Resolved
RESOLVED That the revised terms of reference be noted. That the work programme for 2010/11 be approved.
Audit and Governance Committee noted this item on Thursday 22 April 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the revised terms of reference be noted. That the work programme for 2010/11 be approved.
AUDIT COMMITTEE - TERMS OF REFERENCE V 4.0 March 2010
Procedures
Audit Committee reports direct to Council. There are nine seats and the quorum is four Members.
Council has nominated Audit Committee to be responsible for ensuring effective scrutiny of its treasury management strategy and policies
Meeting Cycle
Under normal circumstances seven meetings will be held per annum. The approximate frequency of meetings and the anticipated agenda items will be: -
• March/April - Draft Annual Audit Plan and Risk Assessment; Progress Report & Tracker; Corporate Fraud Awareness and Risk Register; Audit Committee Work Programme; Annual Governance Statement Summary of Activity
• June – Draft Revenue & Capital Outturn and Statement of Accounts; Internal Audit Annual Report; Annual Governance Statement; Key Lines of Enquiry Use of Resources Action Plan; Risk Position Statement – Quarter 1; Annual Treasury Management Report; Progress Report & Tracker
• July –Review of Contracts and Financial Procedure Rules of the Constitution; Investments Performance Update – Quarter 1; Progress Report & Tracker; Management of Council Tax, NNDR and Sundry Debt; Revenue & Capital Budget Monitoring – Quarter 1
• September - Annual Governance Report; Post-Audit Revenue and Capital Outturn and Statement of Accounts; Audit Benchmarking Results; Progress Report & Tracker; Fraud & Corruption Update; Annual Governance Statement Summary of Activity
• October/November – Review of Contracts and Financial Procedure Rules of the Constitution; Risk Position Statement – Quarter 2; Code of Corporate Governance; Investments Performance Update – Quarter 2; Progress Report & Tracker; Revenue & Capital Budget Monitoring – Quarter 2
• December – Treasury Management Strategy and Policy Statements; and Draft Service Plan; Audit Strategy; Progress Report & Tracker; Key Lines of Enquiry Use of Resources Action Plan Update; Annual Audit Letter
V 4.0 080310 1 • January/February – Risk Position Statement – Quarter 3; Progress Report & Tracker; Management of Council Tax, NNDR and Sundry Debt; Investments Performance Update – Quarter 3;Annual Claims & returns Audit; Revenue & Capital Budget Monitoring – Quarter 3; Key Lines of Enquiry Use of Resources Action Plan Inspection Results & Auditor Feedback
NB The above schedule gives an estimation of when certain regular reports can be expected but is not intended to represent an exact picture.
With very few exceptions the reports listed above represent important supporting evidence for the Annual Governance Statement and are marked as follows in the opening report summary: -
“This Report refers to a key element of the Council’s Governance Framework and therefore represents an important contribution to the evidence trail in support of the Annual Governance Statement “
The above basic meeting framework can be amended to consider issues raised by Members and referrals from Council/Committee. There will also be regular awareness training to enable Members to keep abreast of developments
TERMS OF REFERENCE
Audit Activity
• To consider the Annual Internal Audit Report and opinion, and a summary of Internal Audit activity (actual and proposed) and assess the level of assurance it can give over the Council’s corporate governance arrangements
• To consider summaries of Internal Audit reports
• To consider reports on the management and performance of Internal Audit including benchmarking results
• To consider reports on agreed recommendations not implemented within agreed timescales
• To consider the Audit Commission Annual Audit & Inspection Letter and Annual Governance Report together with any other reports and recommend for adoption by Council
V 4.0 080310 2 • To monitor compliance with the Council’s Treasury Management Strategy and Statement and to receive quarterly updates from the Chief Finance Officer on investment performance
• To consider specific reports as agreed with external audit
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
AppA Terms of ReferenceReport | 3 pages | DownloadRead as text |
PDF |
Audit Committee: Terms of Reference 2010/11:Report | 5 pages | Download |
Follow Audit and Governance Committee at East Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | 2026/27 Q1 Treasury UpdateThat the report be noted. | Noted | Open |
| 9 Sep 2026 | Q1 Risk report 2026/27That the Q1 Risk Report - 2026/27 Report be noted. | Noted | Open |
| 9 Sep 2026 | Local Code of Corporate GovernanceThat the updated Local Code of Corporate Governance be approved. | Approved | Open |
| 9 Sep 2026 | Audit & Governance Committee Annual Report 2025/26That the Audit and Governance Committee's Annual Report 2025/26 be approved and presented to Full Council in October ... | Approved | Open |
| 9 Sep 2026 | Annual Governance Statement 2025/26That the draft Annual Governance Statement 2025/26 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.