Resolved
RESOLVED That the Internal Audit Plan 2012/13 be approved
Audit and Governance Committee approved this item on Wednesday 28 March 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the Internal Audit Plan 2012/13 be approved
This report sets out the proposed work of Internal Audit for 2012/13. The plan is based on our Internal Audit Strategy which has been agreed with the Deputy Chief Executive (the Councils Section 151 Officer).
At the heart of the strategy is our ‘Assurance Map’. This helps focus our work plans on risks that matter – the make or break risks that affect the successful delivery of services and strategic objectives. It also recognises the importance of critical business systems that support successful delivery and ‘protect the business’.
Our aim is to align our work with other assurance functions, particularly performance and risk management and look at different ways of leveraging assurance to help us to maximise the best use of the Internal Audit resource and other assurance functions in the Council.
Our Assurance Map can be linked back to:
§ business plan objectives & priorities; § service plans; § critical systems; § the strategic risk register; § change management programme, § emerging risks, and § the assurance framework. It has been developed through our understanding of the Council business, reference to the risk management arrangements in the Council and by gathering information from Senior Management. Recommendations:
It is recommended that Members consider and approve the Internal Audit Plan 2012/13, subject to any agreed changes. This report has been prepared by:
Lucy Pledge – Tel 01522 553692 e-mail: [email protected] Alastair Simson - Tel: 01507 601111 – ext 228 e-mail: [email protected]
This report was prepared after consultation with:
Alison Penn and Rob Barlow
This report is number 3 in a series of 3
This report has been signed off by: Alison Penn
The following policies form a context to this report:
Code of Corporate Governance
This report is not a key decision included in the Forward Plan.
LIST OF BACKGROUND PAPERS AS REQUIRED BY LAW (papers relied on to write the report but which are not published and do not contain exempt information)
None
OTHER HELPFUL PAPERS (papers which the report author considers might be helpful – this might include published material)
1. Internal Audit Charter
2. Annual Governance Statement
Local Government (Access to Information Act) 1985
Is the report Exempt – No
Please contact the person who has written this report or Alison Penn Tel. No. 01507 601111 ext 3414 e-mail: [email protected] if you want more information about this report or the background papers.
1.0INTRODUCTION
1.1This plan sets out the proposed work of Internal Audit for 2012/13. The plan is based on our Internal Audit Strategy which has been agreed with the Deputy Chief Executive (the Councils Section 151 Officer) of which the key elements are provided below.
Our role
1.2Our primary objective is an assurance function that provides an independent and objective opinion on the councils control environment - we focus our work on the Councils strategic risks, critical systems and key priorities.
1.3Delivery of the Internal Audit work plan enables the Head of Audit to produce the annual audit opinion which objectively examines, evaluates and reports on the adequacy of the control environment as a contribution to the proper, economic, efficient and effective use of resources.
Our effectiveness is evaluated by: § Senior Managers, including the Section 151 Officer of the Council § The Audit and Governance Committee, and § External Audit 2.0. BACKGROUND
How we chose what to look at (Audit Strategy)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Draft Internal Audit Plan 2012/13:Report | 12 pages | DownloadRead as text |
Follow Audit and Governance Committee at East Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | 2026/27 Q1 Treasury UpdateThat the report be noted. | Noted | Open |
| 9 Sep 2026 | Q1 Risk report 2026/27That the Q1 Risk Report - 2026/27 Report be noted. | Noted | Open |
| 9 Sep 2026 | Local Code of Corporate GovernanceThat the updated Local Code of Corporate Governance be approved. | Approved | Open |
| 9 Sep 2026 | Audit & Governance Committee Annual Report 2025/26That the Audit and Governance Committee's Annual Report 2025/26 be approved and presented to Full Council in October ... | Approved | Open |
| 9 Sep 2026 | Annual Governance Statement 2025/26That the draft Annual Governance Statement 2025/26 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.