Lincs Building Consultancy Executive Board agreed this item on Monday 16 March 2009. Below is the council's own wording, with the papers it was decided on.
It was agreed the necessary financial information for each of the long listed options would be presented at a Special Meeting of the Lincs Building Consultancy Executive Board to be held on 11 May 2009. Members noted some of the financial information may not be available for the said Meeting; however, Client Officers would work together to ensure as much information was available as possible in order to make an informed decision. RESOLVED That the options in the report be further developed with the necessary financial information in order that the Board could make a decision on the most appropriate course of action to take regarding the financial position of the LBC. That the following be included in the long list of options for the service: · ‘To dissolve the Partnership and take the work back in house to each Council’ That a Special Meeting of the Lincs Building Consultancy Executive Board be held on 11 May 2009 at the Knoll, Cleethorpes.
Word for word from the decision East Lindsey published for this meeting.Source: democracy.e-lindsey.gov.uk
Report to Lincs Building Consultancy Executive Board, 6 pages
Recommendation
That the options in this report be further developed with the necessary financial information in order that the Board may make a decision on the most appropriate course of action to take regarding the financial position of the LBC at its next meeting.
OTHER OPTIONS FOR CONSIDERATION
All the options are outlined for consideration in principle in this report.
Financial implications
The financial implications of the options in this report which are approved for further consideration will be considered in the follow up report to the next meeting of LBC’s Board.
IMPLICATIONS HIGH MEDIUM LOW NONE FINANCIAL X ENVIRONMENTAL X PERSONNEL X CRIME & DISORDER X HUMAN RIGHTS X DATA PROTECTION X RISK X FREEDOM OF INFO X
1. RISK
1.1By not adequately addressing the balance between the costs and funding of non-fee earning work the Partnership carries out for the constituent Councils, the financial position is likely to deteriorate into a downward spiral of staff reductions, service deterioration and the potential loss of fee paying work. 1.2 If a means of balancing the costs and the long term funding of non-fee earning work, acceptable to both authorities, cannot be found the future of the Partnership would be bought into doubt.
2. THE CURRENT POSITION
2.1When the Partnership was established on 1st April, 2006 non-fee earning work was funded through a mixture of Service Level Agreements and a budgetary allocation from each authority with any shortfall being covered by the surplus from fee-earning work.
2.2Over the three years of its existence the Partnership has had to absorb pay increases and cuts in the budget allocations. More recently as income for fee- earning work has declined with changing market conditions the cross-subsidy has become uncertain and may become untenable. Although a balanced budget has now been presented and fee-earning work is still in surplus the amount may no longer be sufficient to cover the non-fee earning element, despite reductions in staffing levels, if the current economic climate and lack of development interest prevails. It is therefore appropriate to put measures in place now so that the Partnership can to respond to any shortfall in predicted income in the forthcoming financial year.
3. POTENTIAL COURSES OF ACTION
3.1The options available to resolve this issue are as follows:-
• Cease to require some or all of the non-fee earning work to be undertaken. • Continue that work but have it undertaken elsewhere in the two authorities, rather than LBC. • Seek to have the work undertaken by the private sector. • Explore expansion of the partnership beyond North East Lincolnshire and East Lindsey District Councils. • Keep the work in LBC but allow it to operate in the open market by making it an arms length company. • Keep the work in LBC but bring it within the scope of the out-sourcing option being considered by NELC for its Regeneration, Planning and Transport Services. • Keep the work in LBC but bring it within the scope of the shared services option currently being considered by ELDC, Boston Borough Council and South Holland District Council. • Retain the work within LBC but with a new funding structure which does not cross subsidise the non-fee earning work from fee income. • Dissolve the Partnership and take the work back in-house to each Council.
The pros and cons of each are considered below, but it should be noted that they are not mutually exclusive. For each option the financial case will need to be made to ensure it is cost effective in terms of service to the customer and Value for Money. 4. EVALUATION OF OPTIONS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Lincs Building Consultancy Executive Board at East Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
Director's End of Year Report 2010-11RESOLVED That the draft 2010/11 end of year financial report be approved and the annual return signed off by the Chai...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.