CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
East Lindsey District Council
Overview Committee, Wednesday 22 April 2009 at 9.30am

Performance Management Framework

Decided Scrutiny 6 papers

Overview Committee decided this item on Wednesday 22 April 2009. Below is the council's own wording, with the papers it was decided on.

Item76

Resolved

RESOLVED 1) That the Business Manager, Workforce and Organisational Development be requested to present a report relating to PSP1 – Staff Turnover to the next Meeting. 2) That an invitation be extended to the Leader of the Council to attend the next Overview Meeting.
Word for word from the decision East Lindsey published for this meeting. Source: democracy.e-lindsey.gov.uk

Follow this further

Built from East Lindsey's papers

What the report saysPro

Report to Overview Committee, 39 pages

Appendix ‘A’

Performance Management Framework and Corporate Improvement Programme Report

1st April 2008 to 31st March 2009

Note 1: Performance for 2008/9 is provisional and subject to internal and external audit prior to publication

Note 2: Targets for 2009/10 are provisional and part of an on- going ‘challenge’ process prior to publication Report By: Performance and Consultation Team Appendix ‘A’ CORPORATE SCORECARD Summary description To Summary description To date date Our Customers Our Operations Complaints resulting in a change in policy or practice Residual Household waste per household ☺ ☺ Complaints responded to within timescale Municipal waste re-used, recycled or composted L ☺ Feedback from consultation provided to respondents Municipal waste land-filled within three months of the issue of the report ☺ ☺ Percentage of planning applications determined: Telephone call resolution rate at first point of contact L Major applications in 13 weeks L The proportion of customer contact that is avoidable Minor applications in 8 weeks ☺ Number of missed bins per 100,000 collections Other applications in 8 weeks L ☺ Average time processing Housing/Council Tax benefit Completion of Disabled Facilities Grants new claims and change events (days) ☺ L Public land assessed as having significant or heavy levels of: Benefit claims correctly calculated L Litter Detritus Our Staff and Members Graffiti Average number of working days / shifts lost per Fly-posting employee due to sickness absence L Enforcement action re ‘fly-tipping’ ☺ Percentage of performance appraisals completed in Percentage of Council Tax collected year L Staff Turnover Percentage of Non-Domestic Rates collected L L Our Resources Percentage of annual Revenue Expenditure budget over/(under) spent: Capital Expenditure Website availability ☺ Key: Cumulative Performance: ☺ = Annual target met or exceeded

L = Annual target not met CORPORATE IMPROVEMENT PROGRAMME OVERVIEW REPORT

Milestones Re-Planned (see Change Control Forms at Appendix ‘D’) Project Milestone To From Louth Cattle Market Prepare printed version of development brief

Draw up mailshot list of developers

Send out mailshot/Estates Gazette Advert.

Respond to advertisement and other enquiries

Meet interested parties if necessary

Registration of interest deadline

Analyse & prepare shortlist of developers To be Mar 2009 Meet with Chase and Partners and finalise shortlist of developers advised

Detailed analysis (including answers to queries) of bids submitted

Submit report with recommendations and meet ELDC on bids submitted

Run interviews/presentations

Undertake public and stakeholder consultation

Meet Chase and Partners & finalise choice of preferred developer

Obtain Executive Board approval Regeneration Develop outcome-based indicators for regeneration in partnership with Lincolnshire To be Enterprise and Lincolnshire County Council Mar 2009 advised Project Closure Reports Project Status

None

Status Red Risk Appendix ‘B’ CORPORATE SCORECARD

Performance Top Quartile

Provisional (2007/8) Indicator

Actual to February

2009/10 2007/8

2008/9

2008/9

2008/9 Target

Target

Target Actual

Actual 2009 Code

Summary Description

Our Customers Complaints resulting in a change of policy or practice OC1 40% 40% 49% 40% 43% ☺ 40% Complaints responded to within the designated KPI20 timescale 92.3% 95% 89% 95% 90% L 95% Feedback from consultation provided to respondents KPI23 within three months of the issue of the report 94% 95% 100% 95% 100% ☺ 95%

OC2 Telephone call first contact resolution rate 60.6% 70% 66.4% 70% 66.5% L 72%

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PMF: AppA-CReport 39 pages DownloadRead as text
PDF
PMF: AppD1aReport 2 pages Download
PDF
PMF: AppD1bReport 14 pages Download
PDF
PMF: AppD2aReport 2 pages Download
PDF
PMF: AppD2bReport 10 pages Download
PDF
Performance Management Framework:Report 4 pages Download

At this meeting

Whole meeting

On this subject at East Lindsey

Search all
  1. Performance Management FrameworkThis decision
  2. Performance Management Framework and Corporate Improvement ProgrammeNoted
  3. Performance Management Framework and Corporate Improvement ProgrammeNoted
  4. Performance Management FrameworkNoted
  5. Performance Management FrameworkNoted
  6. Performance Management Framework - April to November 2010Noted

More from East Lindsey Overview Committee

All decisions
MeetingDecisionOutcome
23 Jun 2026 Promoting solar and sustainable design across the districtIt was agreed that the work would commence in September as a task and finish exercise and Councillor Hesketh expresse... Agreed Open
23 Jun 2026 Overview Committee Work ProgrammeRESOLVED That the Committee Work Programme 2026/27 be noted. Noted Open
20 May 2026 Election of ChairmanThat Councillor Fiona Martin be elected Chairman of the Overview Committee for the Council year 2026/27. Decided Open
20 May 2026 Election of Vice ChairmanThat Councillor Ru Yarsley be elected Vice Chairman of the Overview Committee for the Council year 2026/27. Decided Open
12 May 2026 Update on the transition arrangements for Magna Vitae to Parkwood LeisureIt was agreed to provide the contract cost information outside the meeting and it was noted that the new arrangements... Agreed Open