Resolved
RESOLVED That the report be noted and the implementation of recommendations by Management be reviewed.
Audit and Governance Committee noted this item on Wednesday 18 March 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the report be noted and the implementation of recommendations by Management be reviewed.
INTERNAL AUDIT REPORT SUMMARY SHEET APPENDIX A
Leased Out Sites and Rights
Date Work Commenced: 5 January 2009 Date of Final Report: 2 March 2009
Main Objectives and Scope:
To ensure that adequate controls exist in respect of the Leased Out Sites and Rights.
Main Contact during review: Principal Valuer
Main Findings and conclusions:
An audit of leased out sites and rights provided Substantial Assurance i.e. overall the system of internal control meets acceptable standards and provides reasonable, but not absolute, assurance that the process covered is reliable and material losses will be detected in the normal course of business.
Main Recommendations Priority Responsibility Timescale
The 3 recommendations made were low risk and as such are not detailed in this summary.
1 INTERNAL AUDIT REPORT SUMMARY SHEET APPENDIX A
Caravan Park
Date Work Commenced: 28 January 2009 Date of Final Report: 4 March 2009
Main Objectives and Scope:
To ensure that adequate controls exist in respect of the Caravan Park management.
Main Contact during review: Caravan Park Manager
Main Findings and conclusions:
An audit of caravan parks and rights provided Substantial Assurance i.e. overall the system of internal control meets acceptable standards and provides reasonable, but not absolute, assurance that the process covered is reliable and material losses will be detected in the normal course of business.
Main Recommendations Priority Responsibility Timescale
The 3 recommendations made were low risk and as such are not detailed in this summary.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Report Summaries & Recommendation Tracker: AppAReport | 2 pages | DownloadRead as text |
PDF |
Report Summaries & Recommendation Tracker: AppBReport | 4 pages | Download |
PDF |
Report Summaries and Recommendation Tracker:Report | 5 pages | Download |
Follow Audit and Governance Committee at East Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | 2026/27 Q1 Treasury UpdateThat the report be noted. | Noted | Open |
| 9 Sep 2026 | Q1 Risk report 2026/27That the Q1 Risk Report - 2026/27 Report be noted. | Noted | Open |
| 9 Sep 2026 | Local Code of Corporate GovernanceThat the updated Local Code of Corporate Governance be approved. | Approved | Open |
| 9 Sep 2026 | Audit & Governance Committee Annual Report 2025/26That the Audit and Governance Committee's Annual Report 2025/26 be approved and presented to Full Council in October ... | Approved | Open |
| 9 Sep 2026 | Annual Governance Statement 2025/26That the draft Annual Governance Statement 2025/26 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.