CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
East Lindsey District Council
Planning Committee, Thursday 12 January 2012 at 2.00pm

S/204/01737/11

Agreed Planning 3 papers

Planning Committee agreed this item on Thursday 12 January 2012. Below is the council's own wording, with the papers it was decided on.

Item114

Resolved

Decision Notice had not yet been despatched and in light of the fact that letters had been sent to the applicant, the objector and all other interested parties inviting speakers on the application and not limiting the basis on which they could speak or detailing the reason why the matter was to return to committee, it had been agreed that the application would be reconsidered from the start, affording both the objector and the applicant the opportunity to speak. Concerns were expressed with regard to predetermination, with Members having once taken the decision to refuse the application. However, the Legal Advisor explained that the matter should receive a fair hearing, as was the public expectation resulting from the letter from the Planning Department and it was important to be fair and equitable to all attendees. Members agreed to continue, but objected most strongly to the situation. [name removed] spoke against the application. [name removed] spoke in support of the application. Members received an application for the siting of a 10kw wind turbine with an overall height of 21.4 metres, construction of a concrete foundation base and provision of underground cable which is an amendment to that previously approved under planning application reference no. S/204/2761/09 in accordance with the additional plans received by the Local Planning Authority on the 3rd October 2011 at Inchmarlo , Main Road, Keal Cotes. The application had initially been referred to the Planning Committee on 15 th December 2011, as it sought to change the type and increase the overall height of a turbine previously approved by Members at the Meeting held on 18 th February 2010 (S/204/2761/09). At that Meeting, Members determined to refuse the application whereby ... view the full minutes text for item 114.
Word for word from the decision East Lindsey published for this meeting. Source: democracy.e-lindsey.gov.uk

Follow this further

Built from East Lindsey's papers

What the report saysPro

Report to Planning Committee, 10 pages

Consultation

4.1Set out below are the consultation responses that have been received on this application. These responses may be summarised and full copies are available for inspection separately. Some of the comments made may not constitute material planning considerations.

Publicity

4.2The application has been advertised by means of site notice and neighbour notification.

Consultees

4.3WEST KEAL PARISH COUNCIL - The Parish Council met last night and resolved to OBJECT to the above application on the following grounds:- 1) Visual impact. The turbine, once constructed, will be well above the tree line and in close proximity to residential properties. 2) Distraction to motorists and nearby residents. The human eye is sensitive to movement in its peripheral vision. When viewing the landscape a single rotating propeller type turbine will force the viewer to it when it is rotating.

4.4LINCOLNSHIRE COUNTY COUNCIL AS HIGHWAY AUTHORITY - The proposed development will not be detrimental to highway safety or traffic capacity.

4.5REGULATORY SERVICES DEPARTMENT - Environmental Protection - Please condition that the noise emission from the turbine must be no greater than 35dB LA90,10min up to wind speeds of 10m/s at 10m height.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
(12) S-204-01737-11Report 10 pages DownloadRead as text
PDF
(12a) APPENDIX A: 1737.11Appendix 1 pages Download
PDF
S/204/01737/11:Report 1 pages Download

At this meeting

Whole meeting

More from East Lindsey Planning Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Tree Preservation Order: 137, Eastgate, Louth (105.36)That 137 Eastgate, Louth (105.36) Tree Preservation Order be confirmed (made permanent). Decided Open
2 Sep 2026 Tree Preservation Order: Land adjacent 116C Horncastle Road, Roughton Moor (215.31)That land adjacent to 116C Horncastle Road, Roughton Moor (215.31) Tree Preservation Order be confirmed (made permane... Decided Open
2 Sep 2026 00489/26/fulThat the application be approved. Approved Open
2 Jul 2026 03860/25/fulThat this Council resolve to grant planning permission with the application being referred to the Secretary of State ... Decided Open
20 May 2026 Election of ChairmanThat Councillor Stephen Eyre be elected Chairman of the Planning Committee for the Council year 2026/27. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies