Resolved
RESOLVED That the Risk Management Position Statement for the first quarter of 2011/12 be received by the Audit Committee, and comments made referred to the Executive Board for consideration.
Audit and Governance Committee decided this item on Wednesday 15 June 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the Risk Management Position Statement for the first quarter of 2011/12 be received by the Audit Committee, and comments made referred to the Executive Board for consideration.
It is recommended that Audit Committee: -
• Reviews the Position Statement and refers its views to Executive Board
REASON: To ensure the Council’s risk management arrangements remain fit-for-purpose
This report has been prepared by:
Alison Penn – Assistant Director - Tel: 01507 329196 e-mail: [email protected]
This report was prepared after consultation with:
Management Team
This report is number 1 in a series of 4.
This report has been signed off by: Chief Executive
The following policies form a context to this report:
Strategy for the Management of Risk
This report is not a key decision included in the Forward Plan.
LIST OF BACKGROUND PAPERS AS REQUIRED BY LAW (papers relied on to write the report but which are not published and do not contain exempt information)
1. Risk Management Register
2. Strategy for the Management of Risk - January 2005
OTHER HELPFUL PAPERS
N/A
Local Government (Access to Information Act) 1985
Is the report Exempt –No
Please contact the person who has written this report or Richard Garbutt Tel. No. 01507 329557 e-mail: [email protected] if you want more information about this report or the background papers.
1.0INTRODUCTION 1.1. Executive Board is charged under the Council’s Constitution with reviewing the effectiveness of risk management and receives a quarterly position statement for this purpose culminating in an overall opinion in the Annual Governance Statement for the previous financial year.
2.0BACKGROUND 2.1. The terms of reference of the Audit Committee include – “To monitor the effective development and operation of risk management and corporate governance in the Council”. Audit Committee therefore provides the means of ensuring a more detailed examination of the Position Statement and an opportunity to challenge its contents before recommending it to Executive Board for adoption.
3.0SUBJECT INFORMATION AND ISSUES/FACTS AND FIGURES 3.1. Strategic Risk Register
3.1.2 The Strategic Risk Register (Appendix A) and the Strategic Risk Register for ELDC’s Business Relationship with CPBS (Appendix B) were formally reviewed by Senior Management Team May 2011.
3.1.3 For the Strategic Risk Register, there are 10 high risks, and 3 medium risks
3.1.4 For the Strategic Risk Register for ELDC’s Business Relationship with CPBS there are 2 high risks, 7 medium risks and 3 low risks. The low risk will be considered for stand down during the next quarter should nothing change.
3.2Business Risk Registers
3.2.1 The quarterly review of individual Business Risk Registers by Business Managers is monitored by the Performance Manager, and any extreme or high risks identified in operational risk registers will be assessed and considered for escalation up to the strategic risk register if necessary.
3.3Project Risk Registers
Many projects in the original programme are either complete or nearing completion. New projects initiated to support the revised corporate strategy will require new individual risk registers. Progress is reported to Senior Management Team in the Performance Management Framework.
Business Continuity Management
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MSO Risk Register (Excel) June 2011 App BAppendix | 13 pages | Download |
PDF |
Risk Management Position Statement: First Quarter 2011/12:Report | 5 pages | DownloadRead as text |
PDF |
Strategic Risk Register (Excel) June 2011 App AAppendix | 14 pages | Download |
Follow Audit and Governance Committee at East Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | 2026/27 Q1 Treasury UpdateThat the report be noted. | Noted | Open |
| 9 Sep 2026 | Q1 Risk report 2026/27That the Q1 Risk Report - 2026/27 Report be noted. | Noted | Open |
| 9 Sep 2026 | Local Code of Corporate GovernanceThat the updated Local Code of Corporate Governance be approved. | Approved | Open |
| 9 Sep 2026 | Audit & Governance Committee Annual Report 2025/26That the Audit and Governance Committee's Annual Report 2025/26 be approved and presented to Full Council in October ... | Approved | Open |
| 9 Sep 2026 | Annual Governance Statement 2025/26That the draft Annual Governance Statement 2025/26 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.