Resolved
RESOLVED That the amendments to the Capital Programme as recommended by the Executive Board on 14 February 2012 and the revised 2011/12 Capital Programme of £5,407,947 be approved.
Council approved this item on Wednesday 29 February 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the amendments to the Capital Programme as recommended by the Executive Board on 14 February 2012 and the revised 2011/12 Capital Programme of £5,407,947 be approved.
This report considers a number of amendments to the Capital Programme based on recommendations from Executive Board. Council are asked to approve these amendments and the revised capital programme for 2011/12.
The amendments are as follows: 1. Solar PV Systems – This scheme is now estimated at a reduced scheme cost. The capital budget is reduced from £498,000 to £400,000. 2. Refurbishment and other works at the Embassy (new projects) - the installation of new digital equipment (£19,000) and capital refurbishment work (£40,000). 3. The budget for general flood works was reduced in November from £100,000 to £60,000 based on an assessment of the work to be undertaken in the financial year; however a review of required works before the year end has required the reinstatement of the full £100,000 budget. 4. Investment in improvement work to the Skegness Foreshore was identified in the last council report, to be funded from existing and new resources. The required allocation between capital and revenue had not been determined at that time. Based on an examination of the work to be undertaken the new capital element is estimated to be £164,900 (new project) with the remainder of the new resources, £205,650, allocated to revenue expenditure. 5. Car Park machines – an additional £24,500 is to be spent to enable the new, and some existing, car park machines to be GPRS enabled (revised budget of £134,750). 6. The Council has been allocated by the Government an additional £120,355 in grant funding for Disabled Facility Grants for the 2011/12 financial year (revised budget of £1,396,355).
The revisions to the 2011/12 capital programme and the associated funding are detailed in the table below, at section 3 of the report and at Appendix 1. The amendments require an increase in the 2011/12 programme of £310,755 to £5,407,947. Recommendation
That Council approves the amendments to the Capital Programme as recommended by the Executive Board on 14 February 2012 and the revised 2011/12 capital Programme of £5,407,947.
The amendments are summarised below.
Capital Programme 2011/12 Expenditure: Variation summary £
Approved Budget (at Council 23 November 5,097,192 2011) Solar PV Systems (reduced capital cost) (98,000) Embassy Theatre Digital equipment 19,000 Embassy Theatre Refurbishment 40,000 Annual General provision for Flood Works 40,000 Skegness Foreshore Improvements 164,900 Car park machines GPRS enabled 24,500 Disabled Facility Grants 120,355 Revised Capital Programme 5,407,947
Budget increase 310,755
Capital Programme 2011/12 Funding: Variation summary Approved Revised Variance Budget Budget £ £ £ Grants and 1,318,607 1,438,962 120,355 Contributions Revenue 801,977 933,377 131,400 Reserves 250,000 269,000 19,000 Capital Receipts 2,726,608 2,766,608 40,000 Total 5,097,192 5,407,947 310,755
REASON: In line with the Council’s Constitution Council must approve all required amendments to the Council’s Capital Programme.
This report has been prepared by:
Jane Crosby, Strategic Business Partner Compass Point Business Services - Tel 01507 601111 x 567, [email removed] This report was prepared after consultation with: Executive Board
This report is number 1 in a series of 1.
This report has been signed off by:
Peter Linfield, Deputy Section 151 Officer
The following policies form a context to this report:
i) Corporate Strategy 2010/11 to 2013/14 ii) Carbon Management Plan 2009 iii) Capital Strategy iv) Medium Term Financial Strategy
This report is a key decision included in the Forward Plan.
LIST OF BACKGROUND PAPERS AS REQUIRED BY LAW (papers relied on to write the report but which are not published and do not contain exempt information)
1. None
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Amendments to the Capital Programme 2012:Report | 7 pages | DownloadRead as text |
PDF |
2011 12 capital programme: Council 2012Appendix 1 | 2 pages | Download |
Follow Council at East Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 May 2026 | Election of Chairman of the CouncilRESOLVED That Councillor Neil Jones be elected as Chairman of the Council for the Council year 2026/27. COUNCILLOR NE... | Decided | Open |
| 20 May 2026 | Election of Vice-Chairman of the CouncilRESOLVED That Councillor Jill Makinson-Sanders be elected as Vice-Chairman of the Council for the Council year 2026/27. | Decided | Open |
| 20 May 2026 | Democratic Arrangements 2026/27RESOLVED 1. That the establishment of its committees for the municipal year 2026/27 including the allocation of seats... | Approved | Open |
| 20 May 2026 | Appointments to Outside BodiesRESOLVED That Members be appointed to the various Bodies detailed below. Outside Body Appointed 2025/26 Nominations 2... | Decided | Open |
| 20 May 2026 | South & East Lincolnshire Councils Partnership Performance Report and Memorandum of Agreement (MOA)RESOLVED That the content of this report in respect of the progress of the South & East Lincolnshire Councils Partner... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.