful. LBC now has 47 partners and we are expanding all of the time. We have checked plans for developments in many locations in England and secured many large prestigious projects. This has contributed significantly to our income and success. Some
2 examples are:- Havercroft, Oglesby & Limb, & Northern Lincolnshire & Goole NHS Trust to name but a few.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Lincs Building Consultancy Executive Board at East Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
Director's End of Year Report 2010-11RESOLVED That the draft 2010/11 end of year financial report be approved and the annual return signed off by the Chai...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.